CM-2015-1000 - 12/11/2015STATE OF TEXAS §
COUNTY OF WILLIAMSON §
SUPPLEMENTAL CONTRACT NO. 1
TO CONTRACT FOR ENGINEERING SERVICES
FIRM: MWM DESIGNGROUP ("Engineer")
ADDRESS: 305 E. Huntland Drive, Suite 200, Austin, TX 78752
PROJECT: Greenlawn Storm Drain
This Supplemental Contract No. 1 to Contract for Engineering Services is made by and between
the City of Round Rock, Texas, hereinafter called the "City" and MWM DesignGroup,
hereinafter called the `'Engineer".
WHEREAS, the City and Engineer executed a Contract for Engineering Services, hereinafter
called the "Contract", on the 18th day of September, 2015 for the Greenlawn Storm Drain
Project in the amount of $33,509.00; and
WHEREAS, it has become necessary to amend the Contract to modify the provisions for the
scope of services and to increase the compensation by $7,399.00 to a total of $40,908.00;
NOW THEREFORE, premises considered, the City and the Engineer agree that said Contract
is amended as follows:
Article 2, Engineering Services and Exhibit B, Engineering Services shall be amended as set
forth in the attached Addendum To Exhibit B. Exhibit C, Work Schedule shall be amended as
set forth in the attached Addendum To Exhibit C.
II.
Article 4, Compensation and Exhibit D, Fee Schedule shall be amended by increasing by
$7,399.00 the lump sum amount payable under the Contract for a total of $40,908.00, as shown
by the attached Addendum to Exhibit D.
IN WITNESS WHEREOF, the City and the Engineer have executed this Supplemental
Contract in duplicate.
Su l
I " j am_ 10 C)
emental Contract
PP
0199.1544; 00347604
Rev. 12/01/08
84275
Date
CITY ROUND CK qSteph
ED AS TO ORM:
Gc0
. Sheets, City Attorney
Date
Supplemental Contract Rev.12101/08
0199.1544;00347604 84275
ADDENDUM TO EXHIBIT B
Engineering Services
The City is considering expanding the limits and type of storm system previously contemplated for this
project. Therefore, Exhibit B in the original contract between the City of Round Rock and MWM
DESIGNGROUP dated September 18, 2015 shall be amended as delineated below.
1. Delete the paragraph under 1. PROJECT DESCRIPTION and replace with the following:
Herein below is a detailed description of professional design, bidding, and construction phase
services for the Greenlawn Storm Drain Improvements Project. The project location extends
south approximately 200 feet along Greenlawn Boulevard from the intersection of Parkside
Circle and Greenlawn Boulevard, turns to the east behind the shopping center, and terminates at
Dry Branch Tributary No. 1. The project is anticipated to include inlets on Greenlawn Blvd,
approximately 365 linear feet of stormdrain, 750 linear feet of concrete lined channel, an outfall
at Dry Branch Tributary No. 1, and associated junction boxes and appurtenances. In addition,
the project also includes pavement removal and overlay on Greenlawn Boulevard from
Parkside Circle to Gattis School Road.
2. Delete the bulleted list under 2. SCOPE OF WORK and replace with the following:
• Task 1: Project Management
• Task 2: Hydrologic Evaluation
• Task 3: Prepare Detailed Design Drawings
• Task 4: Select Technical Specifications and Prepare Bid Form
• Task 5: Design Phase Submittals and Meetings
• Task 6: Opinion of Probable Cost
• Task 7: Bidding and Construction Phases Services
3. Delete the last two sentences under 2.1.2. Task 2: Hydrologic Evaluation and add
the following:
If the City desires, the Engineer will provide more detailed drainage area delineation,
analysis, and modeling as required to accurately design the various improvements.
4. Delete the last sentence under 2.1.3. Task 3: Prepare Detailed Design Drawings
and replace with the following:
It is anticipated that the plan set will include up to 14 sheets.
5. Add the following to 2.1.4. Task 4: Select Technical Specifications and Prepare
Bid Form:
2.1.4.3 If directed by the City, the Technical Specifications selection and Bid Form
preparation shall include items for milling and overlay of the Greenlawn
Boulevard pavement generally from Gattis School Road to Parkside Circle.
ADDENDUM TO EXHIBIT C
Work Schedule
Exhibit C in the original contract between the City of Round Rock and MWM DESIGNGROUP
dated September 18, 2015 shall be deleted and replaced with the following:
Following the effective date of a Notice to Proceed issued by the City authorizing services, the
Engineer will provide the authorized services as scheduled below.
