Loading...
CM-09-10-215Change Order No. 2 Project Name: RM 1431 — 2.0 MG Elevated Water Storage Consultants Project No.: 74095 Tank Project Owner: City of Round Rock, Texas 212 Commerce Cove, Round Rock, TX 78664 Date of Issuance: September 29, 2009 Project Contractor: Landmark Structures I, L.P. Date of Contract: July 29, 2008 Date of Notice to Proceed: July 21, 2008 Original Completion Date: January 12, 2010 Contract Period: 540 Calendar Days It is agreed to modify the Contract referred to above as follows: CPR # ITEM AND DESCRIPTION OF CHANGES CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME 8 Install a sink and drain line for sample water handling, and install sample line insulation. $4,500.00 0 9 Install a sample water pipe header, isolation ball valves, and a second utility line to the sink. $190.00 0 Attach each approved CPR to this form Difference Net $4,690.00 0 Summary: It is agreed to modify the Contract referred to above as follows: Contract Price prior to this Change Order Contract Time prior to this Change Order $ 4,220,803.00 Net (increase) / (decrease) with this Change Order $ 4,690.00 Revised Contract Price with all approved Change Orders $ 4,225,493.00 540 calendar days — January 12, 2010 Net (increase) / (decrease) with this Change Order 0 days Revised Contract Time with all approved Change Orders 540 calendar days - January 12, 2010 The changes included in this Change Order are to be accomplished in accordance with the terms, stipulations and conditions of the original Contract as though included therein. Accept -d for Contractor b : Recomme d for Approval by ( Consulting Firm's Name ): HDR Engineering, Inc. A. proved for Owner by: Attest: (if required) afAL Distribution: wner ❑ Contractor ❑ Office Z'07225-74095 CO R- 43' _. CA';03.vO Cods ruo `c`'_ apt Fqu iert _Cont -ac DI_ ACK doc (�1�1•t�l•Ih.�l� Date: to/ -ib, Date: 9/ZVo ? Date: Date: !D •/5 • 6 ❑ Field El Other Ordcrs_and_CPRs ,hange CSI, Fi by chance Order, the time of completion will be: 3'p wan.V 14, ZotO XIncreased _ Decreased _ Unchanged by Z. calendar days. Change Proposal Request No. 8 (Not a Change Order) u' mme d d _ Do Not Recommend Acceptance .0 L. By: HDR L 4 2 / Date The change will: XA i, Deduct _ Not e,Jrges Action:s„ S-_ , 415t�D, oc i171;; . t: zotvg ileviAg) Contratft. By: tzw„er Pete 8)Z1 b' pate 30 aq FORM P 0-3 thitU*, Copp* 1991 Halt Bisloadriss. 1u. Task IO10 1 o Discharge Structure I i I 1180 00° 0 16" Overflow •'- Foundation Outline 90.000 Lift Slag (typ. of 46) Taper Tie @ 7.50° 24" Wet LS.114 t< 1 — ,-......-„, ,. "7 ji.$).9 ............ t 1 .. 0,.. 4, •••,P *) ••• * . - / JOHN E. GRENDZINSK1 of fiNt...),:et.:../c.E...N.10...'Doeyn,1 _as _ag LANniviAmIC)" b, %Nu . ' .4.' — - — — 1 Landmark Structures I, LP 1665 Harmon Road Fort Worth, Texas. 76177 Tel: (817) 439-8888 Fax: (817) 439-9001 12'-0" Wx 12'-0" H Overhead Door 0.00° g- Tank 24" Outlet C-01/ / 3-0" W x T-0" H Single Door Exterior Bollards (typ. of 2) 24" Watermain Project CITY OF ROUND ROCK, TX 2.0 MG ELEVATED WATER STORAGE TANK E 22/Jan(09 KKC Top Landing Angle / Piping Material to S.S. 29/Oct/08 KKC Scaffold Angle arision: GENERAL ARRANGEMENT FOR CONSTRUCTION Centrecton D. SY KKC IMZ 1238 1""d6'131'/ 08 Soak: N.T.S. On. Nontbon 500 -A ISOLATION BALL VALVE, TYP. EACH SAMPLE LINE SERVICE SINK SAMPLE LINE, TYP. 1 LO --- WALL FINISH FLOOR 1I TO DRAIN s'a� t pkv` l4 ray ,. 9it'll/wk "►-�� r ('-c-r�,� SIDE VIEW - z FRONT VIEW SERVICE SINK NOT TO SCALE FER Grainger Industrial Supply Page 1 of 3 �rRAINGRR . I r Id: aou tetaoxes wa<o arr rrwa�� printed July 21, 2009 Additional Info Utility and Mop Sinks Utility Sink,Thermoplastic,With Legs Utility Sink, Thermoplastic, Overall Length 20 in., Overall Width 24 In., Overall Height 34 In., Single Bowl, Bowl Size 24 x 20 x 13D In., Mounting Type Floor, Faucet Mounting Centers 4 In., Number of Holes 2, Drain Opening 1 1/2 in., White Color/Finish, Standards IAPMO, ANSI Specification 124.6, And CSA, Includes Adjustable Leg Levelers Grainger Item # 1RLN7 Price (ea.) $82.95 E.L. MUSTEE & SONS, INC Mfr. Model # 19f Ship Qty. 1 Sell Qty. (Will -Call) 1 Brand Ship Weight (lbs.) 18.72 Usually Ships Today Catalog Page No. 3498 Price shown may not reflect your price. Log in or register. Utility Thermoplastic sinks have heavy -gauge metal legs with adjustable leg levelers. Meet IAPMO and ANSI 124.6 specifications. CSA Certified. No. 1 RLN8 includes everything needed for installation. Stainless steel sinks are made of 16-ga. 430 SS. Heavy -gauge galvanized legs are directly under the sink bowls for maximum security and weight support. Corrosion -resistant bullet feet are adjustable. No. 1JYR5 drainboard can be attached to either side of the sink (order separately). Tech Specs Item: Utility Sink Material of Construction: Thermoplastic