Loading...
CM-11-09-193ROUND ROCK, TEXAS Consider executing Quantity Adjustment/Change Order No. 3 with Chasco Constructors for the North Mays Street Extension Project. Item Caption: CM—II—Oct --1/3 RECEIVED SEP 152011 City Manager Approval Form Approval Date: September 16, 2011 Department Name: Transportation Department Project Manager: Lance Shellenberger Assigned Attorney: Steve Sheets Item Summary: The original contract with Chasco Constructors was approved by the City Council on October 28, 2010, to straighten and widen North Mays Street to provide better access to businesses and the City of Round Rock Police Department. Quantity Adjustments/Change Orders No. 1 and 2 were approved in 2011 to make needed changes due to unknown existing infrastructure adjustments, to add countdown peds, to lower an existing waterline to accommodate the relocation of a curb inlet, and to extend a 24" RCP. Quantity Adjustment/Change Order No. 3 with Chasco Constructors provides for final quantity adjustments for all items that went over or under, as measured in the field or agreed to by the project manager. The cost of Quantity Adjustment/Change Order No. 3 is $4,813.25. The final cost of the contract, with Quantity Adjustment/Change Order No. 2 with Chasco Constructors would be $2,203,441,15. No. of Originals Submitted: Two Project Name: North Mays Street Extension Cost: $4,813.25 Source of Funds: RR Trans Dev Corp Construction Source of Funds (if applicable): Select Source Fund Account Number: Finance Director Approval: Cheryl Delaney Date: 9/14/11 Department Director Approval: Gary Hudder Date: 9/12/11 **Electronic signature by the Director is acceptable. Please only submit ONE approval form per item. ** CIP Budget N/A OK I El Purchasing N/A OK N/A OK Accounting El N/A OK ITEMS WILL NOT BE PLACED ON THE COUNCIL OR CM AGENDA W/OUT PRIOR FINANCE AND/OR LEGAL APPROVAL REV. 6/20/11 r. - ROUND ROOC. TEXAS PURL AMOK 1.11011/1.1TV rev, 06/11 Department: Transportation Contract Quantity Adjustment/Change Order Project Name: North Mays Street Extension City Project ID Number TX01ARTM Justification Date: Page 1 of 3 8/31/2011 Change Order/Quantity Adjustment No. 3 Quantity Adjustment/Change Order # 3 provides for final quantity adjustments for all items that went over or under as mesaured in the field or agreed to by the project manager. SUMMARY Original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Adjusted Contract Price [Original Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)]: Difference between Original and Adjusted Contract Prices: Original Contract Time: Time Adjustment by previous Quan. Adj./Change Order: Time Adjustment by this Quan. Adj./Change Order: New Contract Time: City Sta For Contractor: Si For City of .e- Round R Signature Signature Prinfedtractor Company Name: (I i\,, Cha5-6s a Gluc e,lr., Preside/4-, DaroGA34-Nd8/31/I1 e Printed Name, Title ate Amount $2,147,473.80 $1,600.00 $4,813.25 $6,413.25 $2,153,887.05 $49,554.10 $0.00 $49,554.10 $2,203,441.15 $55,967.35 300 Calendar Days 0/0 Change 2.30% 0.00% 2.30% 21 Calendar Days 0 Calendar Days 321 Lovice slit&ilam6er90y- Printed Name, Title Calendar Days x'31-/( Date C I\ - 11-07 --I'?'3 mood ititcuitle* Printed Name, Title ate ROUND ROCK. TECAS rev, 06/11 Contract Quantity Adjustment/Change Order Project Name: North Mays Street Extension Quan. Adj./Change Order No.: 3 Change Order Data Page 2 of 3 on • a Item # Item Descri • tion Unit • . Unit Price Amount $0.00 Time Adjustment (Days) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTALS: $0.00 0 "PliP....- 1411111191l MUM IFICOMPIrt rev, 06/11 Contract Quantity Adjustment/Change Order Project Name: North Mays Street Extension Quan. Adj./Change Order No.: n 3 Page 3 of 3 Bid Item # 108 Item Descri . tion Hot Mix Asphalt Concrete Paving Unit EA • . -1,408 Unit Price $8.50 Amount -$11,968.00 on • a Time Adjustment (Days) 112 Concrete Curb & Gutter LF -240 $10.50 -$2,520.00 113 Concrete Sidewalks, 5" Thick SF 598 $0.00 113 Concrete Sidewalks, 5" Thick SF -598 $3.00 -$1,794.00 115 Concrete Driveways, 5" Thick SF 2,888 $5.00 $14,440.00 118 Adjust Water Valve Boxes to Grade EA 7 $315.00 $2,205.00 123 Minor Manhole Adjustment EA 1 $1,300.00 $1,300.00 141 Concrete Riprap, 5" SY 4 $40.00 $160.00 142 Dry Riprap, 18 " Stone CY -102 $55.00 -$5,610.00 149 Type F Railing EA 58 $120.00 $6,960.00 152 Barricades, Sign & Traffic Handling MO -3 $3,400.00 -$10,200.00 154 PVC Conduit, Sch. 40, 4" - Sleeves LF 1,084 $10.00 $10,840.00 161 Work Zone Pavement Markings Removal, Y, 4" SLD EA -4,195 $0.65 -$2,726.75 $0.00 Add. Alt. 504 Surface Milling EA 1,845 $2.00 $3,690.00 Add. Alt. 507 Hot Mix Asphalt Concrete Paving EA -492 $8.50 -$4,182.00 Add. Alt. 510 Concrete Curb & Gutter LF 86 $11.00 $946.00 Add. Alt. 511 Concrete Sidewalks, 5" Thick SF 640 $3.00 $1,920.00 Add. Alt. 523 PVC Conduit, Sch. 40, 4" - Sleeves LF 123 $11.00 $1,353.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTALS: $4,813.25 0