Consider executing Supplemental Contract No. 1 with Huggins/Seiler & Associates, L.P. for the South Mays Street at Gattis
School Road Project.
Item Caption:
Approval Date:
November 18, 2011
Department Name: Transportation Department
Project Manager: Bill Stablein
Assignrd Attorney: Steve Sheets
Item Summary:
The original contract with Huggins/Seiler & Associates, LP. was approved by the City Council on September 10, 2009, for a
revised preliminary schematic, design surveys, right-of-way documents, a Texas Department of Transportation approved
environmental assessment, pavement design, and full PS&E plans and documents. The amount of this contract was
$499,167.80.
Supplemental Contract No. 1 in the amount of $32,334 is needed to revise the design of this project to include the addition of
dual left tum lanes south bound to east bound and west bound to south bound for the intersection of South Mays Street and
Gattis School Road.
The revised contract total would be $531,501.80.
No. of Originals Submitted: Two
Project Name: South Mays Street at Gattis School Road
Cost: $32,344.00
Source of Funds: RR Trans Dev Corp Construction
Source of Funds (if applicable): Select Source Fund
Account Number:
Finance Director Approval: Cheryl Delaney Date: 11/16/11
Department Director Approval: Gary Hudder Date: 11/14/11
**Electronic signature by the Director is acceptable. Please only submit ONE approval form per item. **
CIP n ❑� Budget n [] Purchasing [ ❑ Accounting ❑� ❑
N/A OK N/A OK N/A OK N/A OK
ITEMS WILL NOT BE PLACED ON THE COUNCIL OR CM AGENDA W/OUT PRIOR FINANCE AND/OR LEGAL APPROVAL
REV. 6/20/11
STATE OF TEXAS
COUNTY OF WILLIAMSON
SUPPLEMENTAL CONTRACT NO. 1
TO CONTRACT FOR ENGINEERING SERVICES
FIRM: HUGGINS/SELLER & ASSOCIATES, L.P. ("Engineer")
ADDRESS: 116 East Main Street, Round Rock. TX 78664
PROJECT: South Mays Street at Gattis School Road
This Supplemental Contract No. 1 to Contract for Engineering Services is made by and between
the City of Round Rock, Texas, hereinafter called the "City" and Huggins/Seiler & Associates,
L.P., hereinafter called the "Engineer".
WHEREAS, the City and Engineer executed a Contract for Engineering Services, hereinafter
called the "Contract", on the 10th day of September, 2009 for the South Mays Street at Gattis
School Road Project in the amount of $499,167.80; and
WHEREAS, it has become necessary to amend the Contract to modify the provisions for the
scope of services and to increase the compensation by $32,334.00 to a total of $531,501.80; and
NOW THEREFORE, premises considered, the City and the Engineer agree that said Contract
is amended as follows:
Article 2, Engineering Services and Exhibit B, Engineering Services shall be amended as set
forth in the attached Addendum To Exhibit B. Exhibit C, Work Schedule shall be amended as
set forth in the attached Addendum To Exhibit C.
Il.
Article 4, Compensation and Exhibit D, Fee Schedule shall be amended by increasing by
$32,334.00 the lump sum amount payable under the Contract for a total of $531,501.80, as
shown by the attached Addendum to Exhibit D.
IN WITNESS WHEREOF, the City and the Engineer have executed this Supplemental
Contract in duplicate.
Supplemental Contract Rev.12/01/08
0199.7124; 00236597 84275
TX02MAGAT
1
CM -ll -Ii -23y
HUGGINS/SEIL _ ' & ASSOCIATES, L.P.
By: `go
BI1
9
3 NOV. I t
Date
Supplemental Contract
0199.7124; 00236597
TX02MAGAT
A ' P ' OVED AS TO FORM:
SK.*. 4'O ' wood, Step! : n L. Sheets, City Attorney
Cify nuut�'
Rev.12/01 /08
84275
ADDENDUM TO EXHIBIT B
Engineering Services
The changes to the scope of this project are as follows:
This project consists of revising the intersection of South Mays Street and Gattis School Road.
The project includes a traffic study to determine the need for additional turn lanes. The traffic
study will include three day traffic counts at determined locations and will include 1) No build
Option present and design year, 2) Two design options of improvements for present and design
year and 3) Stripping options for left turn lanes eastbound on Hesters Crossing bridge over IH 35
for present and design year. Based on findings from the traffic study, a preliminary schematic
will be revised and resubmitted for City of Round Rock approval. Design surveys, Right of Way
documents for a maximum of 14 parcels of land and full PS&E plans and documents are
required.
The work effort and the management of the projects included in this contract will be conducted
in the Engineer's office in Round Rock, Texas. The Engineer will be readily available and
accessible to the City of Round Rock's staff and will meet with the City's project manager as
necessary. All work is subject to the review and approval of the City of Round Rock.
The Engineer will solicit and secure written permission for entry to accomplish any work beyond
the existing right-of-way line.
The Engineer is fully responsible for any traffic control required for any data collection
activities. The control must be consistent with the City's procedures. The Engineer may not
close a lane of traffic without the written approval of the City.
The Engineer shall provide the following services:
1. Meet with the City to discuss schedule and scope of work
2. Coordinate sub -consultant survey work and preparation of existing conditions base map
and DTM.
3. Coordinate sub -consultant work for survey and preparation of R.O.W. sketches and
documents.
4. Assist in identification and location existing utilities and coordinate utility relocations as
required.
5. Provide complete PS&E package including storm sewer design, traffic control plan and
modifications for the widening/total reconstruction of the existing roadways to the
approved typical section.
6. Prepare signal plans for Mays and Gattis Intersection.
7. Preparation of any necessary standards, specifications and/or detail sheets when not
available from the City.
8. Prepare bidding documents for City Letting process.
9. Provide a draft advertisement for City review and advertise project for letting.
10. Provide 25 copies of construction plans and bidding documents.
11. Assist the City with the letting event documentation and assessment of bids.
12. Provide any plan and/or specification interpretation required during the construction
process.
ADDENDUM TO EXHIBIT C
Work Schedule
Attached Behind This Page
O
N
a
1
C
t
IL
4
8
n
1
1
IL
C
8
1
7
7
c
El.
a
LL
C
•
7
0
Lr
v
a
i
a
3
1'
m
t
1
1
i
A
e
0
0
0
U
a
a
a
1
E
O
Ty•LL
i
C
3
i
1
n
1
K
i
d
8
1
a
E
E
4
ADDENDUM TO EXHIBIT D
Fee Schedule
Attached Behind This Page
I ..
Exhibit D
Fee Schedule
Task
Total
Total
Other
TOTALS
Labor Hours
Loaded Labor Cost
Direct Costs
Subconsultants
Task 1: (e.g. surveying)
Task
0
$ -
$ -
$ -
$
2: (e.g. public outreach and concept design development)
Task
0
$ -
$ -
$ -
$ -
3: (e.g. preliminary design/ 30% plans)
Task
0
$ -
$ -
$
$
4: (e.g. final design/ 60%, 90%, 100% plans)
Task 5: (e.g. bid phase services)
289
0
$ 32,334.00
$ -
$ -
$ -
$ -
$ -
$ 32,334.00
$
Task 6: (e.g. construction phase services)
0
$ -
$ -
$
-
Task 7: (e.g. project management)
0
$ -
$ -
-
$ -
$
$
GRAND TOTAL: I
289
$ 32,334.00 II
$ - 1
$ - 1
$ 32,334.00