Overall Length (In.): 20 Overall Width (In.): 24 Overall Height (In.): 34 Bowl: Single Bowl Size (In.): 24 x 20 x 13D Mounting Type: Floor Faucet Mounting Centers (In.): 4 Number of Holes: 2 Drain Opening (In.): 1 1/2 Color/Finish: White ADA Compliant: No Standards: IAPMO, ANSI Specification 124.6, And CSA Includes: Adjustable Leg Levelers Optional Accessories J Bend,20 Gauge,Brass,Pipe Dia 1 1/2 In Item #: 1PNL9 Brand: APPROVED VENDOR Usually Ships: Today Price (ea): $10.45 P Trap,20 Gauge,Brass,Pipe Dia 1 1/2 In Item #: 1PNN5 Brand: APPROVED VENDOR Usually Ships: Today Price (ea): $20.40 http://www, grainger. com/Grainger/wwg/iternDetails.shtinI 7/21 /2009 MUSTEE 19F UTILATUB® Laundry/Utility Tub E. L. Mustee & Sons, Inc. 5431 West 164th Street Brookpark, OH 44142 Phone: 216.267.3100 Fax: 216.267.9997 Email: info@mustee.com Web: www.mustee.com Premier 19F and 19W UTILATUB® • Sturdy, 1 -Piece, Extra Deep Molded Tub • Made with Structural Thermoplastic — innovative cellular molding process makes these white tubs "literally indestructible" • 18 Gallon Capacity, 13" Deep • Leakproof, Integrally Molded -in Drain with Stopper • Hooks Up to Standard 1-1/2" P or S Trap • Accommodate Dual -handle Faucet with 4" Center • Floor Model Includes Adjustable Leg Levelers for Uneven Floors • Wall Model Includes Wall Mounting Bracket, Side Supports and Hardware for Securing Tub to Concrete or Stud Wall • Smooth Surface, Rust Resistant • Easy to Assemble and Install • Preferred by the "Pros" Code Accepted utility sinks meet or exceed performance requirements: • International association of plumbing and mechanical officialsri i (iapmo®)— listed file #0635 • Warnock hersey® (canada) — csa #b45.0 and #b45.5 — NehMi.ff sf'.-.a #B125 ■ American national standards institute (ansi)— specification z 124.6 SPECIFICATIONS Model No. Mounting UPC 19F Floor 6 71031 00029 3 Download instructions 1 143/8 34' APPROX Situ taw • • 111n11lvad nlati uCt1O1a MOUNTING BRACKET 11/2' LEVEL ADJUSTMENT Floor 34" FILLER APPROX PANELS FLOOR Wall Top View 71/2' } 20" General: Furnish and install as shown on plans, UTILATUB® Laundry/Utility Tub model (19F, 19W), as manufactured by E.L. Mustee & Sons, Inc. Tub shall be one-piece molded construction using structural thermoplastic with matched metal molds under extreme heat and pressure. Tub to include integrally molded drain assembly, stopper and floor or wall mounting hardware. Shall meet ANSI Specification Z 124.6. White color. Weight: 19F 23 lbs.; 19W 20 lbs. GF Piping Systems Datasheet Schedule 80 PVC Pressure Pipe PVC Pressure Pipe - 20 ft. lengths valid from: 6/20/08 Size [inch] Plain End (P/L 46) Part No. Bell End (P/L 48) Part No. 3/4 1 114 > 1 '/z 2 21/2 3 -,r=c14-3 6 8 10 12 14 16 8008-005AB 8008-007AB 8008-010AB 8008-012AB 8008-015AB 8008-020AB 8008-025AB 8008-030AB 8008-040AB 8008-O60AB 8008-080AB 8008-100AB 8008-120AB 8008.140AB 8008-160AB 8008-005BB 8008-007BB 8008-010BB 8008-012BB 8008-015BB 8008-o20BB 8008-025BB 8008-030BB 8008-040BB 8008-060BB 8008-080BB 8008-100BB 8008-12OBB 8008-140BB 8008-160BB Size [inch] Lift Qty [ft] Average O.D. [inch] min. wall [inch] psi at 73° F A - Socket Entrance (Belled Pipe) B - Socket Bottom (Belled Pipe) C - Minimum (Belled Pipe) '/2 3/4 1 '/4 1'h 2 2'/] 4",,s5 / 4 6 8 10 12 14 16 5600 5000 2360 1960 1800 1060 880 700 520 220 100 80 60 60 60 0.840 1.050 1.315 1.660 1.900 2.375 2.875 3.500 4.500 6.625 8.625 10.750 12.750 14.000 16.000 0.147 0.154 0.179 0.191 0.200 0.218 0.276 0.300 0.337 0.432 0.500 0.593 0.687 0.750 0.843 848 688 630 520 471 404 425 375 324 279 246 230 230 220 220 0.848±0.004 1.058±0.004 1.325±0.005 1.670±0.005 1.912±0.006 2.387±0.006 2.889±0.007 3.516±0.008 4.518±0.009 6.647±0.011 8.655±0.015 10.776±0.015 12.778±0.015 14.035±0.015 16.045±0.015 0.836±0.004 1.046±0.004 1.310±0.005 1.655±0.005 1.894±0.006 2.363±0.006 2.861±0.007 3.484±0.008 4.482±0.009 6.603±0.011 8.598±0.015 10.722±0.015 12.721±0.015 13.985±0.015 15.980±0.015 1.000 1.250 1.500 1.750 2.000 2.250 2.500 3.250 4.000 6.000 6.000 7.500 8.500 9.000 10.000 The technical data are not binding and not expressly warranted characteristics of the goods. They are subject to change. Our General Conditions of Sale apply. Georg Fischer Rohrleitungssysteme AG, Postfach, CH -8201 Schaffhausen/Switzerland +GF+ Page 1 of 1 GF Piping Systems Datasheet Schedule 80 PVC Pressure Fittings 90° Ell (S x S) valid from 1/15/09 The technical data are not binding and not expressly warranted characteristics of the goods. They are subject to change. Our General Conditions of Sale apply. Georg Fischer Rohrleitungssysteme AG, Postfach, CH -8201 Schaffhausen/Switzerland +GF+ Page 1 of 1 Size [inch]m P/L Part No. Minimu Order Qty H [inch] G [inch] Design /. 