CM-08-01-015DATE: January 7, 2008
SUBJECT: City Manager Approval - January 11, 2008
ITEM: Action authorizing the City Manager to execute Change Order # 1
with Manley Contracting for Federal Aid Project STP97(649) MM BI35-
L(Mays Street) Sidewalk Construction.
Department: Engineering and Developmental Services
Staff Person: Danny Halden, P.E., City Engineer
Justification:
Change Order # 1 adds nineteen (19) days to the contract with Manley Contracting.
Funding:
Cost: NA
Source of funds: NA
Amount % Change
Original Contract $125,797.43 N/A
Change Order # 1 $0.00 0%
Revised Contract $125,797.43 0%
Outside Resources: Manley Contracting
Background Information:
Change Order # 1 is needed to account for contract time adjustments in accordance with
the contract.
Public Comment: NA
Blue Sheet Format
Updated 01/20/04
CITY OF ROUND ROCK
CONSTRUCTION CHANGE ORDER
DEPARTMENT: Public Works
PAGE 1 OF 1
DATE: 01/04/08
PROJECT: Mays Street Sidewalk Construction CHANGE ORDER NO: 1
Federal Aid Project STP97(649) MM BI35-L JUSTIFICATION:
ORIGINAL CONTRACT PRICE:
PREVIOUS CHANGE ORDERS:
THIS CHANGE ORDER:
$125,797.43
$0.00
$0.00
CHANGE ORDERS TO DATE:
$0.00
CHANGE DATA
Contract time adjustment
ITEM #
DESCRIPTION OF
CHANGES
UNIT
QTY.
UNIT
PRICE
AMOUNT
ADDED DAYS
CALENDAR/
WORKING
1
2
Delay due to relocation of 18" RCP at
Mays/Texas Street
(construction performed by City crews)
Rain Days
Cal. Days
Cal. Days
14
5
PREPARED BY: Eddie Zapata
PROJECT MANAGE
(IL
Manley Contracting
NAME OF CONTRACTOR
SIGNATURE:
-
PRINT NAME/TITLE: .777,--.= 5,'
TOTAL:
$0.00
19
01/04/08 PERCENT OF ORIGINAL CONTRACT PRICE
DATE THIS CHANGE ORDER: 0.00%
PREVIOUS CHANGE ORDER: 0.00%
TOTAL % CHANGE: 0.00%
ORIGINAL CONTRACT PRICE PLUS
APPROVED:
CITY OF ROUND ROCK
Ct4 - C`E-c `-- C LS
CHANGE ORDERS: $125,797.43