CM-2015-1000 - 12/11/2015STATE OF TEXAS § COUNTY OF WILLIAMSON § SUPPLEMENTAL CONTRACT NO. 1 TO CONTRACT FOR ENGINEERING SERVICES FIRM: MWM DESIGNGROUP ("Engineer") ADDRESS: 305 E. Huntland Drive, Suite 200, Austin, TX 78752 PROJECT: Greenlawn Storm Drain This Supplemental Contract No. 1 to Contract for Engineering Services is made by and between the City of Round Rock, Texas, hereinafter called the "City" and MWM DesignGroup, hereinafter called the `'Engineer". WHEREAS, the City and Engineer executed a Contract for Engineering Services, hereinafter called the "Contract", on the 18th day of September, 2015 for the Greenlawn Storm Drain Project in the amount of $33,509.00; and WHEREAS, it has become necessary to amend the Contract to modify the provisions for the scope of services and to increase the compensation by $7,399.00 to a total of $40,908.00; NOW THEREFORE, premises considered, the City and the Engineer agree that said Contract is amended as follows: Article 2, Engineering Services and Exhibit B, Engineering Services shall be amended as set forth in the attached Addendum To Exhibit B. Exhibit C, Work Schedule shall be amended as set forth in the attached Addendum To Exhibit C. II. Article 4, Compensation and Exhibit D, Fee Schedule shall be amended by increasing by $7,399.00 the lump sum amount payable under the Contract for a total of $40,908.00, as shown by the attached Addendum to Exhibit D. IN WITNESS WHEREOF, the City and the Engineer have executed this Supplemental Contract in duplicate. Su l I " j am_ 10 C) emental Contract PP 0199.1544; 00347604 Rev. 12/01/08 84275 Date CITY ROUND CK qSteph ED AS TO ORM: Gc0 . Sheets, City Attorney Date Supplemental Contract Rev.12101/08 0199.1544;00347604 84275 ADDENDUM TO EXHIBIT B Engineering Services The City is considering expanding the limits and type of storm system previously contemplated for this project. Therefore, Exhibit B in the original contract between the City of Round Rock and MWM DESIGNGROUP dated September 18, 2015 shall be amended as delineated below. 1. Delete the paragraph under 1. PROJECT DESCRIPTION and replace with the following: Herein below is a detailed description of professional design, bidding, and construction phase services for the Greenlawn Storm Drain Improvements Project. The project location extends south approximately 200 feet along Greenlawn Boulevard from the intersection of Parkside Circle and Greenlawn Boulevard, turns to the east behind the shopping center, and terminates at Dry Branch Tributary No. 1. The project is anticipated to include inlets on Greenlawn Blvd, approximately 365 linear feet of stormdrain, 750 linear feet of concrete lined channel, an outfall at Dry Branch Tributary No. 1, and associated junction boxes and appurtenances. In addition, the project also includes pavement removal and overlay on Greenlawn Boulevard from Parkside Circle to Gattis School Road. 2. Delete the bulleted list under 2. SCOPE OF WORK and replace with the following: • Task 1: Project Management • Task 2: Hydrologic Evaluation • Task 3: Prepare Detailed Design Drawings • Task 4: Select Technical Specifications and Prepare Bid Form • Task 5: Design Phase Submittals and Meetings • Task 6: Opinion of Probable Cost • Task 7: Bidding and Construction Phases Services 3. Delete the last two sentences under 2.1.2. Task 2: Hydrologic Evaluation and add the following: If the City desires, the Engineer will provide more detailed drainage area delineation, analysis, and modeling as required to accurately design the various improvements. 4. Delete the last sentence under 2.1.3. Task 3: Prepare Detailed Design Drawings and replace with the following: It is anticipated that the plan set will include up to 14 sheets. 