08 806-002 50 0.95 0.33 HS 3/e 08 806-003 50 1.17 0.41 HS 1/2 08 806-005 25 1.41 0.50 SL '/, 08 806-007 25 1.61 0.56 SL 1 08 806-010 10 1.86 0.69 SL 1 1/4 08 806-012 10 2.16 0.91 SL G -->11/2 08 806-015 10 2.41 1.03 SL 2 08 806-020 20 2.78 1.28 SL 2 1/2 08 806-025 5 3.29 1.53 SL r-- 08 806-030 5 3.75 1.85 SL V A-% 4 08 806-040 5 4.60 2.34 SL 6 08 806-060 2 6.70 3.69 SL 8 08 806-080 1 8.67 4.59 SL 10 02 806-100 1 10.77 5.75 SL 12 02 806-120 1 12.64 6.06 SL 14 05 806-140H 1 23.75 16.75 FAB 16 05 806-160H 1 27.00 19.00 FAB The technical data are not binding and not expressly warranted characteristics of the goods. They are subject to change. Our General Conditions of Sale apply. Georg Fischer Rohrleitungssysteme AG, Postfach, CH -8201 Schaffhausen/Switzerland +GF+ Page 1 of 1 GF Piping Systems Datasheet valid from 4/6/09 Schedule 80 PVC Pressure Fittings Coupling (S x S) The technical data are not binding and not expressly warranted characteristics of the goods. They are subject to change. Our General Conditions of Sale apply. Georg Fischer Rohrleitungssysteme AG, Postfach, CH -8201 Schaffhausen/Switzerland +GF+ Page 1 of 1 Size [inch] P/L Part No. Minimu m Order Qty L [inch] N [inch] Design 1/4 08 08 08 08 08 08 08 08 08 08 08 08 08 02 02 05 05 829-002 829-003 829-005 829-007 829-010 829-012 829-015 829-020 829-025 829-030 829-040 829-060 829-080 829-100 829-120 829-140H * 829-160H * 50 50 25 20 25 10 10 20 5 5 5 2 2 2 1 1 1 1.39 1.64 1.93 2.18 2.41 2.64 2.90 3.14 3.75 4.04 4.79 6.41 8.40 10.55 12.54 17.63 19.88 0.14 0.14 0.13 0.13 0.13 0.12 0.13 0.12 0.16 0.25 0.25 0.34 0.34 0.49 0.50 3.63 3.88 HS HS SL SL SL SL SL SL SL SL SL SL SL SL SL FAB FAB N '/8 ' 3/4 1 , i _ 11/4 -› 11/2 2 21/2 w 4 6 8 10 12 14 16 The technical data are not binding and not expressly warranted characteristics of the goods. They are subject to change. Our General Conditions of Sale apply. Georg Fischer Rohrleitungssysteme AG, Postfach, CH -8201 Schaffhausen/Switzerland +GF+ Page 1 of 1 GF Piping Systems Datasheet valid from 2/2/09 Schedule 80 PVC Pressure Fittings Union (S x S) Size [inch] 1/4 3/8 1/2 3/4 ,r16efr 4 P/L 08 08 08 08 08 08 08 08 08 08 EPDM Part No. 897-002 897-003 897-005 897-007 897-010 897-012 897-015 897-020 897-030 897-040 FPM Part No. 857-002 857-003 857-005 857-007 857-010 857-012 857-015 857-020 857-030 857-040 M[nimu m Order Qty 25 25 25 10 10 5 10 2 1 1 L [inch] 1.61 1.91 2.31 2.58 2.89 3.23 3.44 3.77 4.74 5.62 N [inch] 0.76 0.77 0.95 1.08 1.25 1.32 1.32 1.51 2.00 2.05 The technical data are not binding and not expressly warranted characteristics of the goods. They are subject to change. Our General Conditions of Sale apply. Georg Fischer Rohrleitungssysteme AG, Postfach, CH -8201 Schaffhausen/Switzerland +GF+ Page 1 of 1 therma-cel® Seam -Seal Pipe Insulation Engineered Polymer Foam Insulation SYSTEM COMPATIBLE for VOCs Made in America DESCRIPTION therma-cel° Seam -Seal is a self- seal- ing, flexible, polyolefin, thermal insula- tion and is black in color. It is available in wall thicknesses of 3/8", 1/2", 3/4" and 1", in sizes ranging from 3/8" CTS to 4" IPS. APPLICATIONS therma-cel® Seam -Seal is used to retard heat gain and prevent conden- sation or frost formation on cold water plumbing, chilled -water and air condi- tioning lines. therma-cel® Seam -Seal also retards heat loss on hot water plumbing. therma-cel° Seam -Seal has a low thermal conductivity and very low water vapor transmission rate. This low density product demonstrates excellent thermal, physical and chemi- cal resistant properties and has a broad service temperature range between -330°F and 210°F (-201°C and 99°C). It can be installed in com- mercial, industrial and residential insu- lation projects. Acceptable for use with heat tracing/heat tape. INSTALLATION therma-cel® Seam -Seal is pre -slit with factory applied pressure sensitive adhesive (PSA) to both seam surfaces and has convenient built-in release tabs for easy installation: slip on the tube, pull the tab, and pinch it shut. It can be easily pushed around P -traps and fittings, though mitering is recom- mended for optimum performance. All butt joints should be sealed with 320 orp20 (black) Contact Adhesivelor other approved sealing system. t easily cut with a sharp knife. therma- cel® Seam -Seal is available in a wide range of I.D.s and is sized to fit over copper couplings and fittings. It should be installed on pipes that have been pre -tested for leaks, are not pres- ently hot, and have application tem- peratures that will not exceed 210°F (99°C). OUTDOOR APPLICATIONS therma-cel® Seam -Seal pipe insulation is made from UV resistant polyolefin resins. For severe UV exposure (roof- top applications) or where optimum performance is required, the product must be protected from the elements. Various jacketing or cladding materials are recommended, ie. PVC, CPVC, AL, etc. If