CM-07-06-159CITY OF ROCK PUBLIC WORKS
CONSTRUCTION CHANGE ORDER
Project Forest Creek Golf Clubhouse Expansion
Addeees: 99 Twin Ridge Par! way
Change Order No.: 5
Initiation Data: 6M812007
Round Rock, Texas 78864 Contract For: New Construction
To: G. Cnsek, Inc. Contract Date: 11/21/2006 to 4/1/2007
P.O. Box 163764
Austin, Teas 78716
(Contractor)
The Contract Is changed as follows:
hnassee size and horsepower of kitchen ventilation hood
$2,042.96
The original (Contract Sum) was: $ 449,961.59
Net change by previous authorized Grange Orders- $ 97,938.40
The (Contract Sum) prior to this Change Order was- S 547,899.90
The (Contract Sum) will be (increased) by this Change Order $ 2,042.98
The new (Contract Sum) ung this Change Order will be- $ 549,942.88
The Coats -Oaths will be (unchanged) by ( )days:
The Date of SUbefental Como lotion as of the date of this Change Order therefore is:
R. GIM a Associates G. Creek Mc.
Atedastl
P.O. Box 4307
Address
City of Round Rock
Cay.► Omer
P.O. Box 183764
221 East Mein Street
Adams
AAali Maralson Jena* R. Naos, P.E
(0(2_62, 1; C/o 7
.Oat
CxYk%pal- t4Wl
40-9q01)20041
TACLA 022111E
384 Conal Drive
Buda, Texas 78610
To: G Creek Construction
Re.: Forest Creek Cif Coarse
Pro Sharp Ragas
For: ILV.A.C.
Craig R. Briggs
Phone 512) 3122500
Fax 512) 3122514
June 19, 2007
Clump Proposal
Scope of Work:
The requested dons to the kifthen ventilation hood:
Increase physical sine to 4'-0" x 10'-O"
Increase motor horsepower ofKEF-1 & KSF-1
Price Equipment + $ 740.00
ids + $ 355.00
Labor + $ 860.00
Net Add + $1,95510
Standard ExAssisas:
Pi / Fire Protection / Refrigeration / Electrical
Structung Supports / Housekeeping Pads — Poured Concrete
Chases/Fur I
Special Bow Roofing Work
Regulated by The Department et<L ice abig sad itagtelation
P.O. Hex 12157 Asada, Tem 78711 14N -*S34 2
G. Creek Construction
Project: Forest Creek Golf Course
Proposed change as follows:
Increase physical size of Kitchen ventilation hood, and increase in
motor horsepower.
Briggs Mechanical Inc.
Insurance 2%
Bonds 2.5%
$1,955.00
$ 39.10
$ 48.88
Total Change $2,042.98
DATE: June 25, 2007
SUB3ECT: City Manager - June 29, 2007
ITEM: Action requesting City Manager to approve Change Order No. 5 with
G. Creek Construction for the Forest Creek Golf Course Clubhouse
Expansion.
Department: Engineering and Development Services
Staff Person: Tom Word, Chief pf P.W. Operations
Larry Madsen, Construction Manager
3ustification:
Due to specifications of appliances and using the original kitchen vent -a -hood, had to
increase physical size and increase motor horsepower to meet code.
Fundina:
Cost: $2,042.98
Source of funds: Golf Course Construction Fund
Outside Resources: HCE (MEP, Ray Gill Architects
Background Information: N/A
Public Comment: N/A
Blue Sheet Format
Updated 01/20/04