Loading...
CM-09-11-227STATE OF TEXAS COUNTY OF WILLIAMSON § § § SUPPLEMENTAL CONTRACT NO. 1 TO CONTRACT FOR ENGINEERING SERVICES FIRM: HDR ENGINEERING, INC. ADDRESS: 4401 West Gate Blvd., Suite 400, Austin, TX 78745 ("Engineer") PROJECT: Meister Lane Project This Supplemental Contract No, 1 to Contract for Engineering Services is made by and between the City of Round Rock, Texas, hereinafter called the "City" and HDR Engineering, Inc., hereinafter called the "Engineer". WHEREAS, the City and Engineer executed a Contract for Engineering Services, hereinafter called the "Contract", on the 22nd day of January, 2009 for the Meister Lane Project in the amount of $220,083.00; and WHEREAS, it has become necessary to amend the Contract to modify the provisions for the scope of services and to increase the compensation by $42,379.16 to a total of $262,462.16; and NOW THEREFORE, premises considered, the City and the Engineer agree that said Contract is amended as follows: I. Article 2, Engineering Services and Exhibit B, Engineering Services shall be amended as set forth in the attached Addendum to Exhibit B, Engineering Services. Exhibit C, Work Schedule shall be amended as set forth in the attached Addendum to Exhibit C, Work Schedule. II. Article 4, Compensation and Exhibit D, Fee Schedule shall be amended by increasing by $36,027.64 the lump sum amount payable under the Contract for a total lump sum amount of $256,110.64, as set forth in the attached Addendum to Exhibit D, Fee Schedule. Additionally, a "time and materials" component is hereby added to the Contract, as follows: The City shall pay Engineer on a "time and materials" basis for a portion of the work, Engineer agrees to accept payment from the City on such basis, and the parties expressly agree that only work actually performed by Engineer will be paid for by the City. The "time and materials" portion of the work is set forth in the last paragraph of the attached Addendum to Exhibit B, Engineering Services., and the "time and materials" fee therefor shall be $6,351.52 as set forth in the last paragraph of the attached Addendum to Exhibit D, Fee Schedule. Supplemental Contract 0199.7090/174594 1 Rev.12/01 /08 84275 IN WITNESS WHEREOF, the City and the Engineer have executed this Supplemental Contract in duplicate. HDR ENGINEERING, INC. CITY OF ROUND ROCK By: 11- I2-2Ocf Date JamesR.Nt se,PE. Cay mancttr Supplemental Contract 0199.7090/174594 2 VED AS 0 FORM: Ni n L. Sheets, City Attorney Rer.12/01/08 84275 ADDENDUM TO EXHIBIT B Engineering Services The changes to the scope of this project are as follows: ADDENDUM TO EXHIBIT B Engineering Services PS&E Phase Services — Lump Sum The work to be perforrued by HDR Engineering, Inc. (ENGINEER) under this supplemental agreement shall consist of providing engineering services for updating the roadway, drainage and traffic design and preparing illumination plans for inclusion into the Plans, Specifications, and Estimates (PS&E) for the reconstruction of Meister Lane from the SH45 Westbound Frontage Road to Gattis School Road in the City of Round Rock. The following tasks will be necessary for plan development: • Update the project cross sections. • Update plan elements due to change in sidewalk revisions. • Update intersection layouts and driveway plans. • Revise drainage design. ■ Coordinate with RRISD on driveway drainage. The following tasks will be necessary for preparation of the illumination plans: ■ Submit to the City illumination design criteria for Meister Lane between Gattis School Road and SH45. • Conduct a field review to note and verify physical constraints, power connection, utility placement, and any other details necessary for illumination plan preparation. • Perform photometric analysis using VISUAL software to identify pole locations and fixture types to maintain adequate light levels along the entire corridor. • Prepare illumination plans and quantity estimates