coatings are going to be used, please refer to technical bulletin for recommended coatings. UNDERGROUND For buried lines above the water table, use a clean fill such as sand (3" - 5" layer) to protect therma-cel° Seam - Seal before backfilling. It is recom- mended to use a minimum 1" wall thickness and the materials to be bur- ied are properly sealed at all seams and butt joints with an approved contact adhesive. For optimum perfor- mance, the lines should be encased in a conduit to protect them from prob- lems associated with ground water. Note: All Nomaco Insulation products must always be in- stalled above the water table. RESISTANCE TO MOISTURE VAPOR FLOW The closed -cell structure and unique formulation of therma-cel® Seam - Seal effectively retards the flow of moisture vapor, and is considered a low transmittance vapor retarder. For most indoor applications, therma-cel° Seam -Seal needs no additional pro- tection. Additional vapor barrier protection may be necessary for therma-cel® Seam -Seal when installed on low tem- perature surfaces that are exposed to continuous high humidity. FLAME AND SMOKE RATING therma-cel® Seam -Seal in wall thicknesses of 1" (25 mm) and below has a flame spread rating of 25 or Tess and a smoke development rat- ing of 50 or less as tested by ASTM E 84 Method of Testing entitled: "Surface Burning Characteristics of Building Materials." therma-cel® Seam -Seal is acceptable for use in duct/plenum applications meeting the requirements of NFPA 90A/90B. Numerical flammability ratings alone may not define the performance of products under actual fire conditions. They are provided only for use in the selection of products to meet limits specified, when compared to a known standard. SPECIFICATION COMPLIANCE ASTM C 1427, Type 1, Grade 1 New York City OTCR #13-09 USDA Requirements ASTM E 84 1" 25/50 -tested according to UL 723 and NFPA 255 Complies with requirements of CAN/ULC S102.2 -M88 CFC/HCFC Free Low VOCs Halogen Free Non -porous Fiber Free Resistant to mold growth Sound transmission co -efficient = 11 at 1" per ASTM E90 Compatible with CPVC Piping (Lubrizol Listed) ASTM C 1427, NFPA 90 A/B. City of Los Angeles, Gen. Approval, Research Report RR 8316 Dade Co., FI., Product Control Approved, Acceptance #95-1215.08 Phone 866-876-2684 therma-cels Seam -Seal Physical Properties therma-cel'" Test Insulation Methods Thermal Conductivity (K) 90°F (32°C) Mean Temp .255 (.037) ASTM C 177/C 518 BTU -in/hr - Ft' - °F (W/mK) 75°F (24°C) Mean Temp .250 (.036) ASTM C 177/C 518 50°F (10°C) Mean Temp 245 (.035) ASTM C 177/C 518 Operating Temperature Range Upper 210°F (99°C) Flexible to -100°F (-73°C) Lower -330°F (-201°C) Water. Vapor Permeability Dry Cup. Perm -In 0.0 ASTM E 96 Ozone Resistance Pass ASTM D 1171 Chemical Solvent Resistance Good Mildew Resistance/Air Erosion Pass UL 181 Thickness Recommendations* - To Control Condensation } Pipe Size Normal Conditlons (Max 8.5°F, 29°C - 70% RH.) 3/8" I.D. thru 1-3/8" Over 1-3/8" thru 3-1/8" Over 3-1/8" thru 4-1/2"" Over 4-1/2" Mild Conditions (Max 80°F26°C - 50% R.H.) 3/8" I.D. thru 2-1/8" Over 2-1/8" thru 3-1/8" Over 3-1/8" thru 4-1/2"" Over 4-1/2" Severe Conditions (Max 90°F 32°C -130% RH) 3/8" I.D. thru 1-1/8" I.D. Over 1-1/8" I.D. thru 4-1/2" Over 4-1/2" Line Temp 50°F 10°C Line Temp 35°F 2°C Line Temp 0°F -18°C Line Temp -20°F -29°C 3/8" 3/8" 3/8" 1/2" 3/8" 3/8" 3/8" 3/8" 3/4" 3/4" 3/4" 10 mm 10 mm 10 mm 13 mm 10 mm 10 mm 10 mm 10 mm 19 mm 19 mm 19 mm 1/2" 1/2" 1/2" 3/4" 3/8" 3/8" 3/8" 1/2" 3/4" 13 mm 13 mm 13 mm 19 mm 10 mm 10 mm 10 mm 13 mm 19 mm 1" 25 mm 1" 25 mm 3/4" 1" 1" 1" 1/2" 1/2" 3/4" 3/4" 1-1/4" 1-1/2" 1-1/2" 19 mm 25 mm 25 mm 25 mm 13 mm 13 mm 19 mm 19 mm 32 mm 38 mm 38 mm 1/2" 1/2" 3/4" 3/4" 1-1/4" 1-1/2" 2" 25 mm 25 mm 25 mm 32 mm 13 mm 13 mm 19 mm 19 mm 32 mm 38 mm 50 mm therma-cel® Seam -Seal in thickness noted within the specified temperature ranges will prevent condensation on indoor piping under design con ditions defined below. Thickness recommendations above 1" can be sleeved to achieve thickness desired. Normal: Maximum severity of indoor conditions seldom exceed 85°F and 70% R.H. in United States. Mild: Typical conditions are most air-conditioned spaces and arid climates. Severe: Generally found in areas where excessive moisture is introduced or in poorly ventilated areas where the temperature may be depressed below the ambient. Under conditions of high humidity, additional thickness of insulation may be required. "Available: Nom. 1/2" or Nom. 3/4" thickness only. therma-cel"' Seam Seal "R" Values Pipe 0,D. or Nominal Insulation I.D. 3/8" 10 mm 1/2" 13 mm 5/8" 16 mm 3/4" 19 mm 7/8" 22 mm 29 mm 35 mm 41 mm 50 mm 54 mm 62 mm. 67 mm 72 mm 79 mm 89 mm 92 mm 105 mm 115 mm ► 1 118" • 1-3/8" 1-5/8" 2" 2-1/8 2-3/8" 2-5/8" 2-7/8" 3-1/8" 3-1/2" 3-5/8" ' 4-1/8 4-1/2" R Value 3/8" (10 mm) Wall 2.5 2.3 2.2 2.1 2.0 1.9 1.9 1.8 1.8 1.7 1.7 1.7 1.7 1.7 1.7 1.6 1.6 1.6 R Value R Value 112" (13 mm) Wall 3/4" (19 mm) Wall 3.6 3.3 3.1 3.0 2.9 2.7 2.6 2.5 2.4 2.4 2.4 2.3 2.3 2.3 2.3 2.3 2.2 2.2 6.0 5.5 5.2 4.9 R Value 1" (25 mm) Wall 4.1 3.9 3.9 3.8 3.7 3.7 3.6 3.6 3.5 3.5 3.5 8.8 8.0 7.5 7.1. 