Contract - APAC Texas, Inc - Wheeler Companies - 7/9/2015 Page 1 of 3
Contract Quantity Adjustment/Change Order
w r�-.:iU�u�.OfA.mnat5
rev,06/12
Department: Transportation
Project 2014 Street Maintenance Program (Type
Name: F Overlay)
City Project Change Order/Quantity
ID Number MNTFI Adjustment No. 1
Justification
Quantity Adjustment/Change Order# 1 is required to add additional streets in the project area and to adjust final quantities that was required to
complete necessary work for the project; a deduct in asphalt repair and manhole adjustments is required.There was an increase in HMAC Type
F Overlay and asphalt milling associated with the additions to the project.
SUMMARY Amount %Change
Original Contract Price: $851,427.75
Previous Quantity Adjustment(s): $0.00
This Quantity Adjustment: -$22,721.80
Total Quantity Adjustment(s):
Total Contract Price with Quantity Adjustment(s): $851,427.75
Previous Change Order(s): 0.00
This Change Order: $87,162.28 0.10
Total Change Order(s)To Date: 0.00
Adjusted Contract Price [Original Contract Price Plus
Quantity Adjustment(s)Plus Change Order(s)]: $915,868.23
Difference between Original and Adjusted Contract Prices: $64,440.48
Original Contract Time:
Time Adjustment by previous Quan.Adj./Change Order:
Time Adjustment by this Quan.Adj./Change Order:
New Contract Time: 0
Submitted for Approval
Prepared By: Todd Keltgen Transportation Manager City of Round Rock '
gnature Printed Name,Title, Company Date
Approvals
Contractor: l r
Signature Printed Name,Title, Company Dto
City Project
Manager: ' 11/
a Printed Name,litle V Date
Mayor/City G
Manager
Signature Printed Name,Title Date
��5 - v1 t
Page 2 of 3
Contract Quantity Adjustment/Change Order
rev,08/12
Project Name: 2014 Street Maintenance Program (Type F Overlay)
Quan.Adj./Change Order No.: 1
Change Order Data
Contract
Time
Adjustment
Item # Item Description Unit Qty. Unit Price Amount (Days)
1 Type F HMAC 1"Overlay Ton 583.76 $97.05 $56,653.91
2 Pavement Repair Ton $161.60 $0.00
3 Edge Milling (6'wide) SY 7707 $2.52 $19,421.64
4 Surface Milling SY 1689 $4.07 $6,874.23
5 Valve Can Adjustment EA $65.00 $0.00
6 Manhole Adjustment EA $275.00 $0.00
7 Traffic Control MO 0.5 $8,425.00 $4,212.50
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Page 3 of 3
AV Contract Quantity Adjustment/Change Order
rev,08/12
Project Name: 2014 Street Maintenance Program (Type F Overlay)
Quan. Adj./Change Order No.: 1
Quantity Adjustment Data
Contract
Time
Bid Item # Item Description Unit Qty. Unit Price Amount Adjustment
1 Type F HMAC 1"Overlay Ton $ 97.05 $0.00
2 Pavement Repair Ton -98 $ 161.60 -$15,836.80
3 Edge Milling(6'wide) SY $ 2.52 $0.00
4 Surface Milling SY $ 4.07 $0.00
5 Valve Can Adjustment EA -34 $ 65.00 -$2,210.00
6 Manhole Adjustment EA -17 $ 275.00 -$4,675.00
7 Traffic Control MO $ 8,425.00 $0.00
-$22,721.80 0