CM-07-04-057CITY OF ROUND ROCK
CONSTRUCTION CHANGE ORDER
DEPARTMENT: Public Works
PROJECT: McNutt Creek Wastewater Interceptor
Phase I
ORIGINAL CONTRACT PRICE:
PREVIOUS CHANGE ORDERS:
THIS CHANGE ORDER:
CHANGE ORDERS TO DATE:
PAGE 1 OF 1
DATE: 3/29/2007
CHANGE ORDER NO: 2
JUSTIFICATION: SEE ATTACHED
$10,128,830.00 CHANGE ORDER SUPPLEMENT
$23,004.52
$17,440.03
$40,444.55
CHANGE DATA
ITEM #
DESCRIPTION OF
CHANGES
UNIT
QTY.
UNIT
PRICE
AMOUNT
ADDED DAYS
CALENDAR/
WORKING
CP -8
Additional days due to Ice Storm
N/A
N/A
$0.00
3
CP -9
Production lost due to encountering soft
rock material
LS
1
$17,440.03
$17,440.03
0
CP -10
Additional days due to Toss of electrical
power
N/A
N/A
$0.00
2
TOTAL:
$17,440.03
5
PREPARED BY: D.
EN (NEER
Mole Kassouf Joint Venture
Z8 MAR O'7
DATE
BY:
TITLE:
CONTRACTOR
c/ /11.0i.
APPROVED:
zra,me5 R. Kt u.5e) P, E.
CITY OF ROUND ROCK e.44 m constco2lforms6/Ik
C V o -051
PERCENT OF ORIGINAL CONTRACT PRICE
THIS CHANGE ORDER: 0.17%
PREVIOUS CHANGE ORDER: 0.23%
TOTAL % CHANGE: 0.40%
ORIGINAL CONTRACT PRICE PLUS
CHANGE ORDERS: $10,169,274.55
CITY OF ROUND ROCK
CHANGE ORDER SUPPLEMENT
Project: McNutt Creek Wastewater Interceptor— Phase I
Change Order No. 2
Item #CP -8: Ice storms in the area prevented workers from arriving to the jobsite on
January 16, 17 and 18, 2007. This item extends the contract time by 3 calendar days.
Item # CP -9: The tunnel boring machine encountered rock that was substantially softer
than normal on January 9 and January 22, 2007, causing the tunnel excavation to
progress at a much slower rate. This item is for monetary compensation for lost
production for these shifts.
Item # CP -10: This item extends the contract by 2 calendar days due to electrical
outages on the jobsite encountered on November 10, 2006
M
1 of 1
•
Mole Kassouf Joint Venture
Mole Constructors, Inc., Kassouf Co., Inc. and Murray Hill Construction, Inc.
29100 Hall Street
Solon, Ohio 44139
Phone 440 248-0616 Fax 440 248-8132
January 23, 2007
Page 1 of 1
K. Friese & Associates
7600 Burnet Road, Suite 290
Austin, Texas 78757
Attn: Mr. Tom Owens, P.E.
Re.: McNutt Creek Wastewater Interceptor Project, Phase 1
Delays - Weather related
Letter No. 025
Dear Mr. Owens:
This letter shall serve to notify the Engineer that we have sustained weather
related delays associated with the recent ice event. Given the hazardous road
conditions caused by the icing, we were unable to work on January 16th and
17th. Additionally, we lost over half of the day on the 18th.
We respectfully request that your team investigate this matter and issue a 3 work
day time extension for the impact. Should you have any questions and or
comments regarding this subject, please contact me posthaste.
Very truly yours,
Mole Kassouf Joint Venture
Rod R. Shoulders
Vice President, MCI
Cc: File
M -K JV Texas Field Office
J. Bell, City of Round Rock
DATE April 9, 2007
SUBJECT: City Manager Approval - April 13, 2007
ITEM: Consider authorizing the City Manager to execute approval of Change
Order No. 2 with Mole-Kassouf Joint Venture for the McNutt Creek
Wastewater Interceptor Project.
Department: Water and Wastewater Utilities
Staff Person: Michael Thane, Utilities Director
Justification:
Mole-Kassouf Joint Venture is currently under contract for the construction of the McNutt
Creek Wastewater Interceptor. Change Order No. 2 includes the following: production lost
due to encountering soft rock material during tunneling and additional days to the contract
due to ice storm in January 2007 and due to loss of electrical power in November 2006.
The original contract amount plus Change Order No. 1 is $10,151,834.52. Change Order
No. 2 will add $17,440.03 to the contract for a new contract amount of $10,169,274.55.
Manz
Cost: $17,440.03
Source of funds: Capital Projects Funds (Utility Fund)
Outside Resources: K. Friese & Associates (Design Engineer)
Mole Kassouf Joint Venture (Contractor)
Background Information;
The project scope of work is to construct approximately 8,545 feet of 48" wastewater
interceptor from the existing Brushy Creek Regional Wastewater Plant located on the
eastern side of the City of Round Rock, and extend north-easterly to a certain point just
north of the McNutt Creek. Project is scheduled to be completed by December 2007.