TO CONTRACT FOR ENGINEERING SERVICES
FIRM: HALFF ASSOCIATES, INC. ("Engineer")
ADDRESS: 4030 West Braker Lane, Suite 450, Austin, TX 78759-5356
PROJECT: Purple Saee Drive Culvert
This Supplemental Contract No. 1 to Contract for Engineering Services is made by and between
the City of Round Rock, Texas, hereinafter called the "City" and Halff Associates, Inc.,
hereinafter called the "Engineer".
WHEREAS, the City and Engineer executed a Contract for Engineering Services, hereinafter
called the "Contract', on the 6th day of February, 2015 for the Purple Sage Drive Culvert Project
in the amount of $48,347.00; and
WHEREAS, it has become necessary to amend the Contract to modify the provisions for the
scope of services and to increase the compensation by $8,761.30 to a total of $57,108.30;
NOW THEREFORE, premises considered, the City and the Engineer agree that said Contract
is amended as follows:
1.
Article 2. Engineering Services and Exhibit B. Engineering Services shall be amended as set
forth in the attached Addendum To Exhibit B. Exhibit C. Work Schedule shall be amended as
set forth in the attached Addendum To Exhibit C.
Article 4. Compensation and Exhibit D. Fee Schedule shall be amended by increasing by
$8,761.30 the lump sum amount payable under the Contract for a total of $57,108.30, as shown
by the attached Addendum to Exhibit D.
IN WITNESS WHEREOF, the City and the Engineer have executed this Supplemental
Contract in duplicate.
Supplemental Contract Rev. 12/01/08
0199.1503;00337387 /'��A�p 84275
HAL,FF� ASSOCIATES, INC.
,^
By: ll Y` JJ ;� ° � '`
G (2s�Zo I s
Date
CITY O �O/U/N(D' oROCK APPROVED AS TO FORM:
Ste-- pfian L. Sheets, City Attorney
Z�
Date
Supplemental Contract Rev. 12/01/08
0199.1503;00337387 84275
ADDENDUM TO EXHIBIT B
Engineering Services
Exhibit B "Engineering Services" contained in the Contract for Engineering Services between the City of
Round Rock and Halff Associates, Inc. dated February 6, 2015 is amended by Supplemental Contract No.1
to add the following Bidding and Construction Administration services.
When and as requested by the City, the Engineer will provide Bidding and/or Construction Administration
services; typical services that could be selected by the City include, but shall not be limited, to the
following:
1. Prepare for and conduct the Pre-bid meeting; be available to discuss and answer questions
regarding the construction Drawings, specifications, and other pertinent items.
2. Prepare written addenda.
3. Review Contractor work experience and references; issue recommendation of award to City.
4. Other bidding phase services such as: attend and/or conduct bid opening; prepare and provide bid
tabulation; and attend City Council meeting for construction contract award.
S. Prepare "Release for Construction" sets of Drawings and issue to City and Contractor prior to or at
Pre -construction conference; sets shall incorporate any clarifications resulting from any addenda
issued or other appropriate modifications prior to issuance.
6. Prepare for and conduct Pre -construction Conference.
7. Review Contractor submittals; issue comments and/or recommendations.
8. Review Requests for Information (RFI's) from the Contractor during construction and issue
appropriate responses or clarifications to both the City and the Contractor.
9. Respond to citizen or City questions or inquiries.
10. Visit the project site up to four times during construction to observe the progress and quality of
the work.
11. Coordinate and conduct the final "walk-through" of the completed work; prepare and issue punch
list to Contractor and the City.
12. Prepare record drawings from information readily observed during site visits, or as provided by
the City and the Contractor.
13. Other Construction Administration services such as: preparing for and conducting construction
progress meetings and issuing associated meeting minutes; reviewing/signing pay estimates;
reviewing lab test results and issuing engineering recommendations based on such results;
interpreting governing specifications; and preparing and issuing recommendation letter for
acceptance of the completed construction.
ADDENDUM TO EXHIBIT C
Work Schedule
Exhibit C "Work Schedule" contained in the Contract for Engineering Services between the City of Round
Rock and Halff Associates, Inc. dated February 6, 2015 is amended as follows: all services shall end as of
one week following the date the City issues a Letter of Acceptance/Completion to the Contractor
selected by the City to construct the culvert project; and specific deadlines are established for possible
tasks as shown in the table below.
Task 4.0 Bid and Construction Phase Services
item
Deadline
Review construction Contractor work experience
Two business days from request by City
Review construction Contractor submittals
One business day from receipt
Review construction Contractor RFI
One business day from receipt
Prepare Drawings modifications
Two business days from receipt of information
Conduct completed construction walk-through
Two business days from request
Prepare record drawings
Two business days from receipt of information
Review construction testing results
One business day from receipt
ADDENDUM TO EXHIBIT D
Fee Schedule
Exhibit D "Fee Schedule" contained in the Contract for Engineering Services between the City of Round Rock and
Halff Associates, Inc. dated February 6, 2015 is amended by Supplemental Contract No.1 to add the following:
Other
Total Labor
Total Loaded
Direct
Task
Hours
Labor Cost
Costs
Subconsultants
TOTAL
4.0 Bid and Construction Phase Services
60
$8,524.00
$237.30
1 $0.00
1$8,761.30
City of Round Rock
ROUND ROOK
TEXAS Agenda Item Summary
Agenda Number:
Title: Consider executing Supplemental Contract No. 1 with Halff Associates,
Inc. for the Purple Sage Drive Culvert Project.
Type: City Manager Item
Governing Body: City Manager Approval
Agenda Date: 7/3/2015
Dept Director: Michael Thane, Director of Utilities and Environmental Services
Cost:��
Indexes:
Attachments: SC#1_Halff_PurpleSage_CM7.2.15.pdf
Department: Utilities and Environmental Services
Text of Legislative File CM -2015-826
Consider executing Supplemental Contract No. 1 with Halff Associates, Inc. for the
Purple Sage Drive Culvert Project.
On February 6, 2015 the City Manager approved a Contract for Engineering Services
with Halff Associates, Inc. to design and prepare construction plans for the Purple Sage
Drive Culvert project. In order to reduce the frequency of roadway and property flooding
that has been experienced in the past, the aforementioned plans are for the
replacement of the culvert under Purple Sage Drive just west of Rawhide Drive in the
Chisholm Valley neighborhood.
Now that the plans have been completed and have been issued for bids, it has become
apparent that the City will require some assistance from the engineer during the bidding
and construction phases of the project.
Supplemental Contract No. 1 will allow the City to request services from the engineer
as necessary during the bid and construction phases of the project and will increase
the original contract amount by $8,761.30; bringing the total under the contract to
$57,108.30.
Staff recommends approval.
City o/ Round Rock Page 1 Punted on 7/212015
LEGAL DEPARTMENT APPROVAL FOR CITY COUNCILICITY MANAGER ACTION
Required for Submission of ALL City Council and City Manager Items
Department Name: utilities & Environmental Services Project Name: Purple Sage Drive Culvert
Project NlgrfResource: Lance Shellonberger Contractor/Vendor: Halff Associates, Inc.
[--ICouncii Action:
ORDINANCE RESOLUTION
xx City Manager Approvai
CMA Wording
Consider executing Supplemental Contract No. t with Halff Associates, Inc, for the Purple Sage Drive Culvert Project.
Attorney Approval
✓Attorney
Date
Notes/Comments r '
O:\WdoxkSCCIntS\0199\1503\CONTRACT\00337399.XLS Updated 613108