CM-12-09-18712_01'1$4 �%Mr RECEIVED SEP 19 2012 ROUND ROCK, TEXAS City Manager Approval Form PURPOSE PASSION PROSPERITY Item Caption: Consider executing Quantity Adjustment/Change Order No. 1 with AgH2O Holdings LLC for the OSPV Reuse Water Irrigation Project Phase 2. Approval Date: September 21, 2012 Department Name: Parks and Recreation Department Project Manager: David Buzzell, Park Development Manager Assigned Attorney: 1. Kay Gayle Item Summary: This item is for Change Order #1 which includes the following changes: 1) Additional waterline due to the existing hose bibs being tied on to the reuse irrigation line. The additional waterline connects the hose bibs to the potable water line and brings them into compliance with TCEQ regulations. 2) Additional charge related to the installation of the turf irrigation on the multipurpose field. Due to the construction timing of the multipurpose field, the contractor has to install the turf irrigation system for this area in two phases which results in additional work. 3) Re-routing of approximately 240 linear feet of existing tree irrigation. The existing tree irrigation was located under a corner of the new multipurpose field and needed to be re-routed so staff would not have to destroy the multipurpose field if repairs were needed on this section of the line. The irrigation line was not shown on the as -built plans for the area. This item aligns with the Strategic Plan: Goal 2 - Water : 2) Reduce water consumption by City customers and City facilities and parks Goal 2 - Water : 6) Develop water reuse system serving the Northeast areas and parks No. of Originals Submitted: 1 Project Name: OSPV Reuse Water Irrigation Project Phase 2 Cost: $ 12,654.56 Source of Funds: General Self -Financed Construction Source of Funds (if applicable): Select Source Fund Account Number: pk02reuse Finance Director Approval: LO for C. Delaney Department Director Approval: Date: 9-18-12 Date: **Electronic signature by the Director is acceptable. Please only submit ONE approval form per item. ** CIP I I ❑� Budget N/A OK N/A OK Purchasing El ❑ N/A OK Accounting N/A OK ITEMS WILL NOT BE PLACED ON THE COUNCIL OR CM AGENDA W/OUT PRIOR FINANCE AND/OR LEGAL APPROVAL REV. 6/20/11 rev. 08/12 Contract Quantity Adjustment/Change Order Department: Parks & Recreation Department Project OSPV Reuse Water Irrigation Project Name: (Phase 2) City Project ID Number pk02reuse Justification Page 1 of 3 Date: 9/10/12 Change Order/Quantity Adjustment No. 1 Changes due to 1)unforeseen potable waterline connections, 2)exdsting irrigation location issues, 3)accellerated construction of the mulitipurpose field resulting in a staggered sequence of irrigation construction, and 4) addition of one irrigation zone not shown on the plans SUMMARY Original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Adjusted Contract Price [Original Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)]: Difference between Original and Adjusted Contract Prices: Original Contract Time: Time Adjustment by previous Quan. Adj./Change Order. Time Adjustment by this Quan. Adj./Change Order: New Contract Time: Prepared By: 0 Amount % Change $0.00 02.25 $0.00 $12,654.56 $12,654.56 346,956.81 $12,654.56 0.00 0.04 0.04 0 0 0 N4or\i %Nk.-22\\_4Td4( tQaOrti* UN. CV -1 -A -R Si . nature Printed Name, Title, Com ny Date Contractor: City JAMES R. LES)cc, GeV /+i60. ,q HL0 hbLo /41.1 LLC 9A 211z._ Signature .1U-1/111-..\ Printed Name, Title, Company Date BOUND IN(x:. TTJ(As rev, 08/12 Contract Quantity Adjustment/Change Order Project Name: OSPV Reuse Water Irrigation Project (Phase 2) Quan. Adj./Change Order No.: 1 Change Order Data Page 2 of 3 Item # C01.1 Item Description Rough in of multipurpose field irrigation rotors and exacavate after field grading Unit LS Qty. 1 Unit Price $6,648.54 Amount $6,648.54 Contract Time Adjustment Da 4 CO1.2 Furnish and Install 680 If of waterline for hose bibs and install soc (6 new rotors LS 1 $2,556.02 $2,556.02 3 C01.3 Re-route 1 • existing tree irrigation main and lateral lines LS 1 $1,150.00 $1,150.00 1 CO1.4 Furnis a • Insta two 2 • •ttery operated irrigation contoller "Nodes' for existing tree irrigation EA 2 $150.00 $300.00 1 CO 1.5 umis . I . r 200 r . irrigation . I, •. ;A. (J .; :-.) LS 1 $2,000. e . $2,000. t I 1 - _- $0.00 -� - _- $0.00 ---� $0.00 ---� $0.00 - _--� $0.00 -�� $0.00 - �- $0.00 - _-�- $0.00 -� - _- $0.00 - _- $0.00 - ---� $0.00 scot --�- $0.00 - _- 0.00 $0•11 - ---� 0.00 -� $0.00 �: •