for illumination located along the west side of Meister Lane between Gattis School Road and SH45. Plans will include complete illumination layout sheets, pole schedule, and conduit and conductor schedule and voltage drop calculations. The illumination plans will be prepared in accordance with TxDOT standards. • Submit plans to the CITY for final review prior to bidding project. • Prepare mylar plans, which incorporate CITY comments. This scope assumes that illumination poles will be designed to be installed only on one side of Meister Lane. However, if it is required to design illumination along both sides of Meister Lane, a separate scope of services may be required. Construction Phase Services — Time and Material Basis The Engineer will provide responses during construction when requested by the City. The work is limited to a 40 hour approved budget for this task. If additional time is needed, a supplemental agreement will be issued. ADDENDUM TO EXHIBIT C Work Schedule Attached Behind This Page ADDENDUM TO EXHIBIT C Work Schedule ti d r 03 February I March 1 April 1 0 H F 03 h s. d .32E d U a) A ovem ber J 1 Months' rma] Contract Documents Bid Phase Construction Phase 4 vs Hz� a' ADDENDUM TO EXHIBIT D Fee Schedule The changes to the fee schedule for this project are as follows: ADDENDUM TO EXHIBIT D Fee Schedule Cost Component, Hours Total Hours Project Principal 0 Project Manager 8 Project Engineer 32 EIT 0 Sr. Design Technician 0 CADD Technician 0 Clerical/Steno 0 Total Hours 40 Cost Component, Dollars Labor Burdened Rate Rate Project Principal $80.00 $246.40 $0.00 Project Manager $67.00 $206.36 $1,650.88 Project Engineer $44.00 $135.52 $4,336.64 EIT $35.00 $107.80 $0.00 Sr. Design Technician $36.00 $110.88 $0.00 CADD Technician $20.00 $61.60 $0.00 Clerical/Steno $22.00 $67.76 $0.00 $5,987.52 Technology @ $3.70/hr $3.70 $148.00 Phone, Fax, Postage,Advertisements $0.00 Travel Expenses $116.00 Printing $100.00 Total Expenses $364.00 Project Time & Material Fee Summary Direct Labor $1,944.00 Indirect Costs (1.75%) $3,402.00 Direct Costs $364.00 Profit @12% $641.52 Time and Material 86,351.52 ADDENDUM TO EXHIBIT D Fee Schedule Project Lump Sum Fee Summary Direct Labor $11,298.00 Indirect Costs (1.75%) $19,771.50 Direct Costs $1,229.80 Profit @12% $3,728.34 TOTAL FEE FOR LUMP SUM $36,027.64 Project Time & Material Fee Summary Direct Labor $1,944.00 Indirect Costs (1.75%) $3,402.00 Direct Costs $364.00 Profit @12% $641.52 TOTAL FEE FOR TIME AND MATERIAL $6,351.52 DATE: November 12, 2009 SUBJECT: City Manager Approval — November 13, 2009 ITEM: Consider executing Supplemental Contract No. 1 to Contract for Engineering Services with HDR Engineering, Inc. for the Meister Lane Project. Department: Transportation Services Staff Person: Thomas E. Word, P.E., Chief of Public Works Operations Justification: Supplemental Contract No. 1 will provide engineering services for updating the roadway, drainage and traffic design and prepare illumination plans for inclusion into the Plans, Specifications and Estimates (PS&E) for the reconstruction of Meister lane from SH45 Westbound Frontage Road to Gattis School Road. Strategic Plan Relevance: 26.0 Construct major elements of the transportation and mobility system as approved by Council in the Master Transportation Plan Funding: Cost: $42,379.16 Source of funds: General Self Financed Construction Funds Outside Resources (if applicable): HDR Engineering, Inc. Public Comment (if applicable): N/A UPDATED APRIL 2008 io.l9.09 Request for City Council/City Manager Action ® City Council ELI City Manager Submit completed form for all City Manager and City Council approvals. Department Name: Transportation Services Contact Person: Chaz Gordon / Kathy Michna Project Mgr/Resource: Bill Stablein Project Coordinator. Tom Word, P.E. Assigned Attorney: Stephan Sheets City Council or City Manager Approval Date: Agenda Wording For Received: Atiir'?J ONLY NOV 10 2009 ,uwa• Tag*: Off'.09-II- 22_1 Original Documents Received: h Project Name: Meister Lane ContraCior/Vendor: HDR Engineering, Inc. Funding Source: RR Trans Dev Corp Construction Additional funding Source: Amount S Account Number. 