Loading...
CM-11-07-153ROUND ROCK, TEXAS PURPOSE. PASSION. PROSPERITY Item Caption: City Manager Approval Summary Sheet Consider executing a Fiber Optic Cable Agreement with TW Telecom LLC for the Southwest Downtown Infrastructure Improvement - Main Street Project. Approval Date: July 29, 2011 Department: Transportation Project Manager: Todd Keltgen PUBLIC WORKS OPERATIONS MANAGER Item Summary: As part of the relocation of the dry utility infrastructure for the Southwest Downtown Infrastructure Main Street Project, the relocation of Time Warner Telecom's dry utilities will be required. This agreement covers costs associated with sending a Time Warner Telecom Field Engineer to record actual footages between poles or placement of conduit, stake placement of Time Warner Telecom poles, and completion and submission of any required permits. Also included is the cost to draft base information into the CAD system and design coax/fiber cable network into a design program. Materials, hardware and Time Warner Telecom labor also make up a portion of the total cost. Strategic Plan Relevance: 26.0 Construct major elements of the transportation and mobility systems as approved by council in the master transportation plan. Cost: $5,022.50 Source of Funds: 4B -Round Rock Transportation Corporation -Construction telecom FIBER OPTIC CABLE RELOCATION AGREEMENT The Fiber 0 tic Cable Relocation Agreement ("Agreement") is made, entered into, and effective this day of , 2011, by and between Round Rock, Texas ("REQUESTING PARTY"), a Municipality, and a politica subdivision of the State of Texas, having a mailing address of 221 E. Main, Round Rock, TX 78664, and tw telecom of texas llc, ("tw telecom" or "TWTC"), a Delaware limited liability company, having a mailing address of 10475 Park Meadows Drive, Littleton, CO 80124. Recitals A. REQUESTING PARTY has implemented a street improvement project in the City of Round Rock, TX, which requires the relocating and undergrounding of aerial fiber located within the public rights- of-way along North San Saba and Main. This relocation project shall be referred to as the "Relocation Proj ect". B. The fiber optic cables of tw telecom ("Fiber Optic Cables") currently located in the area of the Relocation Project need to be relocated from aerial to underground, as reflected on Exhibit A attached hereto and incorporated herein. C. In order to perform the Relocation Project in a timely manner, REQUESTING PARTY has agreed to pay all the costs and expenses for the Relocation Project, including the relocation of the Fiber Optic Cables. Now, therefore, in consideration of the mutual promises and covenants contained herein, the parties agree as follows: 1. REQUESTING PARTY agrees to bear all direct and indirect costs incurred by tw telecom relating to the relocation of the Fiber Optic Cables in connection with the Relocation Project, including, but not limited to, removal of fiber optic cable, replacement of fiber optic cable, underground conduit, labor, project management, inspection, materials, permit and license fees, construction, repair of damages, administrative overhead, taxes, travel expense, legal fees and other related out-of-pocket expenses (collectively "Fiber Optic Cable Relocation"). REQUESTING PARTY waives any and all delay damage claims, except if caused solely by the gross negligence or willful misconduct of tw telecom. 2. The total cost of the Fiber Optic Cable Relocation is estimated to be a maximum of Five Thousand Twenty Two and 50/100 Dollars ($5,022.50), as detailed in Exhibit B attached hereto and incorporated herein. REQUESTING PARTY agrees to submit payment equal to 100% of the estimated costs in the amount of $5,022.50 ("Advance Payment") as stated herein within ten (10) days of the date of the invoice sent by TWTC to REQUESTING PARTY. Full execution of this Agreement and receipt of Advanced Payment by tw telecom are required prior to the commencement of any work. tw telecom shall provide written notice to REQUESTING PARTY if tw telecom becomes aware that actual costs will exceed the estimated total cost. In the event the actual costs exceed the estimated total cost, REQUESTING PARTY agrees to pay the excess within ten (10) days of the date of the invoice sent by TWTC to REQUESTING PARTY, except as provided in Section 4 below. Failure to pay the excess within the time herein provided shall entitle TWTC to cease the work hereunder until payment is received. 3. Payment shall be made payable to and delivered by overnight mail to: tw telecom of texas llc PO Box 172567 Denver, CO 80217-2567 The check shall contain the following reference: PA# 1100001477. Without this reference on the check the construction start date may be delayed. C.N\- t.1-67- 16-3 4. Any design changes by REQUESTING PARTY, or other conditions whether or not they could have been reasonably anticipated by REQUESTING PARTY or tw telecom at the time of this Agreement, that result in an increase in tw telecom's estimate of cost or time shall be paid for by the REQUESTING PARTY and carried out under this paragraph 4. tw telecom will request such additional funding and/or additional time through a request for approval of a written change order. All change orders will be in writing and must be accepted by both parties and any additional payments shall be made by REQUESTING PARTY to tw telecom before tw telecom proceeds to execute the work or, if work has been initiated, to continue executing the work, except in an emergency situation endangering life or property. Under no circumstances will tw telecom's request for a change order, or the issuance of a change order, be deemed or used by REQUESTING PARTY as evidence of tw telecom's delay or alleged delay in the Relocation Project. 