Loading...
CM-2015-932 - 10/26/2015Contract Quantity Adjustment/ Change Order mit M, 08 /12 Department: Transportation Project Cypress Boulevard Realignment Between Name: Cypress Cove and Sunrise Road City Project ID Number Justification Quantity Adjustment/Change Order #1 additional Water Pipe and Electrical Conduit. SUMMARY Original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Adjusted Contract Price [Original Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)j: Difference between Original and Adjusted Contract Prices: Original Contract Time: Time Adjustment by previous Quan. Adj./Change Order: Time Adjustment by this Quan. Adj./Change Order: New Contract Time: Contractor: City Project n " Mayor/City 32 Submitted for Approval Printed Name, Title, Company Approvals Printed Name, Title, Company GU's �eU, Ct Page I of 3 Date: 9/24/15 Change Order/Quantity Adjustment No. 2 Amount % Change $1,649,137.75 $25,396.80 -$10,500.00 $14,896.80 $1,664,034.55 $11,790.00 0.01 $2,300.00 0.00 $14,090.00 0.01 $1,678,124.55 $28,986.80 90 90 Contract Quantity Adjustment/Change Order M/12 Project Name: Cypress Boulevard Realignment Between Cypress Cove and Sunrise Road Quan. Adj./Change Order No.: Change Order Data Page 2 of 3 Item # Item Description Unit Qty. Unit Price Amount Contract Time Adjustment (Days) CO -3.1 IRRIGATION PEDISTAL LS 1 $2,300.00 $2,300.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Page 3 of 3 Contract Quantity Adjustment/Change Order M, 08/12 Project Name: Cypress Boulevard Realignment Between Cypress Cove and Sunrise Road Quan. Adj./Change Order No.: Quantity Adjustment Data Bid Item # Item Description Unit Qty. Unit Price Amount Contract Time Adjustment $0.00 104 ALT # 9 - ADD POSER COATING PAINT LS -1 $10,500.00 10,500.00 0.00 0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 -$10,500.0 0 City of Round Rock ROUND ROCK TEXAS Agenda Item Summary Agenda Number: Title: Consider executing Quantity Adjustment/Change Order No.2 with Patin Construction LLC for the Cypress Boulevard Realignment between Cypress Cove and Sunrise Road Project. Type: City Manager Item Governing Body: City Manager Approval Agenda Date: 10/23/2015 Dept Director: Gary D. Hudder Cost: Indexes: Attachments: Change Order#2-Cypress Blvd..pdf Department: Transportation Department Text of Legislative File CM -2015-932 Consider executing Quantity Adjustment/Change Order No.2 with Patin Construction LLC for the Cypress Boulevard Realignment between Cypress Cove and Sunrise Road Project. This project realigned Cypress Boulevard between Cypress Cove and Sunrise Road to align it with the Eagle's Nest on the east. Bid item #104 is being deleted for the colored electric poles and this results in a credit for ($10,500). An additional electric meter pedestal is required for the irrigation system at a cost of $2,300.00. With the negative Quantity Adjustment of ($10,500.00) and the Change Order for $2,300.00, this is an overall deduct of ($8,200.00) to the original contract price of $1,649,137.75. The adjusted new contract price is $1,678,124.55. Staff recommends approval. City of Round Rock Page 1 Printed on 10/22/2015