CM-12-05-095CM-ioS-s RECEIVED
MAY23 2012
ROUND ROCK, TEXAS City Manager Approval Form
PURPOSE. RYSSIO . PROSPERITY
item Caption:
Consider executing Quantity Adjustment/Change Order No. 1 with RGM Constructors of Texas, LLC for
the Resters Crossing Road & La Frontera Boulevard Street Reconstruction Project.
Approval Date: May 25, 2012
Department Name: Transportation Department
Project Manager: Bill Stablein
Assigned Attorney:
Stephan L. Sheets
Item Summary:
Install low profile barriers to save existing median trees and additional quantities for work zone striping removal.
No. of Originals Submitted: 2
Project Name: Nesters Crossing Rd & La Frontera Blvd Street Reconstruction
Cost: $25,685.00
Source of Funds: RR Trans Dev Corp Construction
Source of Funds (if applicable): Select Source Fund
Account Number:
Finance Director Approval: LO for C. Delaney
Department Director Approval: Gary Hudder
Date: 5-22-2012
Date: 5/21/12
-"'Eiectronic. s;,,n; ttir_> by the Dir
P,C7Se J., ysubrr) y;.c "7, ! t:.; :oe,
CIP n n Budget n n Purchasing E Accounting El
N/A OK N/A OK N/A OK N/A OK
ITEMS WILL NOT BE PLACED ON THE COUNCIL OR CM AGENDA W/OUT PRIOR FINANCE AND/OR LEGAL APPROVAL
REV. 6/20/11
4411°2=DIII.Aoac.;..rftsr,
rev, 04/11
Contract Quantity Adjustment/Change Order
Department: Transportation Department
Project Resters Crossing Rd. & La Frontera
Name: Blvd Street Reconstruction
City Project
ID Number WRO1OSP
Justification
Date:
Change Order/Quantity Adjustment
No.
Page 1 of 3
5/10/2012
1
INSTALL LOW PROFILE BARRIERS TO SAVE EXISTING MEDIAN TREES AND ADDITIONAL QUANTITIES FOR WK ZN STRIPING
REMOVAL
SUMMARY
Original Contract Price:
Previous Quantity Adjustment(s):
This Quantity Adjustment:
Total Quantity Adjustment(s):
Total Contract Price with Quantity Adjustment(s):
Previous Change Order(s):
This Change Order:
Total Change Order(s) To Date:
Adjusted Contract Price [Original Contract Price Pius
Quantity Adjustment(s) Plus Change Order(s)]:
Difference between Original and Adjusted Contract Prices:
Original Contract Time:
Time Adjustment by previous Quan. Adj./Change Order:
Time Adjustment by this Quan. Adj./Change Order:
New Contract Time:
2
Amount
% Change
$0.00
$25,685.00
25 685.00
1
$0.00
$0.00
$0.00
$2,954,131.71
$25,685.00
0.00
0.00
0.00
0
0
2 0
For Contractor:
For City of-
Round Rock:
Printed Contractor Company Name:
Signature
RGM Constructors of Texas, LLC
"11.016.)40 6A4
Printed Name, Title
ate
ci-Nzi\AVoodi btu' Zvi tuna r QS z"
T
Printed Name, Title Date
rev. 06/11
Item #
Contract Quantity Adjustment/Change Order
Project Name:
Quan. Adj./Change Order No.:
Item Description
Hesters Crossing Rd. & La Frontera Blvd Street
Reconstruction
1
Cha • Order Data
Page 2 of 3
Q Unit Price Amount
Time
Adjustment
Days
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
0.00
TOTALS: $0.00
rev, 06/11
Contract Quantity Adjustment/Change Order
Project Name:
Quan. Adj./Change Order No.:
Resters Crossing Rd. & La Frontera Blvd Street
Reconstruction
1
Bid Item #
Item Descri . . on
32
33
56
Unit Qty. Unit Price
(: '&I�— L.W
PROFXTY 1)
PORT CTB (FUR & IN
5T)(LOW
PROF)(TY 2)
EUMINATING EXISTING PAVEMENT
MARKINGS (4")
LF
2480
Amount
$8.00
$19,840.00
$2,520.00
LF 665 $5.00 $3,325.00
$0.00 $0.00
$0.00 $0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$L0.00
$0.00
$0.00
$o
$0.00
$0.00
$0.00
$0
$0.00
LF 140
$18.00
.00
.00
Page 3 of 3
Time
Adjustment
Da s
1
1
TOTALS: $25,685.00