CM-10-03-065rev. 1/10 Contract Quantity Adjustment/Change Order Department: Engineering and Development Services Project Name: Egger Aceres and Dennis Drive Improvements City Project ID Number: ST12DENN Justification Date: Page 1 of 3 3/9/2010 Change Order/Quantity Adjustment No. 3 Change Order/Quantity Adjustment # 3 is needed to add concrete valley gutter repairs/modifications at the intersections of Dennis Drive and Robb Lane, Dennis Drive and Karen Cove, and Robb Lane and Sara Drive. Also, pavement spot repairs are being added because such repairs were not included in the original contract, and an item is being added to the contract to account for additional HMAC placement in excess of 2" as originally specified for the streets in the project. Lastly, some items are being removed from the original contract via quantity adjustment. SUMMARY Original Contract Price: Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Original Contract Price Plus Change Order(s) Plus Quantity Adjustment(s): Original Contract Time: Contract Time Prior to this Change Order: Contract Time with All Approved Change Orders: Prepared by: Contractor Approval* City Staff 4 ` Approval: Signature City Official Approval: C`M l0-cs-o cS Signatures and Approvals Amount $1,237,883.00 $1,204,133.00 $33,543.55 $24,626.50 $58,170.05 -$12,000.00 -$21,750.00 -$33,750.00 $1,262,303.05 0/0 Change 2.79% 2.05% 4.83% 240 Calendar Days 240 Calendar Days 248 Calendar Days Eddie Zapata, Project Manager, City of Round Rock Printed Name, Title and Company Hank Lewis, Vice President, Nelson Lewis, Inc. Printed Name, Title and Company Danny Heiden, City Engineer, City of Round Rock Printed Name and Title 3/6/c Date James R. Nuse, City Manager, City of Round Rock Printed Name and Title Date 3/,o/ta Date 3-11-10 Date rev. 01/10 Contract Quantity Adjustment/Change Order Change Order Data Page 2 of 3 Bid Item# Item Description and Change Unit Qty. Unit Price Amount Contract Time Adjustment (Days) C. 0. # 3-1 C. 0. # 3-2 C. 0. # 3-3 Valley Gutter Repair/Modification Pavement Repair Increase in HMAC Thickness Beyond 2" as Specified in Add Alternate Bid 4, Items 4.1 thru 4.7 S.F. S.Y. Ton 470 $15.00 $7,050.00 5 3 0 98 $18.00 $1,764.00 250 $63.25 $15,812.50 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 TOTALS: $24,626.50 8 rev. 01/10 Contract Quantity Adjustment/Change Order uantity Adjustment Data Page 3 of 3 TOTALS: -$21,750.00 Bid Item# Item Description and Change Unit Qty. Unit Price Amount Contract Time Adjustment (Days) Base Bid 11 Base Bid 12 Base Bid 29 Base Bid 36 Base Bid 43 Delete Realign/Lower Existing Six Inch (6") Water Line Delete realign/Lower Existing Eight Inch (8") Water Line Delete Replace Existing One Inch (1") Water Service Delete Replace Existing Concrete Valley Gutter Delete Replace Valley Gutter Excavation E.A. E.A. E.A. E.A. S.Y. 1 (55,500.00) -$5,500.00 0 0 0 0 0 1 (56,500.00) -$6' 500.00 5 (51,500.00) -$7,500.00 1 (5800.00) -$800.00 58 (525.00) -$1,450.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 0 $0.00 $0.00 TOTALS: -$21,750.00 ROUND ROCK, TEXAS PURPOSE. PASSION. PROSPERITY. Item Caption: Approval Date: City Manager Approval Summary Sheet Consider executing Quantity Adjustment/Change Order No. 3 with Nelson Lewis, Inc. for the Egger Acres and Dennis Drive Improvements Project. March 19, 2010 Department: Engineering and Development Services Project Manager: Eddie Zapata Item Summary: Change Order/Quantity Adjustment # 3 is needed to add concrete valley gutter repairs/modifications at the