6.8 6.5 6.1 5.8 5.5 5.5 5.3 5.2 5.1 5.1 5.0 4.9 4.8 4.8 Note: "R" factors were calculated using a K factor of .250 (75° F, 24° C mean temp.) and nominal wall thickness is each case. Lower operating temperatures will result in improved R values. Contact Technical Services for specific recommendations. ma ce am rear..z +ssse:weramunvaltatm.. f rsrrs rween.ca� sa.+x�;a^sx:.ePaz� ::, .Msaa :woutsi s;s;b:n.cw-< F e. S' i(?. , ,_. 866-876-2382 tionMade in UJf'i:+r"` 620 Contact Adhesives - Black Made in America DESCRIPTION 320 & 620 Contact Adhesives are air -drying solvent based neoprene contact adhesives that are excellent for joining seams and butt joints of elastomeric & polyolefin pipe and sheet Insulation. 320 & 620 Contact Adhesives make resilient moisture- and heat -resistant bonds when used with elas- tomeric and polyolefin products. 320 & 620 Contact Adhesives' higher solids content allows them to be brushed or roller applied easily without running. They are ideal for bonding porous and non -porous materials, as they will not be absorbed easily. Caution: Adhesive contains notable solvents and container not in use should be kept closed. Keep adhesive away from sparks and open names. Use with adequate ventilation and avoid excessive contact with the skin. USES 320 & 620 Contact Adhesives may be used for bonding elastomeric and polyolefin products to a variety of materials (i.e., other elastomers, metal, wood, leather, felt, concrete, etc.). The adhesives will make resilient and heat -resistant bonds. They are suitable for line temperatures up to 220°F (104°C) on applications requiring bonded seams and joints. When the adhesives are applied to large flat or curve surfaces, they are suitable for temperatures up to 200°F (93°C). The products are supplied in a variety of sizes ranging from pint brush top containers to gallon containers. Larger containers are available upon request. APPLICATION INSTRUCTIONS For proper adhesion, the surfaces to which the insulation is to be applied must be thoroughly cleaned, dry, and unheated. Primed and painted surfaces should be adhesive tested to be sure the insulation will not lift off after application. The adhe- sive should be thoroughly mixed. Brush or roll a thin even coat of adhesive on both surfaces to be joined. Allow the adhesive films to become dry to the touch, but tacky, before joining the surfaces. Press the two surfaces together. Be sure the insulation is in the desired position before the adhesive surfaces make initial contact, since the adhesive forms an instant bond, and repositioning after contact is difficult. Moderate pressure should then be applied to the entire bonding area to insure com- plete contact. Avoid heat, sparks, and open flames, and use only proper ventila- tion. Close container after use. 320 & 620 Contact Adhesives should be applied at above 40°F (4°C) temperatures, and allowed to dry for 24 hours before equip- ment operation. Protective coatings can be applied to applications with bonded joints and seams, after allowing 24 hours dry time. Applications such as large tanks, or vessels where full adhesive coverage is required, must be allowed to dry 7 days prior to applying a protective coating. The surface may be allowed to dry and solvent reactivated by wiping with a tolu- ene dampened cloth. Thinning the adhesive is not recommend- ed. Common lacquer thinners can be used for clean up. Physical Properties Color Base Solvents Viscosity Solid Content Weight per gallon Coverage Shelf Life Minimum Dry Time Open Time Temperature Limits Flammability Flash Point Freight Classifications Amber (320), Black (620) Neoprene Toluene, Hexane, Acetone Medium Syrup 25% ± 2% 6.98± .2 lbs. 200 sq. ft. per gallon (one surface) One year in original sealed container. • Storage temperature 60°F 2-4 minutes under normal conditions Not to exceed 10 minutes 220°F (104°C) for pipe insulation seams and joints 200°F (93°C) for full bonding sheets ASTM E84 10/0 Flamespread/Smoke Developed Less than -4°F Adhesives NOS. Flammable Liquid 4620 Sub 5, class 60, Un 1133, IMDG class 3.1 PG:11 (packaging group 11) OMACO. iiiitss Insulation sn energy conservation company 203 Capcom Avenue, Suite 102 I Wake Forest, NC 27587 I p 866-876-2684 1 f 866-876-2688 www.nomacoinsulation.com OJuIy 2008 Made in usdi NI -0013 -PS -0708 Change Proposal Request No. 9 (Not a Change Order) Project Name: RM 1431 - 2.0 MG Elevated Water Storage Tank Owner's Project No. (if