CM-2015-932 - 10/26/2015Contract Quantity Adjustment/ Change Order
mit
M, 08 /12
Department: Transportation
Project Cypress Boulevard Realignment Between
Name: Cypress Cove and Sunrise Road
City Project
ID Number
Justification
Quantity Adjustment/Change Order #1 additional Water Pipe and Electrical Conduit.
SUMMARY
Original Contract Price:
Previous Quantity Adjustment(s):
This Quantity Adjustment:
Total Quantity Adjustment(s):
Total Contract Price with Quantity Adjustment(s):
Previous Change Order(s):
This Change Order:
Total Change Order(s) To Date:
Adjusted Contract Price [Original Contract Price Plus
Quantity Adjustment(s) Plus Change Order(s)j:
Difference between Original and Adjusted Contract Prices:
Original Contract Time:
Time Adjustment by previous Quan. Adj./Change Order:
Time Adjustment by this Quan. Adj./Change Order:
New Contract Time:
Contractor:
City Project n "
Mayor/City
32
Submitted for Approval
Printed Name, Title, Company
Approvals
Printed Name, Title, Company
GU's �eU, Ct
Page I of 3
Date: 9/24/15
Change Order/Quantity
Adjustment No. 2
Amount
% Change
$1,649,137.75
$25,396.80
-$10,500.00
$14,896.80
$1,664,034.55
$11,790.00
0.01
$2,300.00
0.00
$14,090.00
0.01
$1,678,124.55
$28,986.80
90
90
Contract Quantity Adjustment/Change Order
M/12
Project Name: Cypress Boulevard Realignment Between Cypress Cove and Sunrise Road
Quan. Adj./Change Order No.:
Change Order Data
Page 2 of 3
Item # Item Description Unit Qty. Unit Price Amount
Contract
Time
Adjustment
(Days)
CO -3.1 IRRIGATION PEDISTAL LS 1 $2,300.00 $2,300.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Page 3 of 3
Contract Quantity Adjustment/Change Order
M, 08/12
Project Name: Cypress Boulevard Realignment Between Cypress Cove and Sunrise Road
Quan. Adj./Change Order No.:
Quantity Adjustment Data
Bid Item # Item Description Unit Qty. Unit Price Amount
Contract
Time
Adjustment
$0.00
104 ALT # 9 - ADD POSER COATING PAINT LS -1 $10,500.00 10,500.00
0.00
0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
-$10,500.0
0
City of Round Rock
ROUND ROCK
TEXAS Agenda Item Summary
Agenda Number:
Title: Consider executing Quantity Adjustment/Change Order No.2 with Patin
Construction LLC for the Cypress Boulevard Realignment between
Cypress Cove and Sunrise Road Project.
Type: City Manager Item
Governing Body: City Manager Approval
Agenda Date: 10/23/2015
Dept Director: Gary D. Hudder
Cost:
Indexes:
Attachments: Change Order#2-Cypress Blvd..pdf
Department: Transportation Department
Text of Legislative File CM -2015-932
Consider executing Quantity Adjustment/Change Order No.2 with Patin Construction
LLC for the Cypress Boulevard Realignment between Cypress Cove and Sunrise Road
Project.
This project realigned Cypress Boulevard between Cypress Cove and Sunrise Road to
align it with the Eagle's Nest on the east. Bid item #104 is being deleted for the colored
electric poles and this results in a credit for ($10,500).
An additional electric meter pedestal is required for the irrigation system at a cost of
$2,300.00.
With the negative Quantity Adjustment of ($10,500.00) and the Change Order for
$2,300.00, this is an overall deduct of ($8,200.00) to the original contract price of
$1,649,137.75. The adjusted new contract price is $1,678,124.55.
Staff recommends approval.