I am writing as a follow-up to the Technical Review Committee meeting on December 9, 2008, in
regard to flow charges for fiscal year 2009 for the regional and subregional customers of the Brushy
Creek Regional Wastewater System.
At the meeting the regional customers approved revisions to the flow charges for fiscal year 2009 as
shown in the attached Summary of Billable Flows and Flow Charges (Summary). Pursuant to section
5.02 of the Wastewater Disposal Contract, please confirm your agreement for the flow charges shown
in the attached Summary by signing a copy of this letter in the space provided below and returning it
to Monica Masters at: LCRA Water Services, P.O. Box 220 — H220, Austin, Texas 78767-0220. After
receipt of your confirmation, LCRA staff will seek approval for these flow charges from the LCRA
Board of Directors at its meeting on Wednesday, January 21, 2009.
I also want to extend my appreciation for our discussion regarding proposals for metering the
wastewater system or alternative methodologies for allocating flow charges for the system. While we
have not reached resolution on these issues, I hope continued discussions will soon resolve these
issues. In support of that, please send me information regarding the number of LUEs served by your
respective wastewater system as of January 1, 2009. The Technical Review Committee will meet
again on February 10, 2009, at 10:00 a.m. at the Brushy Creek Wastewater Treatment Plant
Administration Building in Round Rock to review these LUE numbers and continue our discussions.
Thanks again, and best wishes for the holidays.
Sincerely yours,
CY\ c
\Na
Monica Masters, P.E.
Senior Project Manager
Enclosure
V
AGREED as to attached Summary:
ted Name:Zarm+ NA/S.C.
cc: Phil Ford, General Manager, Brazos River Authority
Michael Thane
Cfit-D°t-oI-o/i+
Cifrs owirovwinte-•
P.O. BOX 220 • AUSTIN, TEXAS • 78767-0220 • (51 2) 473-3200 • 1 -800-776-5272 • WWW.LCRA.ORG
DATE: January 2, 2009
SUBJECT: City Manager Approval — January 9, 2009
ITEM: Consider executing a letter from the Lower Colorado River Authority (LCRA)
regarding revised flow charges for the 2009 fiscal year for the regional and sub -
regional customers of the Brushy Creek Regional Wastewater System
(BCRWWS).
Department:
Staff Person:
Justification:
Water and Wastewater Utilities
Michael D. Thane, P.E., Director of Utilities
During a meeting on December 9, 2009 by the BCRWWS Technical Review Committee, the
regional customers approved a revision to the customers flow charges for fiscal year 2009. This
revision was required due to an adjustment to the method in which Fern Bluff Municipal Utility
District (MUD) calculated their flow charges. This adjustment in flow charges results in an
increase to the City of Round Rock's regional wastewater budget by $25,399. Upon receipt of
this approval letter by all of the regional and sub -regional customers, the LCRA will seek
approval by its Board of Directors on January 21, 2009.
Funding:
Cost: $25,399
Source of funds: Capital Project Funds (Self -Financed Utility)
Outside Resources: Lower Colorado River Authority
Regional and Sub -Regional Customers of BCRWWS
Background Information:
The LCRA owns and operates the Brushy Creek Regional Wastewater System. The system
serves the following regional customers: City of Round Rock, City of Cedar Park, City of Austin,
and the LCRA. The LCRA is a regional customer representing the Brushy Creek MUD and the
Fern Bluff MUD. These MUDs are considered sub -regional customers.
Public Comment:
N/A
Blue Sheet Format