5. tw telecom agrees to commence, and thereafter diligently complete, the Fiber Optic Cable Relocation within forty-five (45) days of: (i) this Agreement fully executed (ii) receipt of 100% Advance Payment from REQUESTING PARTY and (iii) receipt of all permits, licenses, or other authorizations from applicable governmental agencies or private parties required in connection with the Fiber Optic Cable Relocation. 6. Written notice shall be given to tw telecom by REQUESTING PARTY at least forty-eight (48) hours, excluding Saturday, Sunday and legal holidays, in advance of commencement of any work by REQUESTING PARTY or its contractors in the immediate area of tw telecom's work; provided however, that REQUESTING PARTY shall not work within ten feet (10') of either side of the tw telecom facilities until the Fiber Optic Cable Relocation is completed. Said notice shall be given to those individuals listed on Exhibit C attached hereto and incorporated herein. 7. In the event of an emergency, REQUESTING PARTY shall provide telephonic notice to tw telecom at 800-829-0420 immediately upon REQUESTING PARTY's knowledge of such emergency. 8. The obligations of tw telecom are subject to force majeure and tw telecom shall not be in default in this Agreement if any failure or delay in performance is caused by strike or other labor problems, accidents; acts of God, fire, flood, adverse weather conditions, materials or facility shortages or unavailability, lack of transportation, the imposition of any governmental codes, ordinances, laws, rules, regulations or restrictions, including, without limitation, the necessity of obtaining permits or environmental assessments or environmental approvals, condemnation or the exercise of rights of eminent domain, war or civil disorder, or any other cause beyond the reasonable control of tw telecom. 9. This Agreement supersedes all previous oral and/or written agreements or understandings by and between tw telecom and REQUESTING PARTY pertaining to the Fiber Optic Cable Relocation and /or the Relocation Project. Any modification to this Agreement must be made in writing and signed by both parties. 10. This Agreement may be executed by the parties in separate counterparts, each of which shall be deemed to be an original copy, but all of which, together, shall constitute only one agreement. 11. Each party warrants that it has the full right and authority to enter into this Agreement. All necessary approvals and authority to enter into this Agreement have been obtained and the person executing this Agreement on behalf of each party hereto has the express authority to do so, and in doing so, to bind such party hereto. 12. Notices given by one party to the other party under this Agreement shall be in writing and shall be (a) delivered personally, (b) delivered by nationally recognized overnight delivery service, or (c) mailed by, certified US mail postage prepaid, return receipt requested to the following addresses of the parties or to such other address as either party shall designate by proper notice: If to tw telecom: Tina Davis Sr. Vice President and Deputy General Counsel tw telecom inc. 10475 Park Meadows Drive Littleton, CO 80124 Tel.: (303) 566-1279 With a copy to: Victor Gonzalez Director of Operations 9229 Waterford Centre Blvd, Suite 100 Austin, TX 78758 Tel.: (512) 485-6394 If to REQUESTING PARTY: City of Round Rock, Texas Attn: Alan McGraw Mayor 221 E. Main Round Rock, TX. 78664 Tel.:512-218-5400 With a copy to: Todd Keltgen PW Operations Manager 910 Luther Peterson Place Round Rock, Texas 78664 Tel.:512-218-5583 Notices will be deemed given as of the date of actual receipt or refusal to accept, as evidenced by the date set forth on the return receipt, confirmation, or other written delivery verification. IN WITNESS HEREOF, the parties have executed this Agreement as of the day and year first written above. Agreeing to be bound by its terms, tw telecom and REQUESTING PARTY have caused this Agreement to be executed by their respective duly authorized representatives in the dates written below. tw telecom of texas llc a Delaware limited liability company By: tw telecom holdings inc., its sole member By: Z Z/7 Printed Name: 1490 ti GONZA Lei Title: Dâ–º!f'fc . OF Opt'124%T40Nt Date: 7/1512P/ i REQUESTING PARTY: City of Round Rock, TX a Muni * ; y of the Stat of Texas B Printed Name:6te2,Cle Title: c../f ,4 , J Date: 0 7/& // Relocate east entry to RR LSO from aerial to underground. Exhibit A Description of Relocation Work Scope of Work (SOW) Install 900' new aerial over lash 800' of aerial. Pull in 500' of fiber into new conduit provided by the City of Round Rock. Splice 12 count in two locations. Exhibit B Detail of Estimated Cost Aerial Labor $1349.50 Underground Labor $840.00 Fiber Splicing $1500.00 Materials $1333.00 Total $5022.50 Exhibit C tw telecom and REQUESTING PARTY Contact Lists and Information Name Company Name Title Phone Number Todd Keltgen City of Round Rock City OPS Manager 512-218-5583 Victor Gonzalez tw telecom Director of Operations 512-485-6394