applicable): Project Owner: City of Round Rock Regulatory Agency Project No. (if applicable): HDR Project No.: 74095 Initiated by: X Engineer _ Contractor Date: 8/26/09 Contractor: Landmark Structures I, LP Attention: The following change In the contract on this project is proposed. • A breakdown of cost SHALL be attached. • Work shall not commence until authorized by the Owner. Description of the Proposed Change: Provide all necessary labor, equipment, and materials for installing a header for routing sample water to the sink proposed by CPR No. 8, as well as a chlorine residual analyzer and solenoid control valves with local and remote online sampling of total chlorine and temperature. This CPR is structured such that costs for the proposed items can be broken out and selected by the Owner for implementation separately (Leit is possible that some,_but not all, of the items wiihbe implemented]. F16 02 f j daub cP /JO 5 j arm rui,v i...s, - tQ \A . (v� b � \ vcL\tj P1v� s1�.�•� cceLAA &&* _ ck�ZQON� sotR otc( Provide costs for: °'` " a.- C � \ 0 rA `. a " `� ` 1 '1 4 R. l �C � �+UQ b— seco kk,� +15 -ti-g- St K K. g 01. r 1. Baseline roposed Improvemen' (Sample Line Header) - Connect the three sample lineS to a W PVC header pipe, and install a drain down -leg and 1 drain line ball valve for routing the sample water to the sink proposed in CPR No. 8. See the attached Figure 1 for a schematic of the improvements. Note, the isolation ball valves (shown as existing on Fig. 1), pressure gauges, and signage required by Note 13 on Sheet 1D-01 of the construction drawings are still required. Z �Xs C.'T if J?) - .1 Additions to the Baseline Improvements for Online Chlorine and Temperature Monitoring- .. •osed ems include hardware and programming for remote automated sampling, and local m. al sa • 'ng/control. See the attached Figure 2 for a schematic of the improvements. ' •vide separate costs fo -ach of the following items to be combined in part or in whole for im entation: a. Should be panel mounted type since we're adding it to the face of the control panel b. Online •tal Chlorine Residual and Temperature Monitoring - F ish and install a new chlorine iemens Depolox 3 Plus for measuring total orine (membrane type probe) and surface mounted enclosure with V. '-Sens Flow Cell and interconnecting ulating valve to reduce pr- . ure below 60 psi (pressure to the flow cell psi). Provide all • cessary tubing and stop valves for flow cell mainte ce/spare parts kits, to include membranes and residual analyz , temperature, NEMA cable. Pr• '_ - pressure s to be between 2 psi an influent and effluent. Provide a 1-y electrolyte, and an O&M manual. Install 2 new circuits from RTU to t chlorine a - i er for two analog inputs, total chlorine residual and temperature. Each circuit .11 be #18TSP in a gle W. Install a new circuit, 2#12 12G, S/" from the lighting pane • the chlorine analyzer. Provide conduit per Section 16111 an • able per Section 16120. Provide PLC pro temperature mming of two analog inputs for monitoring total ch • e residual and Sol- oid Control Valves (Remote Control) - Install 4 solenoid control valves, o _ • -r sample and drai • ine. Solenoid valves to be ASCO, or approved equal. Parameters: 110 VAC, two- - , normally sed, 125 psi. Materials: brass body, Buna-n seat, class F insulation. Provide an addition isolation ball valve on each sample and drain line (i.e. result is there will be an isolation valve on •oth sides of the solenoid valve). FORM 111-5010-3 (Jun 90) Copyright 1991 HDREngineermg, Inc Task 5010 111-5010-3 Change Proposal 1 LL Request No. J. (Not a Chat* Order) -1 ileW mud circuits from the RTU to each solenoid valve, eirr:trits,b64 he 2 014, !i". The itputs for operfirirthlet;ing solenoid valvforrPrevirto rorldait per Sitctrr.,n gf.:tIrm 16120 . ,. . .., : - ,, ,,, , , rAw.1,,onii,g nec.ssary to implement contrej.end mootteririg of rho suleifoid valve!, 1 :::.:..,t,riold V:th'e :, 411411,11e a i'lle to be remotely open and et6sed. Only one of the three sample lines d at :Joy (ii'zz impfernortt timint) fuer to allow sample weter to drain to the sink by Main •mirouriti valvr.q;:thing hall ritlsrf for art orwrator adjustable amount of limn. After , rk ,“Ir .!;g pOktiOti tig.5 NM. , itain Aykrtuiti v skill 11.i d the. Clittuintl analyzer shall monitor OVA!: i at IT the ..,,,;'int .O4MTdvorNo Attar the 5erePte has Wen recorded, riarriple line .... vi.m,re Nboti r 1 awl iiiliirki '. •a i I , I t A ------,,' i' te.p9i0 vrliver, ! nc.tit;Ofrol , . tit rig, i . 