Loading...
CM-09-10-207CITY OF ROUND ROCK QUANTITY ADJUSTMENT / CHANGE ORDER PAGE 1 OF 3 DEPT: Water & Wastewater Utilities DATE: PROJECT: Water Treatment Plant Rehabilitation - Phase IV Sludge ORDER NO: 1 Collection Equipment Retrofits JUSTIFICATION: ORIGINAL CONTRACT PRICE: PREVIOUS QUANTITY ADJUSTMENTS: PREVIOUS CHANGE ORDERS: CURRENT CONTRACT PRICE: $194,400.00 $0.00 $6,904.00 $201,304.00 (see attachments) QUANTITY ADJUSTMENT D /1�' YAAAR::\Utilities\Utility Administration\CIP - PROJECTS\WTP Rehab Phase IV Sludge Col\Excel Construction\CO#1_WTP-PhIV- 1'lY`O° 10„ Sludge_Excel_10-7-09_DRAFT.xls ITEM # DESCRIPTION OF CHANGES UNIT QTY. UNIT PRICE AMOUNT ADDED DAYS CALENDAR/ WORKING N/A N/A N/A TOTAL: $o.00 0 /1�' YAAAR::\Utilities\Utility Administration\CIP - PROJECTS\WTP Rehab Phase IV Sludge Col\Excel Construction\CO#1_WTP-PhIV- 1'lY`O° 10„ Sludge_Excel_10-7-09_DRAFT.xls CITY OF ROUND ROCK QUANTITY ADJUSTMENT / CHANGE ORDER PAGE2OF3 CHANGE ORDER R:\Utilities\Utility Administration\CIP - PROJECTS\WTP Rehab Phase IV Sludge Col\Excel Construction\CO#1_WTP-PhIV- Sludge_Excel_10- 7- 09 DRAFT. xls ITEM # DESCRIPTION OF CHANGES UNIT QTY. UNIT PRICE AMOUNT ADDED DAYS CALENDAR/ WORKING 1 Costs associated with changing out hardware for stainless steel hardware and grouting of the track brackets Labor Foreman HR 12 $32.00 $384.00 Laborer HR 16 $21.50 $344.00 Laborer HR 16 $21.50 $344.00 Superintendent HR 4 $75.00 $300.00 Materials SS 5/8" Replacement Nuts LS 1 $56.00 $56.00 NS Grout EA 8 $11.00 $88.00 Sub -Total $1,516.00 15% OHP $227.40 Item #1 Total $1,743.40 2 Snap Idle Chain Tension Brackets w/ shipping EA 2 $255.00 $510.00 Shipping $11.25 $11.25 Item #2 Total $521.25 Costs associated with adjusting the 3 clarifiers due to existing grading conditions in the basins Labor 5 Laborers @ 32hrs each = 160hrs HR 160 $21.50 $3,440.00 Superintendent HR 16 $75.00 $1,200.00 Item #3 Total $4,640.00 TOTAL: $6,904.65 0 R:\Utilities\Utility Administration\CIP - PROJECTS\WTP Rehab Phase IV Sludge Col\Excel Construction\CO#1_WTP-PhIV- Sludge_Excel_10- 7- 09 DRAFT. xls CITY OF ROUND ROCK QUANTITY ADJUSTMENT / CHANGE ORDER PAGE 3 OF 3 SUMMARY CURRENT CONTRACT PRICE: $194,400.00 THIS QUANTITY ADJUSTMENT: N/A SUB -TOTAL: N/A PREVIOUS CHANGE ORDER(S): $0.00 THIS CHANGE ORDER: $6,904.00 TOTAL CHANGE ORDER(S): $6,904.00 TOTAL % CHANGE ORDER: 3.55% ADJUSTED CONTRACT PRICE: $201,304.00 PREPARED BY: SIGNATURE: NAME OF CONTRACTOR: SIGNATURE: Kevin Wenske I°lsr-tope Excel Construction Services, LLC DATE / • PRINT NAME/TITLE: fit-rri Dieto-rn. APPROVED: %, 11 CI74Y OF ROUND ROCK eb'KM use., P.E . - C►'-4-TMan.. R:\Utilities\Utility Administration\CIP - PROJECTS\WTP Rehab Phase IV Sludge Col\Excel Construction\CO#1_WTP-PhIV- Sludge_Excel 10-7-09 DRAFT. xls Construction Meeting Summary No. 2 Round Rock Water Treatment Plant Phase IV Sludge Collection Equipment Retrofits Meeting Started: Meeting End: Meeting Room: 10:00 a.m. 10:30 a.m. T/U Conference Room SUMMARY CONSTRUCTION MEETING NO. 2 2009 WATER TREATMENT PLANT REHABILITATION PROJECT PHASE IV SLUDGE COLLECTION EQUIPMENT RETROFITS JUNE 16, 2009 DISTRIBUTION: Jeff Bell Steve Lynk Kevin Wenske Jennifer Higby A. REVIEW AND APPROVAL OF PREVIOUS CONSTRUCTION MEETING SUMMARY 1. CDM noted that the Meeting #1 was documented as part of the HSPS Improvements Project, Post Meeting. B. STATUS OF WORK C. JOB SCHEDULE 1. Time of Completion Contractual a. Notice to Proceed Issued: 5/15/08 b. Substantial Completion: 8/16/09 c. Final Completion: 9/15/09 2. Two Week Schedule 3. Shop Drawing Schedule 4. Schedule of Values 5. CPM Schedule: a. All shafts have been removed and are to be hoisted out in the following days, per Excel/Wenske. b. Wear -strip holes have been drilled c. The supplier informed Excel that materials are to ship on 6/23 and 6/24 D. DESIGN QUESTIONS 1. RFI Status: _1_ Received and _0_ Answered a. Average RFI Review Time of _Days 1. RFI regarding turning over sprockets as spare parts - CORR/Bell provided a verbal approval, with the stipulation that the main drive sprockets must be compatible. 