CM-09-06-109Time Warner Communications Utility Relocation Agreement This Discretionary Service Agreement ("Agreement") is made and entered into this 27th day of May, 2009, by Time Warner Entertainment-Advance/Newhouse dba Time Warner Cable ("TWC" or "Company"), and City of Round Rock ("Customer"), a Municipalimesty, a Texas corporation and distribution utility, collectively as the "Parties". In consideration of the mutual covenants set forth the herein, the Parties agreereferred to asollowsarty" or both referred to 1. Discretionary Services to be Provided -- Company agrees to provide, and Customer agrees to pay for, the following services in accordance with this Agreement. City of Round Rock agrees to pay TWC for relocation of facilities in the southwest round rock area as indicated on attached drawings 2. Discretionary Service Charges -- Charges for any discretionary services covered by this Agreement are determined by actual costs accumulated in accordance with an established accounting procedure developed by the Company and which the Company uses in its regular operations. Company and Customer agree to comply with PUCT or court orders concerning discretionary service charges. 3. Term and Termination -- This Agreement becomes effective the date it is signed by the City of Round Rock and continues in effect until the utility relocation is complete. Termination of this Agreement does not relieve Company or Customer of any obligation accrued or accruing prior to termination. 4. No Other Obligations -- This Agreement does not obligate Company to provide, or entitle Customer to receive, any service not expressly provided for herein. Customer is responsible for making the arrangements necessary for it to receive any further services that it may desire from Company or any third party. 5. Governing Law and Regulatory Authority -- This Agreement was executed in the State of Texas and must in all respects be governed by, interpreted, construed, and enforced in accordance with the laws thereof. This Agreement is subject to all valid, applicable federal, state, and local laws, ordinances, and rules and regulations of duly constituted regulatory authorities having jurisdiction. 6. Amendment --This Agreement may be amended only upon mutual agreement of the Parties, which amendment will not be effective until reduced to writing and executed by the Parties. But changes to applicable Rules are applicable to this Agreement upon their effective date and do not require an amendment of this Agreement. 7. Entirety of Agreement and Prior Agreements Superseded -- This Agreement, including all attached Exhibits, which are expressly made a part hereof for all purposes, constitutes the entire agreement and understanding between the Parties with regard to the service(s) expressly provided for in this Agreement. The Parties are not bound by or liable for any statement, representation, promise, inducement, understanding, or undertaking of any kind or nature (whether written or oral) with regard to the subject matter hereof not set forth or provided for herein. This Agreement replaces all prior agreements and undertakings, oral or written, between the Parties with regard to the subject matter hereof, including without limitation , and all such agreements and undertakings are agreed by the Parties to no longer be of any force or effect. It is expressly acknowledged that the Parties may have other agreements covering other services not expressly provided for herein, which agreements are unaffected by this Agreement. 8. Notices -- Notices given under this Agreement are deemed to have been duly delivered if hand delivered or sent by United States certified mail, return receipt requested, postage prepaid, to: (a) If to Company: Time Warner Cable Attn: Joe Canales 12012 N. MOPAC Expressway Austin, TX 78758 (b) If to Customer: City of Round Rock 2008 Enterprise Dr. Round Rock, TX 78664 The above -listed names, titles, and addresses of either Party may be changed by written notification to the other. 9. Invoicing and Payment — Invoices or payments for any discretionary services covered by this Agreement will be mailed to the following address (or such other address directed in writing by Customer or Company). Invoices 1 of 2 V 1- DID" lO9 City of Round Rock 2008 Enterprise Dr. Round Rock, TX 78664 Pay ments Time Warner Cable Attn: Joe Canales 12012 N. MOPAC Expressway Austin, TX 78758 10. No Waiver -- The failure of a Party to this Agreement to insist, on any occasion, upon strict performance of any provision of this Agreement will not be considered to waive the obligations, rights, or duties imposed upon the Parties. 