4 flEk ,/ 11 t 1pft N.a Ve comm. panel. Contrrit c,iript -it mil tor NEMA 4X,,watkr1erirtted and Azed to IrrAnitr the chlorine imalyzer lo Item No 1 -4nti :, I= ;1' (0' 'i"NttLI rof:-, or, follows r,K .ret) oar} Orsioll on Om toi&ri xtortor a trent of 5 petector .,ovitchns ttpv.tfail he heavy duty, NEMA riX, 2 poxitron rol. witch with maintainer.] contact ...: 0 so ..,c.r, tyrx)operator,(Orie ( I) m.dieh :4v111 have ktgand late of Cc"I/Remote, Witt the Remote t3e ingot to the P ru Four (4) •switiAtes shall have lege late of Openi'Close, ..,vith l'o !"-.t.:40.1 raintarl wrrpil ao art mput to tl'o71 N 1U Switolres shag he labeled: ''Um,ple tele No I', .',..er.61r, I sort No 2-A• "Sample 1.1ne No 1', and "Drain Line" A total of 1014 shorbe,oerkttl from , ,,,,...„ ,tro ..amtrtr< Vv: c6filrolf•innot to the NIUiit 'A' conduit Pr in.de overall flameout() for pariot: r,,i1otrof Prtoor filo PLC ,=.1 tall trtr orootat mood for manual cootrol at (lac. ktdariftririr piro1 PaoPi Shah moot an reilotrornettIo of UL 500A and NEC 409. Affix p4miel wiirtui;, r..sai,.:„.....z.i.... , , ,... BY I rAY Si rt..Vrti 1 C01:4:: —; AN work stud be in accordance with the tonna, liDR Reconunenclation: stipulations. and conditions the original Contract DOCUMINItS. If the work herein provided for Is Approved by Change Order, the time of aeripletbn will be: _ increased ._ Decreased t until:avid by calendar days. re. This change wit Atid $ Contract !Date j,)Z' WAN 1114114114(ha *NAM IM Itaiimenia, itecommended _Do Not Recommend Acceptance By. )J011 laiVrteertiv, Aral 2 9 ce` Date Not Change Owys Action: TIM 1014 1114101114 Atm LANDMARK September 24, 2009 HDR Engineering, Inc. 4401 West Gate Blvd. Suite 400 Austin, TX 78745 Attn: Troy St. Tours, P.E. Landmark Structures 1665 Harmon Road Fort Worth, Texas 76177 817.439.8888 Phone 817.439.9001 Fax www.teamlandmark.com Re: RM 1431 – 2.0 MG Elevated Water Storage Tank CPR #9 Dear Sir: We propose to provide all necessary labor, equipment and materials to install a header for routing sample water to the sink, documents, CPR # 9 and the cost breakout below: 14a6p4- 1. Sample line header: 2b. Solenoi in accordance with the contract - .. -...- - ►IS. •r.. Valves (Remote Control): 2c. Solenoid Valves (Local Contro Add $190.00 00 d $15,950.00 Add $12,300.00 s a . 4 l 1 If item 1 is selecte one (1) calendar day to the con Please let us know at your earliest convenience which items, if any, will be accepted. Sincerely, LANDMARK STRUCTURES I, LP Eugene Chastain Project Manager Attachments ROURNO 70 0ESINK I s• j a• j �'�V f4'L V i CI CPRPR NO,N0, B i i 3/yr i i I t3 �»Na1-v1L TEE m;7p0 0 o TEE MRH DAP S FT AFF HEADER MID WAN UNE ADDED TO SAMPLE UNE BALL VALVE INSTALIAVON 9EE NOTE 13, HEET 1D-01) LENOW AS JI SINK N A i D DIRAN LINE PROPOSED BT I 4'FROM SIDE AND CPR NO. BI REAR SINK WALL fI �..r.._._._._.—._ _._._._._._.—r. I I I SLAB i I I 1D DRAM I 1vV'T 12�v�S of CITY OF ROUND ROCK,TEXAS rote h"'r]R RM 1431 EST 082009 CPR NO.9-SAMPLE LINE HANDLING AT SINK- BASELINE IMPROVEMENTS Figura HDR Engineering, Inc. PRELIMINARY DIAGRAM-NOT TO SCALE 01 a ' DATE: October 21, 2009 SUBJECT: City Manager Approval — October 23, 2009 ITEM: Consider executing Change Order No. 2 with Landmark Structures I, L.P. for the RM 1431-2MG Elevated Water Storage Tank Improvements Project. Department: Staff Person: Water and Wastewater Utilities Michael D. Thane, P.E., Director of Utilities Justification: Change Order No. 2 includes all the labor, equipment, and materials necessary for installing a service sink and drain line to handle water from the three tank sample lines. This change order also includes installing a header for routing sample water to the service sink and isolation valves over the sink. This new system was developed by the utility engineering staff in order to collect water samples for chlorine residuals from the top, middle, and lower thirds of the tank bowl. This design helps monitor the internal mixing of the water flowing through the tank, as well as helps in evaluating the new inlet/outlet piping configuration and inlet nozzle. Strategic Plan Relevance: Goal 27.0 "Ensure there is an adequate, affordable and safe water supply." With the RM 1431-2.0 MG Elevated Water Storage Tank, the City can more efficiently deliver potable water from our current Water Treatment Plant. Additionally, our future Brushy Creek Regional Utility Authority (BCRUA) Water Treatment Plant will benefit from this project as well. In addition to this project, two other projects were required to meet our obligations under an Interlocal Agreement for Emergency Water Supply between the Cities of Round Rock and Cedar Park. These projects include the RM 1431 36 -inch Water Line project which is complete and the 7.5 MGD High Service Pump project. Cedar Park has contributed $1,000,000 toward these projects per said agreement. Funding: Cost: $4,690.00 Source of funds: Self -Financed Water Construction Amount % Change Original Contract $4,185,000.00 N/A Previous Change Orders $35,803.00 0.86 Change Order # 2 $4,690.00 0.11 Revised