2. Field Order Status: _0_ Issued and _0_ Executed 3. Submittal Status: 4 Received and 4 Answered a. Average Submittal Review Time of _ Days b. O&M Manuals — Excel to submit 4 to CDM for review purposes. CDM to contact CORR/Lutz (or CORR/Bell) to obtain their O&Ms, in order to update them with the final materials. 4. Change Proposals/Orders: Review CPR Log: a. Upcoming CPRs . . 1) In Basin 4.2, not all of the hardware is stainless steel. Per CDM/Lynk and CORR/Bell, this hardware needs to be replaced. Verbal direction provided during meeting for Excel to perform this work on a T&M Basis. 5. Miscellaneous a. Pay Application Status — First Pay Application will not be submitted until parts have been received and installed, per Excel/Wenske. E. MISCELLANEOUS Page 1 of 2 File: CORR Phase IV Summary Mtg #2 6-16-09.doc w. imte EXCE COr1STRUCTIOr1 SERVICES LLC July 15, 2009 Mr. Steven Lynk, P.E. Camp Dresser & McKee 12357-A Riata Trace Parkway, Ste 210 Austin, Texas 78727 RE: Request for Change 001 — Replace Rusted Hardware / Grout Flight Brackets City of Round Rock 2009 WTP Rehab Project — Phase IV Sludge Collection Retro Dear Mr. Lynk: Excel Construction Services is pleased to offer the following proposal for the replacement of rusting hardware and grouting of existing flight track return rails at Basin 4. Work included removal of flight track, remove / install new SS backing nuts at track brackets, reinstall track, straighten and grout behind brackets. Excel Construction performed this work on a time and material basis. See attached backup for a breakdown of cost. Total Cost for Replacing Hardware and Grouting Brackets $1,743.00 We also replaced two drive chain tension brackets (Snap Idle Model #180) that were either broken or removed. Only the cost for the materials and shipping is included. Total Cost for Snap Idle Chain Tension Brackets w/ Shipping TOTAL COST FOR RFC -001 $521.25 $2,264.25 If you have any additional questions or comments, don't hesitate to contact me at 848-2419. Regards, Excel Construction Services, LLC K. 14/444e Kevin Wenske Project Manager cc: 1202 Leander Drive Phone (512) 259-5005 Leander, Texas 78641 Fax (512) 259-5665 WORK PROPOSAL COST ITEMIZATION: RFC 001 Round Rock 2009 WTP Improvements Sludge Collection Equipment Retrofit July 15, 2009 units quantity I unit cost total A) LABOR 1. Arnold Cruz - Foreman HR 12 $ 32.00 $ 384.00 2. Luis Silva - Labor HR 16 $ 21.50 $ 344.00 3. Angel Vasquaz - Labor HR 16 $ 21.50 $ 344.00 4. Don Henderson - Superintendent HR 4 $ 75.00 $ 300.00 5. $ - 6. $ - B) MATERIALS 1. SS 5/8" Replacement Nuts LS 1 $ 56.00 $ 56.00 2. NS Grout EA 8 $ 11.00 $ 88.00 3. $ - 4. $ - 5. $ - 6. $ - 7 $ - 8. $ - Sub -Total $ 1,516.00 15% OHP $ 227.40 TOTAL $ 1,743 rr aux BILL TO ROUND ROCK BRANCH CAPITOL BEARING SERVICE 2689 OAKMONT PHONE 612-244.2248 ROUND ROCK, TX 78864 004401 EXCEL CONSTRUCTION SRVS LLC 1202 LEANDER DR LEANDER, TX 78641 REMIT TO CAPITOL BEARING SERVICE P.O. BOX 190 ROUND ROCK TX. 78880-00180 SHIP TO Invoice INVOICE # 2130584 LOCATION 02 DATE 07/08/09 PAGE 1 OF 1 r EXCEL CONSTRUCTION SRVS LLC 1202 LEANDER DR. ***PO # REQUIRED*** LEANDER, TX 78641 ORDER NUMBER 232717 ORDER DATE 07/01/09 CUSTOMER WO NUMBER 9-013 PAYMENT TERMS NET 30 DAYS WRITTEN BY JIMMY GRIMES CONTACT KEVIN 848-2419 SHIP VIA CUSTOMER PICK-UP FREIGHT TERMS DETERMINE CHARGES JOB NUMBER SALES REP HOUSE :.: ..: ::. �:::.