11. Taxes -- All present or future federal, state, municipal, or other lawful taxes (other than federal income taxes) applicable by reason of any service performed by Company, or any compensation paid to Company, hereunder must be paid by Customer. 12. Headings -- The descriptive headings of the various articles and sections of this Agreement have been inserted for convenience of reference only and are to be afforded no significance in the interpretation or construction of this Agreement. 13. Multiple Counterparts -- This Agreement may be executed in two or more counterparts, each of which is deemed an original but all constitute one and the same instrument. 14. Other Terms and Conditions - City of Round Rock agrees that payment shall be made within 60 days of the date the project is completed or the date the invoice is received, whichever is later. TWC shall provide notice to Reimbursor when TWC becomes aware that actual costs will exceed the estimate by more than ten (10%) percent. Time Warner Cable City of Round Rock BY: Kevin Bell TITLE: Director of Construction DATE: '/ Z /o BY: TITLE: DATE: Time Warner Cable CONSTRUCTION COST: Southwest Round Rock Pull Fiber Thru Conduit QTY 3,800 Cost Estimate UNIT ft. AMOUNT PER UNIT Pull Coax Thru Conduit 3,200 ea. Set Pedestals Coax Splicing 21 ea. $0.98 $0.98 $57.00 SUBTOTAL TOTAL, Underground Construction 33 ft. $30.00 $3,724.00 $3,136.00 $1,197.00 $990.00 5/22/2009 Wreck -out aerial cables 200 ft. Lash coax Cable& fiber 5,003 ft. $0.25 $1.07 $9,047.00 MATERIALS: Estimated Adjustment Cost Without Betterment ("In -Kind") Aerial Construction Hardware Electronics and Hardware UNIT ea. Labor Total: AMOUNT PER UNIT $543.20 $50.00 $5,353.21 $14,45(L21,5, TOTAL' ea. Coax Cable 3,600 ft. $3,085.000 UG Construction Material ea. Fiber 8,665 ft. $0.600 $1,213.000 Fiber Splicing Materials ea. TOTAL $0.86 $1,609.00 $3,085.00 $2,160.00 $1,213.00 $7,451.90 $1,609.00 $543.20 Freight and Handling ( 14.25%) $13,909.90 TWC LABOR: Fiber Splicing Field Engineering (see note below) 16 NIT hr. Materials Total: AMOUNT PER HOUR" Computer drafting (see note below) Computer design (see note below) 80 hr. $54.00 $54.00 $2,059.57 16,512.67 8 hr. $54.00 $864.00 $4,320.00 40 hr. $54.00 MISCELLANEOUS: ITEM Overhead , 15% (Management and Supervision) 1 Labor Total: AMOUNT ITY UNIT PER UNIT 1 ea. $5,810.83 Miscellaneous Total: TOTAL ESTIMATED COST OF ADJUSTMENT: (Sections A, B, C & D) $432.00 $2,160.00 ',776.00 TOTAL $5,810.83 5,810.83; $44,549.711 "= Field engineering - Costs to send a Field Engineer to location to record actual footages between poles or placement of conduit, stake placement of TWC poles, and completion and submission of any required permits. Computer Drafting - Costs for employee to draft base information into the CAD system. Computer Design - Cost for employee to design coax / fiber cable network in design program DATE: June 10, 2009 SUBJECT: City Manager Approval — June 12, 2009 ITEM: Consider executing a Utility Relocation Agreement with Time Warner Communications for the Southwest Downtown District Infrastructure Improvements Phase 1B Project. Department: Transportation Services Staff Person: Tom Word, P.E., Chief of Public Works Operations Justification: As part of the relocation of the dry utility infrastructure for the Southwest Downtown Infrastructure Project, the relocation of Time Warner Communication's dry utilities will be required. This agreement covers costs associated with sending a Time Warner Communication Field Engineer to record actual footages between poles or placement of conduit, stake placement of Time Warner Communication poles, and completion and submission of any required permits. Also included is the cost to draft base information into the CAD system and design coax/fiber cable network into a design program. Materials, hardware and Time Warner Communication labor also make up a portion of the total cost. Funding: Cost: $44,549.71 Source of funds: 2002 General Obligation Bonds Outside Resources: Time Warner Communications BRH Garver Construction Company Background Information: City Council approved a contract with BRH Garver Construction Company at the January 8, 2009 Council meeting for the construction of the Southwest Area Downtown Infrastructure Project. (R -09-01-08-8D2) Public Comment: N/A UPDATED APRIL 2008