CM-08-06-178BLUE SHEET FORMAT
DATE: June 23, 2008
SUBJECT: City Manager Approval - June 27, 2008
ITEM: Consider a resolution authorizing the City Manager to
approve Change Order #2 for construction services with
Westar Construction for the Greater Lake Creek Park
Development Project.
Department: PARD
Staff Person: Rick Atkins
David Buzzell
Justification: Planned quantities differed from actual quantities, there
was additional concrete and granite trail constructed and
additional sleeves needed.
Funding: $16,401.20
Cost: $708,0359.10
Source of funds: LCRA Grant, TPWD Grant, 2002 GO Bonds
Outside Resources: Westar Construction
Background Information: The Greater Lake Creek Park Project involves
three existing park properties and several
parcels of land that the City already has or will
acquire through the platting process of new
neighborhoods. Clay Madsen Park, Greenlawn
Park, and Lake Creek Park will all receive
improvements in the form of new development
and/or renovations. These three parks will
also be connected with a hike & bike trail. Also
included in this project will be the City's first
dog park and inline hockey facility. This
project is partially funded by a Texas Parks and
Wildlife Dept. (TPWD) Grant and a LCRA
Partnership in Parks Grant.
Public Comment: N/A
Blue Sheet Format
Updated 01/20/04
CITY OF ROUND ROCK
CONSTRUCTION CHANGE ORDER
DEPARTMENT: Parks & Recreation
PROJECT: Greater Lake Creek Development
ORIGINAL CONTRACT PRICE:
PREVIOUS CHANGE ORDERS:
THIS CHANGE ORDER:
CHANGE ORDERS TO DATE:
ITEM #
1
2
3
DESCRIPTION OF
CHANGES
4" Sch. 40 sleeves
Additional Concrete Trail
Additional granite Trail
$695,936.90
($3,475.00)
$16,401.20
($3,475.00)
CHANGE DATA
UNIT
LF
LF
LF
QTY.
127
113
162
PAGE 1 OF 1
DATE:
CHANGE ORDER NO:
JUSTIFICATION:
PVC sleeves, additional
concrete & granite trail
6/24/2008
2
UNIT
PRICE
$14.00
$59.12
$49.20
AMOUNT
$1,778.00
$6,652.80
$7,970.40
ADDED DAYS
CALENDAR/
WORKING
PREPARED BY:
ENGINEE
Westar Construction
ME OF CONTRACTOR
SIGNATURE:
DATE
PRINT NAME/TITLE: �Meti� ` P� 4
�, N 1+uA,(4
APPROVED:
TY OF ROUND ROCK
TOTAL:
$16,401.20
0
PERCENT OF ORIGINAL CONTRACT PRICE
THIS CHANGE ORDER: 2.30%
--MOM
TOTAL % CHANGE: 3.16%
ORIGINAL CONTRACT PRICE PLUS
PREVIOUS CHANGE ORDER:
CHANGE ORDERS:
constco2/forms6/Ik
$708,359.10