�::::::•::::.;::::.:.:.:::::::. •::Attri ....... Y ..4 ?... 4 11�#sl,.. X.....:• :•::•::.;•...........::.: •....... 1- I OV SNAP IDLE Picked Up/Received by: 0 7 2 2 0 255.00 EA 510.00 MERCHANDISE TOTAL HANDLING MISC CHARGE TAX FREIGHT DEPOSIT AMOUNT DEPOSIT APPLIED INVOICE TOTAL 510.00 0.00 0.00 0.00 11.25 0.00 0.00 ::f DATE: October 14, 2009 SUBJECT: City Manager Approval — October 16, 2009 ITEM: Consider executing Quantity Adjustment/Change Order No. 1 with Excel Construction Services, LLC for the Water Treatment Plant Rehab - Phase IV Sludge Collection Equipment Retrofits Project. Department: Staff Person: Justification: Water & Wastewater Utilities Michael D. Thane, P.E., Director of Utilities This Change Order No. 1 is for the costs associated with exchanging the rusting hardware with stainless steel hardware, grouting the track brackets, and adjusting the clarifiers due to existing grading conditions in the basins. Work included removal of flight track, removing and installing of new stainless steel backing nuts at track brackets, re -installation of track, straightening and grouting behind brackets, and replacing two drive chain tension brackets that were either broken or removed. Funding: Cost: $6,904.00 Source of funds: Self -Financed Water Construction Amount % Change Original Contract $194,400.00 N/A Change Order # 1 $6,904.00 3.55% Revised Contract $201,304.00 3.55% Outside Resources: Excel Construction Services, LLC (Contractor) Camp Dresser & McKee, Inc. (Engineering Consultant) Background Information: Several projects at the City's Water Treatment Plant are in various phases that will enable the City to treat and distribute its full amount of reserved raw water. One of the projects is the 7.5 MG High Service Pump that has just been completed by Excel Construction. Other projects include the rehabilitation of the plant's process structures, the construction of a climatic - controlled MCC Room for High Service Pumps 1 through 6, and the additional 1.5 MG Clearwell. With TCEQ's approval of the plants re -rating, the plant will be able to provide a firm 52 mgd of potable water to our distribution system by the summer of 2010 and into the future. Public Comment: N/A 5/12/1019 Request for City Council/City Manager Action Ei City Council El City Manager Submit completed form for all City Manager and City Council approvals. Department Name: Water & Wastewater Utilites Contact Person: Chaz Gordon / Kathy Michna For Administration Use ONLY Received: Tag #: IiY1-09- IQ_ 207 Original Documents Received: 2_ Water Treatment Plant Rehab - Phase N Sludge Collec9m Equipment Project Name: Retrofits ContlactorNendor. Excel Construction Services, LLC Project Mgr/Resource: Don Runde!' Funding Source: Sen -Financed Water Construction Project Coordinator. Wheel Thane Additional funding Source: Assigned Attorney: Steve Sheets Amount Account Number: City Council or City Manager Approval Date: Agenda Wording 10/16/2009 6,90400 Consider executing Quantity Adjustment/Change Order No. 1 with Excel Construction Services, LLC for the Water Treatment Plant Rehab - Phase IV Sludge Collection Equipment Retrofits Project. Finance Information Is Funding Required? Yes Q No Initial Construction Contract O Construction Contract Amendment # Q Change Order # t 11JChange in Quantity JlJUnforeseen Circumstances ED Initial Professional Services Agreement ED Supplemental Professional Service Agreement ED Purchasing/Service