Loading...
CM-09-03-047CITY OF ROUND ROCK CONSTRUCTION CHANGE ORDER DEPARTMENT: Parks & Recreation PAGE 1 OF 1 DATE: 3/16/2009 PROJECT: Old Settlers Park Tennis RestroomlPro Shop CHANGE ORDER NO: 2 JUSTIFICATION: $472,821.25 Additional concrete work was required where Building Project ORIGINAL CONTRACT PRICE: PREVIOUS CHANGE ORDERS: THIS CHANGE ORDER: CHANGE ORDERS TO DATE: $0.00 new sidewalk tied into existing sidewalk because $4,630.00 of ADA issues. $7,579.00 CHANGE DATA PREPARED BY: Sck -tet SIGNATURE: Date 3 1!4./01 Date PERCENT OF ORIGINAL CONTRACT PRICE THIS CHANGE ORDER: 0.98% PREVIOUS CHANGE ORDER: 0 TOTAL % CHANGE: 1.60% ORIGINAL CONTRACT PRICE PLUS PRINT NAMEITITLE: David Buzzell, Park Development Manager CHANGE ORDERS: $477,451.25 �M D0t-O o41 OF ROUND ROCK C \o.. c r constco2/forms6/1k t» ,,.,v., „ ! .�..,«,�,.»..«»... ...n,.•„ «, ,goy,,,,, ,,. „11.1111.., ,.�,« �,,.,», ,�, , , ,n , , , ,,.,.,.,�,».,,,,,.*.. ,,,,,,i., ITEM # », , 1 •«I...n»..•. ,» DESCRIPTION OF CHANGES •,n •... 0,11111.41/1111,1,4.,11.41.M04,,,,,,, ,,••.• ,., 1, , s,«!„,n,«1«.1 UNIT ,,,< i 11i,,. x,,. QTY. ml».ry ,.l UNIT PRICE .ti 1,111.441.41.1 .-...0•' AMOUNT H! 1M1.,1.1 „ lniliIM , ,m„ t ., ADDED DAYS CALENDAR/ WORKING ,i.i..,.,,«.!«.«...»»«.,,... , «..«».1,«" CP 3 Remove and Replace Sidewalk LS 1 $4,630.00 $4,630.00 0 .11.---,a101_. TOTAL: $4,630.00 0 PREPARED BY: Sck -tet SIGNATURE: Date 3 1!4./01 Date PERCENT OF ORIGINAL CONTRACT PRICE THIS CHANGE ORDER: 0.98% PREVIOUS CHANGE ORDER: 0 TOTAL % CHANGE: 1.60% ORIGINAL CONTRACT PRICE PLUS PRINT NAMEITITLE: David Buzzell, Park Development Manager CHANGE ORDERS: $477,451.25 �M D0t-O o41 OF ROUND ROCK C \o.. c r constco2/forms6/1k DATE: March 23, 2009 SUBJECT: City Manager Approval — March 27, 2009 ITEM: Consider executing Change Order No. 2 with FT Woods Construction for the Old Settlers Park Tennis Restroom / Pro Shop Building Project. Department: Parks and Recreation Department Staff Person: Rick Atkins David Buzzell, RLA, ASLA Justification: The change order is for additional concrete work that was required where new sidewalk tied into existing sidewalk because of ADA issues. Funding: $472,821.25 Cost: $4,630.00 Source of funds: 2007 C.O. Bonds & 2008 General Self Finance Construction Outside Resources: FT Woods Construction Background Information: UPDATED APRIL 2008 The Project: Sports Capital of Texas Plan was developed in 2004 to plan for the necessary upgrades to our existing sports complexes, at Old Settlers Park at Palm Valley, to make them top notch recreational and tourism facilities.