CM-11-01-008ROUND ROCK, TEXAS PURPOSE. PASSION. PROSPERITY. Item Caption: City Manager Approval Summary Sheet Consider executing Quantity Adjustment/Change Order No. 7 - Final with RGM Constructors, L.P. for the Wyoming Springs Drive Improvements Project. Approval Date: January 7, 2011 Department: Infrastructure Development and Construction Management Project Manager: Bill Stablein Item Summary: Quantity Adjustment/Change Order No. 7 - Final is to make final adjustments to several bid item quantities to reflect as -built conditions and to add work that was not foreseen when the design of the project was finalized. Strategic Plan Relevance: Goal No. 26.0: Construct major element of the transportation and mobility system as approved by Council in the Master Transportation Plan. Cost: ($12,681.03) Source of Funds: Round Rock Transportation Development Corporation Construction REV. 6/10/10 RQUNO_ROCK, TEXAS rev, 09/10 Contract Quantity Adjustment/Change Order Department: Transportation Administration Project Name: City Project ID Number Justification WYOMING SPRINGS DRIVE IMPROVEMENTS TX04WY0 Date: Change Order/Quantity Adjustment No. Page 1 of 4 12/10/2010 RMV SERVICE PED., WATERING, TEMP. POWER FOR IRRIGATION, RMV RAMP & INSTL CURB / SIDEWALK @ SCHOOL, RIBBON CURB, EXTRA NAL WORK INFRONT OF COMMUNITY CENTER, ADDITONAL STRIPING FOR SYMERS, AND FINAL QUANTITY ADJUSTMENT SUMMARY Original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Original Contract Price Pius Change Order(s) Plus Quantity Adjustment(s): Original Contract lime: Contract Time Prior to this Change Order: Contract Time with All Approved Change Orders: Prepared By: Contractor Approval: City Staff Approval: Signature City Official Approval: Signature gnature Signature 4,11-OI_Ool Amount % Chan e $2,050,016.90 $175,168.64 -$24,548.53 $150,620.11 $2,200,637.01 I f $244,869.89 /o $11,867.50.311M3 256 737.39 o Wig $2,457,374.40 mg go.40 6:50e4 4 i t yi✓AttL /i2 Printed Name, Title and Company d ate Miff t; LQ% "044414 ✓ NAn/Acc,C , /� 07y Printed Name, Title and Company IIJJ D 124/40 Printed Name, Title Date C1uJ� lb bEiIER'S . VA , Aci;�,8.-rvrnAwa /7 t2 '/ Printed Name, Title Date rev, 09/10 Contract Quantity Adjustment/Change Order ROLINO ROCK., TEXAS Page 2 of 4 Chan a Order Data Contract Time Bid Item # Item Descri tion and Chan e Unit . Adjustment Unit Price Amount Da s 200 201 202 203 204 ELECT SRV & PED REMOVAL HAND WATERING / TEMP POWER RIBBON CURB @ SYMERS LS 1 LS 1 RMV RAMP & INSTL CURB / SDWLK LF 30 $3,289.00 $3,728.50 EXTRA WORK INFRONT OF CENTER LS 1 LS 1 $20.00 $3,000.00 $1,250.00 $3,289.00 $3,728.50 $600.00 $3,000.00 $1,250.00 TOTALS: $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 0.00 $11,867.50 0 rev, 09/10 R0.11.11•41:0 MOCK, X.