Contract $4,225,493.00 0.97 Outside Resources: Landmark Structures I, L.P. HDR, Inc. Public Comment: N/A UPDATED APRIL 2008 5,12/2009 Request for City CounciUCity Manager Action LI City Council 11 City Manager Submit completed form for all City Manager and City Council approvals. Department Name: Water & Wastewater Utilites may For 'crniniRkrstcr'1`^ONLY � Received: Tag #: �-�Y�- e� ! o -2I 5 Original Documents Received: 2 Project Name: RM 1431.2MG Elevated Water Storage Tank Contact Person: Chaz Gordon / Kathy Michna ContractorNendor Landmark Structures I, LP. Project Mgr/Resource: Don Rundell Funding Source: Sex -Financed Water Construction Project Coordinator Michael Thane Additional funding Source: Amount Account Number nor Assigned Attorney: Steve Sheets City Council or City Manager Approval Date: Agenda Wording 10/23/2009 4,690.00 Consider executing Change Order No. 2 with Landmark Structures I, L.P. for the RM 1431-2MG Elevated Water Storage Tank Improvements Project. Finance Information Is Funding Required? Yes No Initial Construction Contract Construction Contract Amendment Change Order # 11jChange in Quantity Unforeseen Circumstances ED Initial Professional Services Agreement Q Supplemental Professional Service Agreement #_ ED Purchasing/Service Agreement Purchase Order Item(s) to be purchased Other (Please clearly identify action on lines below) Amount 4,690.00 FINANCE N/A Approved 0 0 0 0 E J 0 0 Finance/CIP FinancelAcct Purchasing Budget Date Date Date Date APPROVALS (to be completed ONLY by Finance) Final Finance Approval Required APPruved Finance Director Date Once approvals have been obtained. please forward the RFA. blue sheet. backup information and originals to City Secretary, Sara White. ITEMS WILL NOT BE PLACED ON THE COUNCIL AGENDA WITHOUT FINANCE AND LEGAL APPROVAL PRIOR TO SUBMISSION. Reuuired for Submission of ALL City Council and City Manager Items Project Mgr. Signature: Dept. Director Signature: 'City Attomey Signature: City Manager Signature: Date: Date: �B �Q80 f Date: 10-.Q3-01 Date: ! o- 03-c9) `City Attorney signature M required for all items. REVISED 10/16/2009 5/12/2009 Request for City Council/City Manager Action 0 City Council p City Manager Submit completed form for all City Manager and City Council approvals. Department Name: Water & Wastewater Utilites Contact Person: Chaz Gordon / Kathy Michna Project Mgr/Resource: Don Rundell Project Coordinator tv9chael Thane Assigned Attomey: Steve Sheets City Council or City Manager Approval Date: Agenda Wording For Administration Use ONLY Received: Tag #: Original Documents Received: Project Name: RM 1431 - 2MG Elevated Water Storage Tank ContractorNendor: Landmark Structures I, L.P. Funding Source: Ser -Financed Water construction Additional funding Source: Amount: Account Number: na 10/23/2009 4,690.00 Consider executing Change Order No. 2 with Landmark Structures I, L.P. for the RM 1431-2MG Elevated Water Storage Tank Improvements Project. Finance Information Is Funding Required? Yes n No Initial Construction Contract Construction Contract Amendment u Change Order # 2 Change in Quantity Initial Professional Services Agreement Supplemental Professional Service Agreement OPurchasing/Service Agreement Purchase Order Item(s) to be purchased Unforeseen Circumstances El Other (Please clearly identify action on lines below) Amount $ 4,690.00 FINANCE WA Approved DEI CI= APPROVALS (to be completed ONLY by Finance) Final Finance Approval Required Finance/CIP B. Ramsey Date 10/21/2009 Finance/Acct E. Wilson Date 10/21/2009 Purchasing EE Bowden Date 10/20/2009 Budget P. Bryan Date 10/20/2009 Approved Cheryl Delaney 10/21/2009 Finance Director Date Once approvals have been obtained. please forward the RFA. blue sheet, back up information and originals to City Secretary, Sara White. ITEMS WILL NOT BE PLACED ON THE COUNCIL AGENDA WITHOUT FINANCE AND LEGAL APPROVAL PRIOR TO SUBMISSION. Required for Submission of ALL City Council and City Manager Items Project Mgr. Signature: Dept. Director Signature: *City Attorney Signature: City Manager Signature: Date: Date: Date: Date: *City Attomey signature is required for all items. REVISED 10/21/2009 LEGAL DEPARTMENT APPROVAL FOR CITY COUNCIL/CITY MANAGER ACTION Required for Submission of ALL City Council and City Manager Items Department Name: PW/Utilities Project Name: RM 1431 - 2MG Elevated Water Storage Project Mgr/Resource: Don Rundell nCouncil Action: ORDINANCE Agenda Wording ContractorNendor: Landmark Structures!, L.P. E-1 RESOLUTION City Manager Approval CMA Wording Consider executing Change Order No. 2 with Landmark Structures I, L.P. for the RM 1431-2MG Elevated Water Storage Tank Improvements Project. Attorney pproval Attorney Notes/Comments Date O:\wdoxISCCInts10140\09001M ISC100174015.XLS Updated 613108