CM-2001-040 (2)C iN
CITY OF ROUND ROCK
INTEROFFICE MEMORANDUM
DATE: February 5, 2001
TO: Jim Nuse
Director of Public Works
FROM: Bill Stablein
Construction Coordinator
RE: Park Valley Drive
Change Order # 2
This is a Change Order # 2 for the Park Valley Project. This includes a total of six items. (1)
Removal of unsuitable material within the roadway, (2) Saw -cut and excavation for a storm
sewer line, (3) Installation of curbing at the Oakwood Arbors Medical Center, (4) Connecting
water service to the Wyoming Springs Medical Center, (5) Installation of sprinkler system
driveway sleeves, and (6) Connect two existing driveways to Park Valley Drive. I have
discussed and reviewed these items with Tom Word. We recommend approval of the change
order in the amount of $ 22,949.00.
If you have any questions please contact me at 218-3237.
Respectfully yours,
zs.Di
Bill Stablein
\\Bill\my documents\CIP 2000\Park Valley\Park Valley Chg Order 2.doc
PUBLIC WORKS DEPARTMENT
SMITH CONTRACTING COMPANY
General Construction • Excavating • Paving • Concrete • Utilities • Site -Work
INVOICE
CHANGE ORDER NUMBER TWO
To: City of Round Rock
Attn: Bill Stablein
12/23/00 Invoice# 122300
Re: Park Valley Drive Roadway Project
Item #1: Excavate 44' X 250' X 18" ( 611 CY) Station 13+25 to 15+75;
Removal of pre-existing clay area (Unstable Subgrade Material)
Excavation: 611 CY c@ $5.00 3,055.00
Haul -Off: 40 Loads to Disposal Site $80.00 3,200.00
Select Fill: 200 Tons 1-1/2" Screenings $2.40 480.00
485 Tons City of Round Rock Base $3.50 1,697.50
Trucking: 30 Loads from T.C.S. $65.00 1,950.00
Installation: 600 CY L $3.00 1,800.00
Subtotal 12,1 W,50
Item #2: Excavate approx. 75 LF for 30 -Inch RCP Storm Sewer Line;
Line terminates at Wingwall of Pond "D"
Saw -Cut & Excavate 75 L.F.
$15.00
Subtotal
1,125.00
Item #3: Install 107 LF of Hand -Form Curbing at Oakwood Arbors Med Center
(Curbing removed to accomodate excavation of Storm Sewer)
Concrete Curb & Gutter 107 LF
$15.00
Subtotal
1,605.00
Item #4: Connect Water Service Line for Wyoming Springs Medical Center
Labor: 1 Operator 2 Hours $15.00 30.00
2 Laborers 4 Hours $10.00 40.00
Taxes/Insurance-Labor: 25% 17.50
Materials: Sleeve, Glan Pack, Bedding, Fittings, etc 175.00
Equipment: Backhoe for Excavatng and Back -filling 50.00
Subtotal
Item #5: Install (2) 3 -Inch PVC Driveway Sleeves for Womens Center
Labor: 2 Laborers 6 Hours $10.00 60.00
Taxes/Insurance-Labor: 25% 15.00
Materials: 180 LF Sch 40 PVC; Misc. Fittings, etc. 270.00
Subtotal
Item #6: Connect (2) Existing Driveways to Park Valley Drive;
(Excludes signage, handicapped ramps or pavement markings)
Flexible Base Material, Installed
Concrete Curb & Gutter
HMAC, 4 -Inch, Installed
Total all Items
15% GC Profit and OH
GRAND TOTAL
90 CY
102 LF
132 �Y
$20.00
$15.00
$ 8.00
Subtotal
Respectful Submitted, App -r,' VAL:
116.By: ',
Title: 1,a,it_ay....."
Date: a J 4-01
15308 Ginger St. • Austin, Texas 78728 • Office 512-990-7640 • Fax 512-990-7855
! -- C Li'(
1,800.00
1,530.00
1,056.00
1,125.00
1,605.00
312.50
345.00
4,386.00
19, 956.00
2, 993.40
$22,949.40