CM-07-05-084CITY OF ROUND ROCK PUBLIC WORKS CONSTRUCTION CHANGE ORDER Project: Amphitheater at the Baca Sr. Activity Center Address: 301 W. Bagdad Change Order No.: 2 Initiation Date: 4/30/2007 Round Rock, TX Contract For: New Construction To: Fazzone Construction Company, Inc. Contract Date: 2/22/2007-5/18/2007 2008 Windy Terrace Cedar Park, TX 78613 (Contractor) The Contract is changed as follows: 1. Install two additional steel tension rods to the back portion of the roof per direction of Structural Engineer Summary The original (Contract Sum) was. . $ 225,000.00 Net change by previous authorized Change Orders. $ 1,670.63 The (Contract Sum) prior to this Change Order was. $ 226,670.83 $ 900.00 $ 227,570.83 The (Contract Sum) will be (increased) (unchanged) by this Change Order The new (Contract Sum) including this Change Order will be:... The Contract time will be (unchanged) by ( 0) days. The Date of Substantial Completion as of the date of this Change Order therefore is: 18 -May -07 Changes included in the summary above (do) (do not) include modifications which have been authorized by Construction Change Directive(s). Moman Architects Fazzone Construction Co., Inc. City of Round Rock Archdect Contractor 309 W. Main Street, Suite 120 2008 Windy Terrace Address Round Rock, Texas 78664 aidr Address Cedar P -J Texas :613 Owner 221 East Main Street Address Round Rock, Texas 78664 By Matt Webb Joe Fazzone 4.3o.o7 s12-ilGri Date Date Cm -o1 -o5-084 CO-Architectsjds/Adminlfonns 5-1 I -a 00 7 Date FAllONE April 20, 2007 Change Order Proposal Response To: From: Moman Architects Inc. Fazzone Construction Inc. 309 West Main Street Suite 120 2006 Windy Terrace, Ste. B Round Rock, Texas Cedar Park, TX. 78613 (512) 733-1150 Fax: (512) 733-8411 (512) 331-4484 Fax: (512) 335-3711 CO # Description Contractor Response #002 Reference RFI #5 Tension Rod quantity rear section of roof. S&S Steel will manufacture the additional tension rods and install for the price Engineer specified that this roof section needed 4 tension rods change listed below. but only 2 were call out in the plan. Contract price increase $ 900.00 Comments: Sincerely, Paul Whetstone 2008 Windy Terrace Cedar Park, TX. 78613 • (512) 331-4484 Fax: (512) 335-3711 FAZzONE nstruction ompany April 17, 2007 Request for Information # 05 To: Moman Architects Inc. 309 West Main Street Suite 120 Round Rock, Texas 78664 Owner: City of Round Rock 2008 Enterprise Drive Round Rock, Texas 78664 Contractor: Fazzone Construction Co., Inc. 2006 Windy Terrace, Ste. B Cedar Park, TX. 78613 (512) 331-4484 Fax: (512) 335-3711 Project: Amphitheater at the Baca Sr. Activity Center 301 West Bagdad Round Rock, Texas 1106159-00 SUBJECT: Tension rod support on near roof section SPECIFICATION SECTION: DRAWING: Pian S-20 LOCATION: Roof ROOM #: OTHER: INFORMATION REQUESTED: The steel erector asked do the two tension rods at the center of the beam provide enough support for the roof. There Is a 13' span out to the edge of the roof from each rod attachment to the beam. The erectors concern was the amount of vertical lift at the side edges of the roof. WIII this be lessened after all welds are In place and will the roof deck help to stlffen out the roof to minimize the vertical IIft7 It will take 7 to 10 days to manufacture additional tension rods. REPLY: THE BACK TUBE SHALL HAVE FOUR TENSION RODS LIKE THE FRONT. DATE: May 7, 2007 SUBJECT: City Manager - May 11, 2007 ITEM: Action authorizing the City Manager to execute change order No. 2 with Fazzone Construction Inc. for the Amphitheater at the Baca Sr. Activity Center. Department: Engineering and Development Services Staff Person: Tom Word, Chief pf P.W. Operations Larry Madsen, Construction Manager Justification: Per direction of Larry Fisher, Structural Engineer, two additional tension rods are needed for roof support on the Amphitheater Project. Funding: Cost: $900.00 Source of funds: GO Bond Interest Money Outside Resources: N/A Background Information: N/A Public Comment: N/A Blue Sheet Format Updated 01/20/04