Agreement Purchase Order Item(s) to be purchased Other (Please clearly identify action on lines below) Amount 6,904.00 FINANCE N/A Appored E CI ElC CI 0 Finance/CIP Finance/Acct Purchasing Budget Date Date Date Date APPROVALS (robe completed ONLY by Finance) Final Finance Approval Required APProved Finance Director Once approvals have been obtained. please forward the RFA. blue sheet. backup information and originals to City Secretary, Sara White. ITEMS WILL NOT BE PLACED ON THE COUNCIL AGENDA WITHOUT FINANCE AND LEGAL APPROVAL PRIOR TO SUBMISSION. uired •r u mi on !f LC Project Mgr. Signature: Dept. Director Signature: 'City Attorney Signature: City Manager Signature: Date: Date: in -16-09 10' 1!0'09 City Attorney signature is required for all items. Date REVISED 10/9/2009 5/12/2009 Request for City CounciUCity Manager Action 0 City Council n City Manager Submit completed foes for all City Manager and City Council approvals. For Administration Use ONLY Received: Tag #: Original Documents Received: Water Treatment Plant Rehab - Phase IV Sludge Collection Equipment Department Name: Water & Wastewater Utilites Project Name: Retrofits Contact Person: Chaz Gordon / Kathy Michna ContractorNendor: Excel Construction Services, LLC Project Mgr/Resource: Don Rundell Funding Source: Self -Financed Water Construction Project Coordinator: Michael Thane Additional funding Source: Assigned Attomey: Steve Sheets Amount: Account Number: City Council or City Manager Approval Date: Agenda Wording 10/16/2009 6,904.00 Consider executing Quantity Adjustment/Change Order No. 1 with Excel Construction Services, LLC for the Water Treatment Plant Rehab - Phase IV Sludge Collection Equipment Retrofits Project. Finance Information Is Funding Required? Yes n No Initial Construction Contract Construction Contract Amendment Change Order Change in Quantity Initial Professional Services Agreement Supplemental Professional Service Agreement Purchasing/Service Agreement Purchase Order Item(s) to be purchased Unforeseen Circumstances Other (Please clearly identify action on lines below) Amount 6,904.00 FINANCE WA Approved O O O APPROVALS (to be completed ONLY by Finance) Final Finance Approval Required Approved Finance/CIP B. Ramsey Date 10/13/2009 FinancefAcct E. Wilson Date 10/14/2009 Purchasing EE Bowden Date 10/14/2009 Budget P. Bryan Date 10/13/2009 Cheryl Delaney 10/13/2009 Finance Director Date Once approvals trave been obtained, please forward the RFA. blue sheet, back up information and originals to City Secretary, Sara White. ITEMS WILL NOT BE PLACED ON THE COUNCIL AGENDA WITHOUT FINANCE AND LEGAL APPROVAL. PRIOR TO SUBMISSION. Required for Submission of ALL City Council and City Manager Items Project Mgr. Signature: Dept. Director Signature: *City Attorney Signature: City Manager Signature: Date: Date: Date: Date: *City Attorney signature is required for all items. REVISED 10/14/2009 LEGAL DEPARTMENT APPROVAL FOR CITY COUNCIL/CITY MANAGER ACTION Required for Submission of ALL City Council and City Manager Items Department Name: PW/Utilities Project Mgr/Resource: Don Rundell Council Action: ORDINANCE Agenda Wording Water Treatment Plant Rehab - Phase IV Sludge Project Name: Collection Equipment Retrofits ContractorNendor: Excel Construction Services, LLC ri RESOLUTION City Manager Approval CMA Wording Consider executing Quantity Adjustment/Change Order No. 1 with Excel Construction Services, LLC for the Water Treatment Plant Rehab - Phase IV Sludge Collection Equipment Retrofits Project. Attorney Approval Attorney Notes/Comments Date O:1wd oxlS CC In t s10199171141M I S C100173414.XLS Updated 6/3/08