CM-09-05-100CITY OF ROUND ROCK CONSTRUCTION CHANGE ORDER DEPARTMENT: Parks & Recreation PROJECT: Old Settlers Park Sports Complex Improvements Project 'X ORIGINAL CONTRACT PRICE: PREVIOUS CHANGE ORDERS: THIS CHANGE ORDER: CHANGE ORDERS TO DATE: $2,444,209.80 $66,954.00 $13,804.00 $80,758.00 ATA PAGE 1 OF 1 DATE: CHANGE ORDER NO: JUSTIFICATION: 3/31/2009 3 There was a discrepancy between the plan quantities and actual quantities of concrete fiatwork. The discrepancy was discovered upon final measurement. PREPARED BY :IP' -`--/51.414 Schrick I, Rollins & As Ch SIGNATURE: S. 22o7 Date 3. 3/.e7 Date PRINT NAME/TI E: David Buzzel , Park Development Manager APPROVED: Oci 05 00 OF ROUND ROCK • PERCENT OF ORIGINAL CONTRACT PRICE THIS CHANGE ORDER: PREVIOUS CHANGE ORDER: TOTAL % CHANGE: ORIGINAL CONTRACT PRICE PLUS CHANGE ORDERS: $2,524,967.80 0.58% 2.74% 3.30% constco2fforms6Ak _ -- . . ___ _____—..„ UNIT PRICE .. AMOUNT ADDED DAYS CALENDAR/ WORKING • - ITEM # - - DESCRIPTION OF CHANGES UNIT QTY. CP 15 Additional concrete paving LS 1 $13,804.00 $13,804.00 0 TOTAL: $13,804.00 0 PREPARED BY :IP' -`--/51.414 Schrick I, Rollins & As Ch SIGNATURE: S. 22o7 Date 3. 3/.e7 Date PRINT NAME/TI E: David Buzzel , Park Development Manager APPROVED: Oci 05 00 OF ROUND ROCK • PERCENT OF ORIGINAL CONTRACT PRICE THIS CHANGE ORDER: PREVIOUS CHANGE ORDER: TOTAL % CHANGE: ORIGINAL CONTRACT PRICE PLUS CHANGE ORDERS: $2,524,967.80 0.58% 2.74% 3.30% constco2fforms6Ak DATE: May 22, 2009 SUBJECT: City Manager - May 29, 2009 ITEM: Consider executing Change Order No. 3 with Chasco Constructors for the OSPV Sports Complex Improvements Project 'A'. Department: Parks & Recreation Department Staff Person: Rick Atkins David Buzzell, RLA, ASLA Justification: This change order is for a quantity discrepancy between the plan quantity and the actual constructed quantity. The additional quantity of concrete flatwork was discovered upon final measurement of constructed work. If approved, the total change order amount for this project will be $80,758 or a 3.30% addition. Funding: Cost: $13,804.00 Source of funds: 2007 CO Bond Money General Self Finance Construction Outside Resources: Chasco Constructors and Schrickel, Rollins, and Associates Public Comment: Numerous meetings and presentations with the Round Rock baseball and softball leagues. Blue Sheet Format Updated 01/20/04