5. Add the following to 2.1.4. Task 4: Select Technical Specifications and Prepare Bid Form: 2.1.4.3 If directed by the City, the Technical Specifications selection and Bid Form preparation shall include items for milling and overlay of the Greenlawn Boulevard pavement generally from Gattis School Road to Parkside Circle. ADDENDUM TO EXHIBIT C Work Schedule Exhibit C in the original contract between the City of Round Rock and MWM DESIGNGROUP dated September 18, 2015 shall be deleted and replaced with the following: Following the effective date of a Notice to Proceed issued by the City authorizing services, the Engineer will provide the authorized services as scheduled below. • 50% Design Submittal — three weeks following receipt of surveying information to be supplied by the City. • 100% Design Submittal — two weeks following receipt of 50% Design Submittal comments from the City. • Bidding Phase is anticipated to last 3 months; if requested by the City, preparation of documents (i.e. addenda, bid tabulation, etc.) shall generally occur within two business days of request; other services (i.e. conduct Pre-bid meeting, conduct bid opening, attend council meeting, etc.) shall be provided at the respective scheduled times. • Construction Phase is anticipated to last 3 months; if requested by the City, review of/response to Contractor submittals shall generally be provided within five business days of receipt; response to Contractor BFI's and City/citizen questions shall generally be provided within one business day of receipt; preparation of record drawings shall occur within ten business days; other services (i.e. conduct Pre -construction conference, visits to the construction site, walk-through, etc.) shall be provided at the respective scheduled times. No services shall be provided after July 1, 2016. ADDENDUM TO EXHIBIT D Fee Schedule Delete in entirety the Fee Schedule contained in Exhibit D of the original contract between the City of Round Rock and MWM DesignGroup dated September 18, 2015 and replace with the following: Task Total Labor Hours Total Loaded Labor Cost Other Direct Costs Sub - consultants TOTALS Original Contract Task 1: Project Management 12 $1,670.00 $0.00 $0.00 $1,670.00 Task 2: Hydrologic Evaluation 36 $7,204.00 $0.00 $0.00 $7,204.00 Task 3: Prepare Detailed Design Drawings 116 $12,424.00 $0.00 $0.00 $121424.00 Task 4: Tech Specs and Prepare Bid Form 18 $2,150.00 $0.00 $0.00 $29150.00 Task 5: Design Phase Submittals and Meetings 20 $2,736.00 $500.00 $0.00 $3,236.00 Task 6: Opinion of Probable Cost 10 $1,318.00 $0.00 $0.00 $19318.00 Task 7: Biddding and Construction Phases 66 $5,507.00 $0.00 $0.00 $59507.00 Subtotal: 278 $33,009.00 $500.00 $0.00 $33,509.00 Supplemental Agreement No. 1 Task 1: Project Mangement 2 $350.00 $0.00 $0.00 $350.00 Task 2: Hydrologic Evaluation 9 $19143.00 $0.00 $0.00 $1,143.00 Task 3: Prepare Detailed Design Drawings 39 $4,200.00 $0.00 $0.00 $4,200.00 Task 4: Tech Specs and Prepare Bid Form 4 $538.00 $0.00 $0.00 $538.00 Task 7: Bidding and Construction Phases 9 $1,168.00 $0.00 $0.00 $1,168.00 Subtotal: 63 $7,399.00 $0.00 $0.00 $79399.00 AMMENDED GRAND TOTAL: 341 $40,058.00 $500.00 $0.00 $40,908.00 City of Round Rock JR UND ROCK TEXAS Agenda Item Summary Agenda Number: Title: Consider executing Supplemental Contract No. 1 with MWM DesignGroup for the Greenlawn Storm Drain Project. Type: City Manager Item Governing Body: City Manager Approval Agenda Date: 12/11/2015 Dept Director: Michael Thane, Director of Utilities and Environmental Services Cost: Indexes: Attachments: ESC—Greenlawn Storm Drain SA No. 1_12.7.15.pdf, LAF_Greenlawn Storm Drain SA No. 1_12.7.15.pdf� Greenlawn@GattisStormDrain.jpg Department: Utilities and Environmental Services Text of Legislative File CM -2015-1000 Consider executing Supplemental Contract No. 1 with MWM DesignGroup for the Greenlawn Storm Drain Project. The City previously entered into an Engineering Services Contract with MWM DesignGroup to design storm drainage system improvements in the vicinity of the intersection of Greenlawn Boulevard and Gattis School Road. These improvements will help with alleviating flooding that has been experienced in the past at the intersection; and at the commercial properties immediately to the northeast of the intersection. Based on the analysis already undertaken by MWM, it appears that extending the previously contemplated storm drainage system north to the intersection of Greenlawn Boulevard and Parkside Circle would provide better storm water capture resulting in a more effective project. This supplemental contract will provide the additional engineering services required for the storm drainage system extension. The original Engineering Services Contract provided for a maximum payment of $33,509; this supplement will increase the contract to a maximum of $40,908. Staff recommends approval. City of Round Rock Page 1 Printed on 12/10/2015