11/13/2009 42,379.16 Consider executing Supplemental Contract No. 1 to Contract for Engineering Servies with HDR Engineering, Inc. for the Meister lane Project. Finance Information Is Funding Required? Initial construction Contract Construction Contract Amendment Change Order Change in Quantity Initial Professional Services Agreement Supplemental Professional Service Agreement Purchasing/Service Agreement Purchase Order item(s) to be purchased Yes El No ❑Unforeseen Circumstances Other (Please clearly identify action below) Amount $ 42,379.16 FINANCE N/A Approved Q Finance/CIP D80e Finance/Acct Date CD a Purchasing Dag; JJ Budget Date APPROVALS (to be completed ONLY by Finance) Final Finance Approval Required APProved 1 1 Finance Director Once approvals have been obtained. please forward the RFA, blue sheet, back up information and originals to City Secretary, Sara White. ITEMS WILL NOT BE PLACED ON THE COUNCIL AGENDA WITHOUT FINANCE AND LEGAL. APPROVAL PRIOR TO SUBMISSION. Date Required for Submission of ALL City Council and City Manager items Project Mgr. Signature: Dept. Director Signature: "City Attorney Signature. City Manager Signature: Date: Date: Date: Date: 11-03-64 I j-12-2ooq 11-)2-zocP/ 'City Aftomeyireiarequiredbrallitem. REVISED 11/3/2009 101909 Request for City CounciUCity Manager Action ED City Council En City Manager Submit completed fonn for all City Manager and City Council approvals. Department Name: Transportation Services Contact Person: Chaz Gordon / Kathy Michna Project Mgr/Resource: Bill Stablein Project Coordinator: Tom Word, P.E. Assigned Attomey: Stephan Sheets City Council or City Manager Approval Date: Agenda Wording For Administration Use ONLY Received: Tag#: Original Documents Received: Project Name: Meister Lane Contractor/Vendor: HDR Engineering, Inc. Funding SOUrce: General Self -Financed Construction Additional funding Source: Amount: $ Account Number: 11/13/2009 42,379.16 Consider executing Supplemental Contract No. 1 to Contract for Engineering Servies with HDR Engineering, Inc. for the Meister Lane Project. Finance Information Is Funding Required? Yes L7.` No = Initial Construction Contract Construction Contract Amendment n Change Order fF Change in Quantity =Unforeseen Circumstances Initial Professional Services Agreement Supplemental Professional Service Agreement # t = Purchasing/Service Agreement = Purchase Order Item(s) to be purchased a Other (Please clearly identify action below) Amount $ 42,379.16 FINANCE WA ` Approved Finance/CIP Finance/Acct L. Olsen Date ;11/9/2009 Date Purchasing EE Bowden P. Bryan Delaney'. nance<Director 11/9/2009 Date Date 11/10/2009 Date 11/10/2009'. Once approvafs have been obtained, plead Ioneard:t ITEMS WILL NOT REPLACED ON THE COUNCIL ad riligrnafs to City Secretary,, Sara While.- iAL / PPROVAL,PRIOR-TO $Ut3MISSION:` • Required for Submission of ALL City Council and City Manager Items Project Mgr. Signature: Dept. Director Signature: 'City Attorney Signature: City Manager Signature: Date: Date: Date: Date: *City Attomey signature is required for an items. REVISED 11/10/2009 LEGAL DEPARTMENT APPROVAL FOR CITY COUNCIL/CITY MANAGER ACTION Required for Submission of ALL City Council and City Manager Items Department Name: Transportation Project Mgr/Resource: Bill Stabtetn riCouncil Action: cm ORDINANCE Agenda Wording Project Name: Meister Lane ContractorNendor: HDR Engineering, Inc. ri RESOLUTION City Manager Approval CMA Wording Consider executing Supplemental Contract No. 1 to Contract for Engineering Services with HDR Engineering, Inc. for the Meister Lane Project. Attorney Approval Attorney Notes/Comments Date /O.3. , O:lwdox\SCCInts10199170901M1SC100174626.XLS Updated 6/3/08