intersections of Dennis Drive at Robb Lane, Dennis Drive at Karen Cove, and Robb Lane at Sara Drive. Also, pavement spot repairs are being added because such repairs were not included in the original contract, and an item is being added to the contract to account for additional HMAC placement in excess of two inches (2") as originally specified for the streets in the project. Lastly, some items are being removed from the original contract via quantity adjustment. Amount % Change Original Contract $1,237,883.00 N/A Previous Quantity Adjustments ($12,000.00) N/A Quantity Adjustment # 3 ($21,750.00) N/A Previous Change Orders $33,543.55 2.74% Change Order # 3 $24,626.50 2.05% Revised Contract Total $1,262,303.05 4.83% Strategic Plan Relevance: Goal No. 2.0: Prevent neighborhood deterioration. Goal No. 29.0: Provide for effective management of storm water. Cost: $24,626.50 Source of Funds: 2002 G.O. Bonds REV. 3/8/10 10.19.09 Request for City Council/City Manager Action IID City Council City Manager Submit completed form for all City Manager and City Council approvals. V_ Fot n ii ra:b L e ONLY 1 7A` Received: 1\01/) -- Tag#: nil —60-D3-0426— Original Documents Received: Department Name: Engineering and Development Services Project Name: Egger Acres and Dennis Drive Improvements Contact Person: Chaz Gordon / Kathy Michna Project Mgr/Resource: Eddie Zapata Project Coordinator: N/A Assigned Attorney: Steve Sheets City Council or City Manager Approval Date: Agenda Wording ContractorNendor: Nelson Lewis, Inc. Funding Source: 2002 General Obligation Bonds Additional funding Source: N/A Amount: $24,626.50 Account Number: March 19, 2010 Consider executing Quantity Adjustment/Change Order No. 3 with Nelson Lewis, Inc. for the Egger Acres and Dennis Drive Improvements Project. Finance Information Is Funding Required? Initial Construction Contract Construction Contract Amendment Change Order Change in Quantity Initial Professional Services Agreement Supplemental Professional Service Agreement Purchasing/Service Agreement Purchase Order Item(s) to be purchased Yes O No Q # 3 ElUnforeseen Circumstances Other (Please clearly identify action below) Amount $24, 626.50 FINANCE NIA Approved oa E Finance/CIP Finance/Acct Purchasing Budget Date Date Date Date APPROVALS (to be completed ONLY by Finance) Final Finance Approval Required APProved Finance Director Date Once approvals have been obtained. please forward the RFA, blue sheet. back up information and originals to City Secretary, Sara White. ITEMS WILL NOT BE PLACED ON THE COUNCIL AGENDA WITHOUT FINANCE AND LEGAL APPROVAL PRIOR TO SUBMISSION. Re uired for Submission of ALL Ci uncil and Mana er Items Project Mgr. Signature: Dept. Director Signature: 'City Attorney Signature: City Manager Signature: Date: .5kie Date: 3 //6 j( O Date: 3- l9- is Date: "City Attorney signature is required for all items. REVISED 3/12/2010 LEGAL DEPARTMENT APPROVAL FOR CITY COUNCIL/CITY MANAGER ACTION Required for Submission of ALL City Council and City Manager Items Department Name: PW/Engineering Project Mgr/Resource: Danny Halden/Eddie Zapata nCouncil Action: ORDINANCE Agenda Wording Project Name: Egger Acres and Dennis Drive Improvements ContractorNendor: Nelson Lewis, Inc. n RESOLUTION City Manager Approval CMA Wording Consider executing Quantity Adjustment/Change Order No. 3 with Nelson Lewis, Inc. for the Egger Acres and Dennis Drive Improvements Project. Attorney Approval Attorney Notes/Comments Date / 2/ /` ::) O:\wdox\SCClnts\019917116\M ISC100185778.XLS Updated 6/3/08