•••15 Bid Item # 7 9 Contract Quantity Adjustment/Change Order unatity Adjustment Data Item Descri • tion and Chan e ASPHALT STABILIZED BASE Unit TON -328 Unit Price 28 29 30 31 PRIME COAT 4" PIPE GAL -1353 Amount $53.00 -$17,385.06 Page 3 of 4 Time Adjustment Da LF -100 32 47 48 49 50 51 52 53 8" PIPE 12" PIPE 16" PIPE 30" PIPE LF -100 LF -100 LF -100 PAVEMENT MARKING PAINT (W)(6 IN)(BRK) PAVEMENT MARKING PAINT (W)(6 IN)(SLD) PAVEMENT MARKING PAINT (W)(8 IN)(SLD) PAVEMENT MARKING PAINT (W)(12 IN)(SLD) PAVEMENT MARKING PAINT (W)(24 IN)(SLD) PAVEMENT MARKING PAINT (Y)(4 IN)(SLD) PAVEMENT MARKING PAINT (Y)(12 IN)(SLD) LF -10 LF -100 $3.10 $17.00 $25.00 $37.00 $48.00 $105.00 LF 1156 LF 272 LF -19 LF 33 LF 2410 LF 24 54 55 56 57 58 60 61 62 64 66 77 80 PAVEMENT MARKING PAINT (W)(WORD) PAVEMENT MARKING PAINT (W)(ARROW) THERMO PAVEMENT MARKINGS (W)(4 IN)(BRK THERMO PAVEMENT MARKINGS (W)(4 IN)(SLD) THERMO PAVEMENT MARKINGS (W)(8 IN)(SLD) THERMO PAVEMENT MARKINGS (W)(24 IN)(SLD) THERMO PAVEMENT MARKINGS (Y)(4 IN)(SLD) THERMO PAVEMENT MARKINGS (Y)(12 IN)(SLD) THERMO PAVEMENT MARKINGS (W)(ARROW) REFLECTIVE PAVEMENT MARKER (TY II - C -R) 82 83 IRRIGATION PIPE (4 IN) (PVC) EA 1 EA 8 LF -100 $0.12 $0.46 $0.19 $1.54 $3.10 $0.13 $1.60 $77.00 $41.00 LF 1156 LF 272 LF 33 LF 2410 LF 24 EA 6 EA -15 $0.31 $0.46 $0.62 $5.40 $0.33 $2.85 $87.00 TREE PROTECTION STABILIZED CONSTRUCTION ENTRANCE (TY I) SILT FENCE LF 700 LF -674 EA -1 LF -220 $4.30 $4.40 $2.55 $1,300.00 84 102 103 104 144 DRILL SHAFT (RDWY ILL POLE) (30 IN) PED DETECT (2 INCH PUSH BTN TRAFF SIG PULL BOX WITH APRON (TY D) CONDT (PVC) (SCHD 40) (3") 145 FIBER ROLL LF -8 EA 6 EA -2 LF -809 $1.75 $144.00 $106.00 $720.00 PAVEMENT MARKINGS PAINT (W)(6 IN)(SLD) LF -300 LF -440 $6.10 $4.40 $0.19 -$4,193.59 -$1,700.00 -$2,500.00 -$3,700.00 -$4,800.00 -$1,050.00 -$12.00 $531.76 $51.68 -$29.26 $102.30 $313.30 $38.40 $77.00 $328.00 -$31.00 $531.76 $168.64 $178.20 $795.30 $68.40 $522.00 -$64.50 $3,080.00 -$1,718.70 -$1,300.00 -$385.00 -$1,152.00 $636.00 -$1,440.00 -$4,934.90 -$1,320.00 -$83.60 ROUNO,ROCK, TEXAS 2V, 09/10 Contract Quantity Adjustment/Change Order Page 4 of 4 TOTALS: -$24,548.53 0 148 PAVEMENT MARKINGS PAINT (Y)(4 IN)(SLD) LF -2 $0.13 -$0.26 150 THERMO PAVEMENT MARKINGS (W)(6 IN)(SLD) LF -50 $0.46 -$23.00 157 CURB RAMPS (TY 1) EA -1 $757.00 -$757.00 162 PULL BOX WITH APRON (TY D) EA -1 $720.00 -$720.00 172 PAVEMENT MARKING PAINT (W)(12 IN) (SLD) LF -110 $1.53 -$168.30 173 THERMO PAVEMENT MARKINGS (W)(12 IN)(SLD) LF 10 $2.80 $28.00 175 THERMO PAVEMENT MARKINGS (WXYIELD BAR) LF -48 $12.80 -$614.40 87 CONDUIT (PVC) (SCHD 80) (2") (BORE) LF 607 $29.50 $17,906.50 112 ELEC CONDR (NO. 08) BARE LF 85 $1.05 $89.25 165 ELEC CONDR (NO. 8) BARE LF 85 $1.03 $87.55 Page 4 of 4 TOTALS: -$24,548.53 0