CM-08-10-248CITY OF ROUND ROCK
CONSTRUCTION CHANGE ORDER
DEPARTMENT: Engineering & Development Services
PROJECT: Gattis School Road Corridor Enhancements
ORIGINAL CONTRACT PRICE:
PREVIOUS CHANGE ORDERS:
THIS CHANGE ORDER:
CHANGE ORDERS TO DATE:
ITEM #
1
2
3
DESCRIPTION OF
CHANGES
Add section of concrete fence at
Magnolia Drive and Dixie Lane.
Delete section of wooden fence at
Magnolia Drive and Dixie Lane.
Add one wooden mangate at Dixie
Lane residence.
PREPARED B)(,Z/'G
ENGIN
Fen e eel tAQ. 7rQI>t Ott, -1-1te.
NAME OF CONTRACT
SIGNATUR
PRINT NAME/TITLE: Yuc(& lb (� 1 e r
APPROVED:
$207,271.75
$0.00
$3,821.50
$3,821.50
CHANGE DATA
UNIT
LE
LF
EA
DATE
TY OF ROUND ROCK
QTY.
122
122
1
PAGE 1 OF 1
DATE: 10/10/08
CHANGE ORDER NO: 1
JUSTIFICATION:
Change Order # 1 is needed to change the
fencing material in one section of the fence
and to add one mangate.
UNIT
PRICE
$51.50
$25.75
$680.00
TOTAL:
AMOUNT
$6,283.00
($3,141.50)
$680.00
$3,821.50
ADDED DAYS
CALENDAR/
WORKING
0
0
0
PERCENT OF ORIGINAL CONTRACT PRICE
THIS CHANGE ORDER:
PREVIOUS CHANGE ORDER
TOTAL % CHANGE:
ORIGINAL CONTRACT PRICE PLUS
SNGE ORDERS:
constco2/forms6/Ik
0
1.90%
0%
1.90%
$211,193.25
DATE: October 6, 2008
SUBJECT: City Manager- October 10, 2008
ITEM: Consider executing Change Order No. 1 with Fencecrete America, Inc.
for Gattis School Road Corridor Enhancement Project.
Deoartm_ent• Engineering and Development Services
Staff Peron• Danny Halden, P.E., City Engineer
Justification:
Change Order No. 1 is needed to change the fencing material from wood to concrete for two
residences between Magnolia Drive and Dixie Lane and to add a mangate at Dixie Lane.
FunFun
Cost: $3,821.50
Source of funds: 2002 G.O. Bonds
Original Contract Amount oho Change
$207,27
Previous Change Orders .00 N/A
0
Change Order # 1 0.00 polo
3 21
Revised Contract $8Sn 1 1.9%
$211,193.25
Oid
utse Resources•
Fencecrete America, Inc.
FHI, Inc.
Background Information
The City Council approved the original construction contract, R -07-12-20-9F1, with
Fencecrete America, Inc. for $207,271.75 on December 20, 2007. This project is part of a
continuing program to aesthetically improve City street corridors. This fence will enhance
the visual appearance of the Gattis School Road corridor by replacing existing
privacy
fences, typically made of wood, with permanent, more durable concrete fencing.Change
Order No. 1 changes the fencing material from wood to concrete for two residences between
Magnolia Drive and Dixie Lane and adds a mangate at the residence on Dixie Lane. The
cost of this change order is $3,821.50 and would increase the total cost of the construction
contract to $211,093.25.
Public Comment• N/A
Blue Sheet Format