Loading...
CM-07-06-096CITY OF ROUND ROCK CONSTRUCTION CHANGE ORDER DEPARTMENT: Transportation Services PROJECT: A. W. Grimes Boulevard Phase I1 CHANGE ORDER NO: 11 JUSTIFICATION: Reference page 2 of 2 Page 1 of 2 DATE: 5/24/2007 ORIGINAL CONTRACT PRICE: PREVIOUS CHANGE ORDERS: THIS CHANGE ORDER: CHANGE ORDERS TO DATE: $4,978,357.76 $846,941.74 $19,754.92 $866,696.66 SI A RE (CONT - OR) PRINTED NAME: Martin Morello DATE TITLE: Project Manager APPROVED: CITY OF RO PERCENT OF ORIGINAL CONTRACT PRICE THIS CHANGE ORDER: $19,754.92 PREVIOUS CHANGE ORDER: $846,941.74 TOTAL % CHANGE TO DATE: 17.41% ORIGINAL CONTRACT PRICE PLUS CHANGE ORDERS: $5,845,054.42 °Ta.Illis Ci1t air ITEM # DESCRIPTION OF CHANGES UNIT QTY. UNIT PRICE _yv,_...._._'-...,-.:.n..,a++w.wx..�.ro...cu+..xw•.+k AMOUNT ADDED DAYS CALENDAR! WORKING ..imvwa...+w+� TRAFFIC CONTROL $0.00 0 TRAFFIC CONTROL REQUIRED FOR MARKING ELIMINATION AND 1 RE -INSTALLATION LS 1 $1,575.00 $1,575.00 2 RIGHT LANE CLOSURE ON A.W.GRIMES $0.00 DELIVERY, INITIAL PLACEMENT AND PICK 2a UP LS 1 $430.00 $430.00 MONTHLY RENTAL RATE FOR SIGNS, BARRICADES AND CHANNELIZERS FOR 2b RIGHT TURN LANE CLOSURE MO 3 $935.00 $2,805.00 MONTHLY RENTAL RATE FOR ONE 2c ARROW BOARD MO 3 $860.00 $2,580.00 PAVEMENT MARKINGS $0.00 1 REFL PAV MRK TY I (W) (8") (SLD) LF 671 $1.95 $1,308.45 2 REFL PAV MRK TY I (W) (241 (SLD) LF 72 $5.25 $378.00 3 REFL PAV MRK TY I (W) (ARROW) EA 4 $105.00 $420.00 4 REFL PAV MRK TY I (W) (WORD) EA 4 $130.00 $520.00 5 REFL PAV MRK TY I (Y) (4") (SLD) LF 424 $0.84 $356.16 6 REFL PAV MRK TY I (Y) (24") (SLD) LF 23 $6.75 $155.25 7 REFL PAV MRK TY II (W) (8") (SLD) LF 671 $0.70 $469.70 8 REFL PAV MRK TY II (W) (12') (SLD) LF 231 $1.50 $346.50 9 REFL PAV MRK TY II (W) (24") (SLD) LF 72 $2.60 $187.20 10 REFL PAV MRK TY II (W) (ARROW) EA 4 $32.00 $128.00 11 REFL PAV MRK TY II (W) (WORD) EA 4 $43.00 $172.00 12 REFL PAV MRK TY II (Y) (41 (SLD) LF 424 $0.48 $203.52 13 REFL PAV MRK TY II (Y) (24") (SLD) LF 23 $3.15 $72.45 14 REFL PAV MRK TY I (W) (12") (SLD) LF 231 $2.60 $600.60 15 RAIS PAV MAKR CL B (REFL) TY II -A -A EA 20 $5.00 $100.00 16 RAIS PAV MAKR CL B (REFL) TY II -C-R EA 68 $5.00 $340.00 17 REFL PAV MRK TY I (W) (4") (SLD) LF 183 $1.33 $243.39 18 REFL PAV MRK TY II (W) (4") (SLD) LF 183 $0.60 $109.80 19 ELIM EXT PAV MRK & MRKR (4") LF 1330 $1.33 $1,768.90 20 ELIM EXT PAV MRK &MRKR (12") LF 200 $3.97 $794.00 21 ELIM EXT PAV MRK & MRKR (24") LF 300 $7.94 $2,382.00 22 ELIM EXT PAV MRK & MRKR (ARROW) EA 4 $112.50 $450.00 23 ELIM EXT PAV MRK & MRKR (WORD) EA 4 $132.25 $529.00 TAPE DOUBLE ARROW, STRAIGHT & 24 RIGHT TURN EA 1 $330.00 $330.00 $0.00 X I. \ _ TOTAL: $19,754.92 0 SI A RE (CONT - OR) PRINTED NAME: Martin Morello DATE TITLE: Project Manager APPROVED: CITY OF RO PERCENT OF ORIGINAL CONTRACT PRICE THIS CHANGE ORDER: $19,754.92 PREVIOUS CHANGE ORDER: $846,941.74 TOTAL % CHANGE TO DATE: 17.41% ORIGINAL CONTRACT PRICE PLUS CHANGE ORDERS: $5,845,054.42 °Ta.Illis Ci1t air 4 CITY OF ROUND ROCK CONSTRUCTION CHANGE ORDER Page 2 of 2 DEPARTMENT: Transportation Services DATE: 5/24/2007 PROJECT: A. W. Grimes Boulevard Phase II CHANGE ORDER NO: 11 JUSTIFICATION: 1 Provide traffic control for the pavement marking elimination and re -installation in accordance with Rodriguez Transportation Group revised contract drawings P.E. Stamped May 3, 2007 at FM1460. 2 Provide lane closure for the right tum lane from A.W. Grimes Blvd onto US79 in accordance with The City of Round Rock directive 3 Provide existing pavement marking elimination and pavement marking installation in accordance with Rodriguez Transportation Group revised contract drawings P.E. Stamped May 3, 2007 at FM1460 m 1 0 3. C CO o co 3� CD o V) r-ci rncn na) c0 CD DATE: May 25, 2007 SUBJECT: City Manager - June 1, 2007 ITEM: Action authorizing the City Manager to execute Change Order #11 with RGM Constructors, L.P. for A.W. Grimes Boulevard Phase II project. Deart pment: Transportation Services Staff Person: Thomas G. Martin, P. E., Director of Transportation Services Justification: In order to provide a safe traffic control and pavement markings for the driving public during the temporary phase of construction on US 79, and to accommodate the opening of A. W. Grimes additional quantities are required for compliance with MUTCD. Funding Cost: Source of Funds: $19,754.92 4B -RR Transportation Development Corporation Original Contract Previous Change Orders Change Order #11 Revised Contract Amount $4,978,357.76 $846,941.74 $19,754.92 $ 5,845054.42 % Change N/A 17.01% 0.40% 17.41% Outside Resources: RGM Constructors, L.P. Background Information: The A.W. Grimes Boulevard Phase II project was awarded to RGM Constructors, L.P., by Council on July 14, 2005. Phase II constructs a six -lane section from US 79 to Lake Creek including curb and gutter, sidewalk, a raised median, drainage and utility improvements, a bridge over Brushy Creek and a crossing under the Union Pacific Railroad. When complete, A.W. Grimes Boulevard will provide the final link for connecting Georgetown, Round Rock and Pflugerville. Public Comment: N/A Blue Sheet Format Updated 01/20/04