Loading...
CM-07-03-044CITY OF ROUND ROCK CONSTRUCTION CHANGE ORDER DEPARTMENT: Public Works PROJECT: Dell East Campus Channel Repair ORIGINAL CONTRACT PRICE: PREVIOUS CHANGE ORDERS: THIS CHANGE ORDER: CHANGE ORDERS TO DATE: $166,385.00 $0.00 $24,179.50 $24,179.50 ITEM # 1 2 3 4 5 6 DESCRIPTION OF CHANGES 2 -foot Gravel Bottom Add'I Excavation Concrete Steel Increase Concrete Apron Area Decrease 9" Gabion Mattress Spillway Apron Concrete Thickness Increase PE= CHANGE DATA PREPARED BY: Cynthia . Lancas er, P.E. ENGINEER UNIT SF CY SF SF SF SF QTY. 4590 80 12960 2200 2200 1740 PAGE 1 OF 2 DATE: CHANGE ORDER NO: 1 JUSTIFICATION: design changes due to unsuitable subgrade materials & excessive groundwater seepage; increased borrow due to voids under concrete UNIT PRICE $2.95 $20.00 $0.65 ($7.50) $6.00 $2.25 TOTAL: AMOUNT $13,540.50 $1,600.00 $8,424.00 ($16,500.00) $13,200.00 $3,915.00 $24,179.50 ADDED DAYS CALENDAR/ WORKING 0 3/13/2007 PERCENT OF ORIGINAL CONTRACT PRICE Manley Contracting NAME OF CONTRACTOR SIGNATUR DATE THIS CHANGE ORDER: PREVIOUS CHANGE ORDER: TOTAL % CHANGE: 14.53% ORIGINAL CONTRACT PRICE PLUS 14.53% 0 PRINT NAME/TITLE: cc (1.(i gyp!- ` 4-lhaffa CHANGE ORDERS: $190,564.50 APPROVED: 3 -a10 -a061 ITY OF ROUND ROCK J'Culte. 5 R. u use, P. € . constco2lforms6/Ik Windy Park Subdivision Manville Water Supply Corporation Property Dell East Subdivision Property ' POUND IROCK TEXAS Proposed Drainage Channel Improvements Exibit A to Cost Participation Agreement between the City of Round Rock and Dell USA L.P. N s «�" .h.et o..ye Ryan a..r6F Sergio M • � 09/26/06 DATE: March 19, 2007 SUBJECT: City Manager - March 23, 2007 ITEM: Action authorizing the City Manager to execute Change Order # 1 with Manley Contracting for Dell East Campus Channel Repair. Department: Engineering and Development Services Staff Person: Danny Halden, P.E. Justification: The original contract with Manley Contracting was approved by the City Council in December of 2006 for $166,385.00. Due to unforeseen circumstances, the original scope of services has changed, and Change Order # 1 is requesting an increase of $24,179.50 bringing the total contract amount to $190,564.50. Funding: Cost: $24,179.50 Source of funds: 2002 G.O. Bonds Outside Resources: Alan Plummer Associates, Inc. Background Information: Upon excavation of the deteriorated concrete channel lining, the sub -grade was found to be extremely poor and groundwater seepage has created constructability issues. This change order will provide additional measures to stabilize the channel bottom, to control ground water, and to increase the structural capacity of the new channel lining. This change order also modifies the spillway area of the abutting Dell pond that discharges at the end of the channel. Dell and the City of Round Rock are funding these channel improvements with each paying fifty percent (50%) of the construction costs. Public Comment: NA Blue Sheet Format Updated 01/20/04