• 50% Design Submittal — three weeks following receipt of surveying information to be
supplied by the City.
• 100% Design Submittal — two weeks following receipt of 50% Design Submittal
comments from the City.
• Bidding Phase is anticipated to last 3 months; if requested by the City, preparation of
documents (i.e. addenda, bid tabulation, etc.) shall generally occur within two business
days of request; other services (i.e. conduct Pre-bid meeting, conduct bid opening, attend
council meeting, etc.) shall be provided at the respective scheduled times.
• Construction Phase is anticipated to last 3 months; if requested by the City, review
of/response to Contractor submittals shall generally be provided within five business days
of receipt; response to Contractor BFI's and City/citizen questions shall generally be
provided within one business day of receipt; preparation of record drawings shall occur
within ten business days; other services (i.e. conduct Pre -construction conference, visits
to the construction site, walk-through, etc.) shall be provided at the respective scheduled
times.
No services shall be provided after July 1, 2016.
ADDENDUM TO EXHIBIT D
Fee Schedule
Delete in entirety the Fee Schedule contained in Exhibit D of the original contract between the City of
Round Rock and MWM DesignGroup dated September 18, 2015 and replace with the following:
Task
Total
Labor
Hours
Total
Loaded
Labor Cost
Other
Direct
Costs
Sub -
consultants
TOTALS
Original Contract
Task 1: Project Management
12
$1,670.00
$0.00
$0.00
$1,670.00
Task 2: Hydrologic Evaluation
36
$7,204.00
$0.00
$0.00
$7,204.00
Task 3: Prepare Detailed Design Drawings
116
$12,424.00
$0.00
$0.00
$121424.00
Task 4: Tech Specs and Prepare Bid Form
18
$2,150.00
$0.00
$0.00
$29150.00
Task 5: Design Phase Submittals and
Meetings
20
$2,736.00
$500.00
$0.00
$3,236.00
Task 6: Opinion of Probable Cost
10
$1,318.00
$0.00
$0.00
$19318.00
Task 7: Biddding and Construction Phases
66
$5,507.00
$0.00
$0.00
$59507.00
Subtotal:
278
$33,009.00
$500.00
$0.00
$33,509.00
Supplemental Agreement No. 1
Task 1: Project Mangement
2
$350.00
$0.00
$0.00
$350.00
Task 2: Hydrologic Evaluation
9
$19143.00
$0.00
$0.00
$1,143.00
Task 3: Prepare Detailed Design Drawings
39
$4,200.00
$0.00
$0.00
$4,200.00
Task 4: Tech Specs and Prepare Bid Form
4
$538.00
$0.00
$0.00
$538.00
Task 7: Bidding and Construction Phases
9
$1,168.00
$0.00
$0.00
$1,168.00
Subtotal:
63
$7,399.00
$0.00
$0.00
$79399.00
AMMENDED GRAND TOTAL:
341
$40,058.00
$500.00
$0.00
$40,908.00
City of Round Rock
JR
UND ROCK
TEXAS Agenda Item Summary
Agenda Number:
Title: Consider executing Supplemental Contract No. 1 with MWM DesignGroup
for the Greenlawn Storm Drain Project.
Type: City Manager Item
Governing Body: City Manager Approval
Agenda Date: 12/11/2015
Dept Director: Michael Thane, Director of Utilities and Environmental Services
Cost:
Indexes:
Attachments: ESC—Greenlawn Storm Drain SA No. 1_12.7.15.pdf, LAF_Greenlawn
Storm Drain SA No. 1_12.7.15.pdf� Greenlawn@GattisStormDrain.jpg
Department: Utilities and Environmental Services
Text of Legislative File CM -2015-1000
Consider executing Supplemental Contract No. 1 with MWM DesignGroup for the
Greenlawn Storm Drain Project.
The City previously entered into an Engineering Services Contract with MWM
DesignGroup to design storm drainage system improvements in the vicinity of the
intersection of Greenlawn Boulevard and Gattis School Road. These improvements will
help with alleviating flooding that has been experienced in the past at the intersection;
and at the commercial properties immediately to the northeast of the intersection.
Based on the analysis already undertaken by MWM, it appears that extending the
previously contemplated storm drainage system north to the intersection of Greenlawn
Boulevard and Parkside Circle would provide better storm water capture resulting in a
more effective project. This supplemental contract will provide the additional
engineering services required for the storm drainage system extension.
The original Engineering Services Contract provided for a maximum payment of
$33,509; this supplement will increase the contract to a maximum of $40,908.
Staff recommends approval.