Loading...
CM-09-04-058Change Order No. #1 Project Name: 2008 - 2010 Water Tank Rehabilitation Project Consultants Project No.: Project Owner City of Round Rock 212 Commerce Cove, Round Rock, TX 78664 Date of Issuance: 3/3/09 Project Contractor: N.G. Painting, LP 313 Mill Run Kerrville, TX 78028 Date of Contract: 9/25/08 Date of Notice to Proceed: 10/29/08 Original Completion Date: 4/28/09 Contract Period: 180 Days It is agreed to modify the Contract referred to above as follows: CPR # ITEM AND DESCRIPTION OF CHANGES CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME 8 Welding Repairs SE GST- Not Required ($4,740.00) 11 Rafter Replacement SE GST - Not Required ($12,000.00) 13 Blast Prime & Paint Interior Dry SE EST - Not Required ($16,000.00) 16 Welding Repairs SE EST -Not Required ($2,400.00) Attach each approved CPR to this form Difference Net ($35,140.00) Summary: It is agreed to modify the Contract referred to above as follows: Contract Price prior to this Change Order Contract Time prior to this Change Order $ 561,300.00 Net (increase) / (decrease) with this Change Order $ (35,140.00) Revised Contract Price with all approved Change Orders $ 526,160.00 180 days April 28, 2009 Net (increase) / (decrease) with this Change Order No Change Revised Contract lime with all approved Change Orders No Change - April 28, 2009 The changes included in this Change Order are to be accomplished in accordance with the terms, stipulations and conditions of the original Contract as though incl u r : • therein. Accepted for Contractor by: Mike Kasberg, Contract Supervisor Recommended for Approval by ( Consulting F' t�tn tkist7f,GTiont S>ve rtcE- Approved for Owne Approved: (Other - when required) :r; OU r ' Kz oc.. �.i.x.i1 •�, \t,� (y `'hili Distribution: 0 Owrier Con act Date: 3/4/09 Date: 3-25-oct Date: Date: 0 o O i e 0 Field R:\Utilities\Utility Administration\MASTER Forms \Prdject orms\Change Order Form_05-21-08.doc ..1 . t • r �` 0 Other DATE: SUBJECT: ITEM: Department: Staff Person: Justification: April 8, 2009 City Manager Approval — April 10, 2009 Consider executing Change Order No. 1 with N.G. Painting for the 2008-2010 Tank Rehabilitation Project. Water and Wastewater Utilities Michael Thane, P.E., Director of Utilities The original contract includes all the necessary construction for the rehabilitation of two City tanks to be completed between October 2008 and April 2009. The original contract amount for both tanks is $561,300. This change order accounts for a final adjustment to quantities and amounts, and reduces $35,140.00 thus bringing the final contract amount down to $526,160. Funding: Cost: Source of funds: Original Contract Change Order # 1 Revised Contract ($35,140.00) Self Financed Utility Fund Amount $561,300.00 ($35,140.00) $526,160.00 Outside Resources: HOT Inspection Services Background Information: % Change N/A (6.26%) (6.26%) The state requires annual inspections of all water storage tanks within our distribution system. The inspection results will provide the City with the information necessary to schedule any repairs and painting for each tank. In general, steel tanks need re -painting every 10 to 15 years. The work performed under this contract was for rehabilitation of the Southeast Elevated Tank (interior only — exterior had an overcoat in 2000) and the Southeast Ground Storage Tank (interior and exterior). Subsequent to project completion, all of the City's tanks, excluding the 1431 Standpipe, will be complete for this cycle of tank rehabilitation. Public Comment: N/A UPDATED APRIL 2008