CM-07-05-084CITY OF ROUND ROCK PUBLIC WORKS
CONSTRUCTION CHANGE ORDER
Project: Amphitheater at the Baca Sr. Activity Center
Address: 301 W. Bagdad
Change Order No.: 2
Initiation Date: 4/30/2007
Round Rock, TX Contract For: New Construction
To: Fazzone Construction Company, Inc. Contract Date: 2/22/2007-5/18/2007
2008 Windy Terrace
Cedar Park, TX 78613
(Contractor)
The Contract is changed as follows:
1. Install two additional steel tension rods to the back portion of the roof per direction of Structural Engineer
Summary
The original (Contract Sum) was. . $ 225,000.00
Net change by previous authorized Change Orders. $ 1,670.63
The (Contract Sum) prior to this Change Order was. $ 226,670.83
$ 900.00
$ 227,570.83
The (Contract Sum) will be (increased) (unchanged) by this Change Order
The new (Contract Sum) including this Change Order will be:...
The Contract time will be (unchanged) by ( 0) days.
The Date of Substantial Completion as of the date of this Change Order therefore is:
18 -May -07
Changes included in the summary above (do) (do not) include modifications which have been authorized by Construction
Change Directive(s).
Moman Architects
Fazzone Construction Co., Inc. City of Round Rock
Archdect Contractor
309 W. Main Street, Suite 120 2008 Windy Terrace
Address
Round Rock, Texas 78664
aidr
Address
Cedar P -J Texas :613
Owner
221 East Main Street
Address
Round Rock, Texas 78664
By
Matt Webb Joe Fazzone
4.3o.o7 s12-ilGri
Date
Date
Cm -o1 -o5-084
CO-Architectsjds/Adminlfonns
5-1 I -a 00 7
Date
FAllONE
April 20, 2007
Change Order Proposal
Response
To: From:
Moman Architects Inc. Fazzone Construction Inc.
309 West Main Street Suite 120 2006 Windy Terrace, Ste. B
Round Rock, Texas Cedar Park, TX. 78613
(512) 733-1150 Fax: (512) 733-8411 (512) 331-4484 Fax: (512) 335-3711
CO #
Description
Contractor Response
#002
Reference RFI #5 Tension Rod quantity rear section of roof.
S&S Steel will manufacture the additional
tension rods and install for the price
Engineer specified that this roof section needed 4 tension rods
change listed below.
but only 2 were call out in the plan.
Contract price increase
$ 900.00
Comments:
Sincerely,
Paul Whetstone
2008 Windy Terrace Cedar Park, TX. 78613 • (512) 331-4484 Fax: (512) 335-3711
FAZzONE
nstruction
ompany
April 17, 2007
Request for Information # 05
To:
Moman Architects Inc.
309 West Main Street Suite 120
Round Rock, Texas 78664
Owner:
City of Round Rock
2008 Enterprise Drive
Round Rock, Texas 78664
Contractor:
Fazzone Construction Co., Inc.
2006 Windy Terrace, Ste. B
Cedar Park, TX. 78613
(512) 331-4484 Fax: (512) 335-3711
Project:
Amphitheater at the Baca Sr. Activity Center
301 West Bagdad
Round Rock, Texas
1106159-00
SUBJECT:
Tension rod support on near roof section
SPECIFICATION
SECTION:
DRAWING:
Pian S-20
LOCATION:
Roof
ROOM #:
OTHER:
INFORMATION REQUESTED:
The steel erector asked do the two tension rods at the center of the beam provide enough support for the roof. There Is a 13' span out to
the edge of the roof from each rod attachment to the beam. The erectors concern was the amount of vertical lift at the side edges of the
roof. WIII this be lessened after all welds are In place and will the roof deck help to stlffen out the roof to minimize the vertical IIft7 It will
take 7 to 10 days to manufacture additional tension rods.
REPLY: THE BACK TUBE SHALL HAVE FOUR TENSION RODS LIKE THE FRONT.
DATE: May 7, 2007
SUBJECT: City Manager - May 11, 2007
ITEM: Action authorizing the City Manager to execute change order No. 2
with Fazzone Construction Inc. for the Amphitheater at the Baca Sr.
Activity Center.
Department: Engineering and Development Services
Staff Person: Tom Word, Chief pf P.W. Operations
Larry Madsen, Construction Manager
Justification:
Per direction of Larry Fisher, Structural Engineer, two additional tension rods are needed for
roof support on the Amphitheater Project.
Funding:
Cost: $900.00
Source of funds: GO Bond Interest Money
Outside Resources: N/A
Background Information: N/A
Public Comment: N/A