CM-07-04-064CITY OF ROUND ROCK PUBLIC WORKS
CONSTRUCTION CHANGE ORDER
Project: Amphitheater at the Baca Sr. Activity Center Change Order No.: 1
Address: 301 W. Bagdad Initiation Date:
Round Rock, TX Contract For: New Construction
To: Fazzone Construction Company, Inc. Contract Date: 2/22/2007-5/18/2007
2008 Windy Terrace
Cedar Park, TX 78613
(Contractor)
The Contract is changed as follows:
1. Install vegetative filter strip & level spreader per Civil Enginnering plans
2. Provide and Install Hydrel # 4650 light fixtures
Summary
The original (Contract Sum) was: ..... ........... ........... .............. ......
Net change by previous authorized Change Orders. $
The (Contract Sum) prior to this Change Order was.
The (Contract Sum) will be (increased) (unchanged) by this Change Order
The new (Contract Sum) including this Change Order will be. . $
The Contract time will be (unchanged) by ( 0) days.
The Date of Substantial Completion as of the date of this Change Order therefore is:
225,000.00
225,000.00
1,670.83
226,670.83
18 -May -07
Changes included in the summary above (do) (do not) include modifications which have been authorized by Construction
Change Directive(s).
Moman Architects
Architect
Fazzone Construction Co., Inc.
Contractor
309 W. Main Street, Suite 120 2008 Windy Terrace
Address
City of Round Rock
Owner
221 East Main Street
Address Address
Round Rock, Texas 78664 Cedar
By
r1 rk Te 178613 ' ound Rock Texas 78664
N .
Matt Webb
N•I7•o7
Date
Joe Fazzone
Date
e.r�to1-off o(04
CO-Architects.xls/Admintfonns
James R. Nuse, P.E
Date
FAllONE
Apri113, 2007
Change Order Proposal
Response
To: From:
Moman Architects Inc. Fazzone Construction Inc.
309 West Main Street Suite 120 2006 Windy Terrace, Ste. B
Round Rock, Texas Cedar Park, TX. 78613
(512) 733-1150 Fax: (512) 733-8411 (512) 331-4484 Fax: (512) 335-3711
CO #
Description
Contractor Response
PR# 001
Exhibit #1 Vegetative filter strip & level spreader
Will install per plan for $763.83
Exhibit #2 Hydrel #4650 light fixtures provide and install
Sub price for work $907.00
Contract price increase
$1670.83
Comments:
Sincerely,
Paul Whetstone
2008 Windy Terrace • Cedar Park, TX. 78613
• (512) 331-4484 Fax: (512) 335-3711
DATE: April 20, 2007
SUBJECT: City Manager - April 27, 2007
ITEM: Action authorizing the City Manager to execute change order No. 1
with Fazzone Construction Inc. for the Amphitheater at the Baca
Activity Center.
Department: Engineering and Development Services
Staff Person: Tom Word, Chief pf P.W. Operations
Larry Madsen, Construction Manager
Justification:
TCEQ upon review of plans required a vegetative strip to be installed on the back side of the
concrete slab for the Amphitheater. The cost for this is $763.83. Stage Lighting has been
revised to provide the best lighting for events. In the original plan the rough in was laid out
but not the actual light fixtures specified. This change order provides for the light fixtures
that are to be installed at the stage area. The cost for this is $907.00.
Funding:
Cost: $1,670.83
Source of funds: GO Bond Interest Money
Outside Resources: N/A
Background Information: N/A
Public Comment: N/A
Blue Sheet Format
Updated 01/20/04