Loading...
CM-08-08-223CITY OF ROUND ROCK CONSTRUCTION CHANGE ORDER PAGE 1 OF 1 DEPARTMENT: Utility Administration DATE: 7/29/2008 PROJECT: 2005-06 Wastewater Collection System Rehab Basins CHANGE ORDER NO: 3 BC22-Z, CC32-Z,OC30-Z, EW01-Z, LCI1,LCI2.LC14,LC16-Z JUSTIFICATION: ORIGINAL CONTRACT PRICE: PREVIOUS CHANGE ORDERS: THIS CHANGE ORDER: CHANGE ORDERS TO DATE: S2,112,690.00 $17,808.00 (578,807.50) (560,999.50) CHANGE DATA ITEM# DESCRIPTION OF CHANGES 8" Dia PVC Sewer Open Cut 0'-6' CHANGE ORDER QTY 138 UNIT LF NEW TOTAL QTY 1535 UNIT PRICE $65.00 AMOUNT $8,970.00 8" PVC Sewer Open Cut 6' - 12" 100 LF 265 $67.00 $6,700.00 8" PVC SDR -26 Pressure Pipe 0'-6' deep 176 LF 1,001.00 $60.00 $10,560.00 8" Dia. HDPE DR -17 Sewer Pipe by enlargement 445 LF 1,753.00 $65.00 $28,925.00 Rock Excavation 1192 CY 1,392.00 $50.00 $59,600.00 Apply Epoxy 22.59 VF 435.59 $250.00 $5,647.50 12" PVC SDR -26 Pressure Pipe 0'-6' deep 775 LF 1,635.00 $120.00 $93,000.00 12" Dia. HDPE DR -17 Sewer Pipe by directional drilling -600 LF 0.00 $180.00 ($108,000.00) Job #1020 -1 LS 0.00 $4,500.00 ($4,500.00) 6" Dia. CIPP Sewer Liner -1250 LF 0.00 $45.00 ($56,250.00) 8" Dia. CIPP Sewer Liner -10 LF 140.00 $45.00 ($450.00) 24" Dia CIPP Sewer Liner -2 LF 288.00 $160.00 ($320.00) 6" PVC Service Re -Connects after CIPP (external) -5 EA 17.00 $1,500.00 ($7,500.00) Remove & replace 48" Dia MH 0-6' Deep -2 EA 1.00 $7,500.00 ($15,000.00) Point Repair Prior to CIPP -2 EA 0.00 $7,500.00 ($15,000.00) 6" PVC Sewer Service Lines with CIO -12 EA 28.00 $1,500.00 ($18,000.00) 6" PVC Sewer Service Line Extension -250 LF 0.00 $80.00 ($20,000.00) Fence Repair -84 LF 16.00 $35.00 ($2,940.00) Point Repair Prior to Pipe Enlargement or CIPP -1 EA 0.00 $5,500.00 ($5,500.00) Paved Frame & Grade Adjustments -40 EA 5.00 $900.00 ($36,000.00) Install Bolts and Gaskets - bolt down cover -22 EA 3.00 $125.00 ($2,750.00) 4 / /-- ($78,807.50) PREPARED BY: ,8/21/2008 TE s SIGNATURE: PRINT NAME/TI andall ": -ar" C President APPROVED: CITY OF ROUND ROCK -�1-0�-O`b�22� % OF ORIG. CONTRACT PRICE THIS CHANGE ORDER: -3.73% PREV. CHANGE ORDERS: 0.84% TOTAL % CHANGE: -2.89% ORIG. CONTRACT PRICE PLUS CHANGE ORDERS: 52,051,690.50 constco2/forms6/Ik CITY OF ROUND ROCK CONSTRUCTION CHANGE ORDER PAGE 2 OF 2 DEPARTMENT: Public Works DATE: 7/29/2008 PROJE CHANGE ORDER NO: 2 ITEM # DESCRIPTION OF CHANGES CHANGE DATA UNIT UNIT QTY. PRICE AMOUNT ADDED DAYS (CALENDAR) 12" PVC SDR -26 Pressure Pipe 0'-6' deep 775 LF $120.00 $93,000.00 45 Rock Excavation 1192 CY $50.00 $59,600.00 45 TOTAL: 90 BID ITEM DESCRIPTION/ LOCATION Qty Extension infront of Fire Station CIPP 3005 12" 620 High School Bore Pit 2 Onion Creek- lowering 620 BC22Z-064 = 4.67 BC22Z-062 = 5.0 BC22Z-061 = 5.42 BC22Z-051A = 4.0 BC22Z-051B = 3.5 72 580 90 450 DATE: SUBJECT: ITEM: August 27, 2008 City Manager Approval — August 29, 2008 Action authorizing the City Manager to execute Change Order No. 3 with Enviro Remediation Coatings Services, Inc. for the 2005-2006 Wastewater Collection System Rehabilitation Project. Department: Water and Wastewater Utilities Staff Person: Michael D. Thane, P.E., Director of Utilities Justification: The City is required to inspect, repair, and certify the wastewater collection system in compliance with the Texas Commission on Environmental Quality's Edwards Aquifer Recharge Zone Protection Program. This change order adjusts final contract quantities and contract time for all work performed under this contract. Contract time is being increased by 90 days to account for delays caused by increased rock excavation, and changing the method of 12 -inch pipe installation from directional drilling to open cut. Funding: Cost: Source of funds: ($78,807.50) WW Utility Fund (F260 Outside Resources: RJN Group, Inc. (Engineering Consultant) Background Information: This project rehabilitates the defective wastewater collection system, which was identified in the 2005- 2006 Wastewater Collection System Inspection Project, in three Edwards Aquifer Basins (CC -32Z, OC - 30Z, and BC -22Z). The elimination of defects helps protect the aquifer and reduces inflow and infiltration entering the sewer system, thereby reducing the City's treatment cost. The scope of the project includes cured -in-place pipe, liner patches, point repairs, pipe bursting, boring, conventional pipe replacement, internal joint grouting, and manhole rehabilitation and replacement. Public Comment: N/A Blue Sheet Format Updated 01/20/04 Amount % Change Original Contract $ 2,112,690.00 N/A Previous Change Orders $ 17,808.00 0.84% Change Order No. 3 $ -78,807.50 -3.73% Revised Contract $ 2,051,690.50 -2.89% Outside Resources: RJN Group, Inc. (Engineering Consultant) Background Information: This project rehabilitates the defective wastewater collection system, which was identified in the 2005- 2006 Wastewater Collection System Inspection Project, in three Edwards Aquifer Basins (CC -32Z, OC - 30Z, and BC -22Z). The elimination of defects helps protect the aquifer and reduces inflow and infiltration entering the sewer system, thereby reducing the City's treatment cost. The scope of the project includes cured -in-place pipe, liner patches, point repairs, pipe bursting, boring, conventional pipe replacement, internal joint grouting, and manhole rehabilitation and replacement. Public Comment: N/A Blue Sheet Format Updated 01/20/04