CM-07-10-219CITY OF ROUND ROCK
CONSTRUCTION CHANGE ORDER
PAGE 1 OF 2
DEPARTMI Parks & Recretaion DATE: 9/13/2007
PROJECT: Round Rock West Park Improvement CHANGE ORDER NO: 2
JUSTIFICATION:
ORIGINAL CONTRACT PRICE:
PREVIOUS CHANGE ORDERS:
THIS CHANGE ORDER:
CHANGE ORDERS TO DATE:
$52,050.96
$8,715.72
$6,325.00
$15,040.72
CHANGE DATA
additional concrete flatwork
ITEM #
DESCRIPTION OF
CHANGES
UNIT
QTY.
UNIT
PRICE
AMOUNT
ADDED DAYS
CALENDAR/
WORKING
1
revised quantity concrete flatwork
LF
275
$23.00
$6,325.00
0
DATE
NAME OF CONTRACTOR
SIGNATURE:
PRINT NAME/TITLE:
APPROVED:
/0/0,570 7
ITY OF ROUND ROCK constco2/forms6/Ik
scot/forms6/Ik
TOTAL:
$6,325.00
0
PERCENT OF ORIGINAL CONTRACT PRICE
THIS CHANGE ORDER: 3.20%
PREVIOUS CHANGE ORDER: $8,715.72
TOTAL % CHANGE: 7.80%
ORIGINAL CONTRACT PRICE PLUS
CHANGE ORDERS: $67,091.68
CM- 07- /o -`�
DATE:
September 24, 2007
SUBJECT: City Manager Approval - October 5, 2007
ITEM: Consider a resolution authorizing the City Manager to
approve the Change Order for Construction Services with
Ceda - Tex Services for the Round Rock West Park
Development Project - additional linear feet of concrete
flatwork.
Department: PARD
Staff Person: Rick Atkins, Parks and Recreation Director
Justification:
This project facilitates the community's need for a safe
recreational trail in the park. There are currently no
accessible trails in Round Rock West Park.
Funding: $70,000
Cost: $6,325.00
Source of funds: 2000 C.O. Bond
General Self -Financed Construction
Outside Resources: N/A
Background Information: This project will replace the existing
deteriorated trail with a safer and more
accessible walking/jogging trail in the park.
This project will also include site furnishings.
Public Comment: N/A
/o_,2