CM-07-08-190CITY OF ROUND ROCK
CONSTRUCTION CHANGE ORDER
Page 1 of 2
DEPARTMENT: Transportation Services DATE: 8/7/2007
PROJECT: A. W. Grimes Boulevard Phase II CHANGE ORDER NO: 12
JUSTIFICATION: Reference page 2 of 2
ORIGINAL CONTRACT PRICE:
PREVIOUS CHANGE ORDERS:
THIS CHANGE ORDER:
CHANGE ORDERS TO DATE:
$4,978,357.76
$866,696.66
$7,020.00
$873,716.66
CHANGE DATA
ITEM #
DESCRIPTION OF
CHANGES
UNIT
QTY.
UNIT
PRICE
AMOUNT
ADDED DAYS
CALENDAR/
WORKING
CORE DRILL 6"x20" HOLES THRU SB
BRIDGE DECK, 8 EA, AND NB BRIDGE
1
DECK, 4 EA.
EA
12
$320.00
$3,840.00
BARRICADES, SIGNAGE & CHANNELIZERS
2
DELIVERY, PLACEMENT AND PICK-UP
LS
2
$430.00
$860.00
3
DAILY RENTAL RATE FOR BARRICADES,
SIGNAGE & CHANNELIZERS
DAY
4
$105.00
$420.00
4
DAILY RENTAL RATE FOR ARROW BOARD
DAY
4
$100.00
$400.00
CLEAN-UP/REMOVE CORE DRILL ANCHOR
5
BOLTS
DAY
1.5
$1,000.00
$1,500.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
TOTAL:
$7,020.00
0
ARED BY:
SIGN E (E�NEE
SIGNAT E (CONTRA
TOR)
PRINTED NAME: Martin Morello
l�
DATE
8/7/2007
TITLE: Project Manager
APPROVED:
CITY OF ROU
$-I11
DA E
G ofvv `
PERCENT OF ORIGINAL CONTRACT PRICE
THIS CHANGE ORDER: $7,020.00
PREVIOUS CHANGE ORDER: $866,696.66
TOTAL % CHANGE TO DATE: 17.55%
ORIGINAL CONTRACT PRICE PLUS
CHANGE ORDERS: $5,852,074.42
CITY OF ROUND ROCK
CONSTRUCTION CHANGE ORDER
DEPARTMENT: Transportation Services
PROJECT: A. W. Grimes Boulevard Phase II
Page 2 of 2
DATE: 8/7/2007
CHANGE ORDER NO: 12
JUSTIFICATION:
1 In accordance with The City of Round Rock directive to improve drainage on the bridge deck, we are to core drill
eight additional holes through the south bound concrete bridge deck as referenced in Aguirre & Fields letter dated
dated July 31, 2007. In accordance with an additional directive received from The City of Round Rock on
August 6, 2007, we are also core drilling four additional holes through the north bound concrete bridge deck.
DATE:
SUBJECT:
ITEM:
Department:
Staff Person:
Justification:
August 13, 2007
City Manager Action - August 17, 2007
Action authorizing the City Manager to execute Change Order
#12 with RGM Constructors, L.P., for drainage improvements
on the bridge deck over Brushy Creek on A.W. Grimes
Boulevard.
Transportation Services
Thomas G. Martin, P. E.,
Director of Transportation Services
In order to improve the drainage on the bridge decks crossing Brushy Creek on the Arterial
Roadway of A. W. Grimes Boulevard during extraordinary flooding events, additional core
holes will be drilled through the decks, both South bound, and North bound.
Funding
Cost:
Source of Funds:
$7,020.00
4B -RR Transportation Development Corporation
Original Contract
Previous Change Orders
Change Order #12
Revised Contract
Amount
$4,978,357.76
$866,696.66
$7,020.00
0/0 Change
N/A
17.41%
0.14%
$ 5,852,074.42
Outside Resources: RGM Constructors, L.P.
Background Information:
17.55%
The A.W. Grimes Boulevard Phase II project was awarded to RGM Constructors, L.P., by
Council on July 14, 2005. Phase II constructs a six -lane section from US 79 to Lake Creek
including curb and gutter, sidewalk, a raised median, drainage and utility improvements, a
bridge over Brushy Creek and a crossing under the Union Pacific Railroad. A.W. Grimes
Boulevard provides the Zink for connecting Georgetown, Round Rock and Pflugerville.
Public Comment: N/A