CM-13-07-106City of Round Rock
ROUND ROCK, TEXAS
PURPOY. PASLON PROSPERITY
Agenda Item Summary
Agenda Number:
Title: Consider issuing a Purchase Order to Playworks, Inc. for installation of
support piers and a park pavilion for the Lake Creek Park Improvement
Project.
Type: City Manager Item
Governing Body: City Manager Approval
Agenda Date: 7/12/2013
Dept Director: Rick Atkins
Cost: $11,653.25
Indexes: General Self -Financed Construction
Attachments: 07-12-13-LAF-Lake Creek Park Improvement-Playworks Inc,
07 -12 -13 -Lake Creek Park Improvement-Playworks Inc Agreement
Text of Legislative File CM -13-07-106
This item will authorize the City to issue a purchase order to Playworks, Inc. for installation of support piers and
a park pavilion for the Lake Creek Park Improvement Project. The pavilion will provide shade for park visitors.
The project includes the demolition of existing park amenities and construction of a new playground, trail
segment, park pavilion, rest room building and site furnishings (picnic tables, grills, benches, and trash
receptacles).
This project was identified in Year 3 of the PARD Repair and Replacement Program. Staff met with the
neighborhood twice over the past year to gather input on the park master plan and improvement plan. The final
improvement plan presented to the neighborhood received positive feedback and the neighborhood was
excited to see the redevelopment efforts.
Replace with Recommended Action (the ..Recommended Action above must not be removed)
City of Round Rock Page 1 Printed on 7/11/2013
LEGAL DEPARTMENT APPROVAL FOR CITY COUNCIL/CITY MANAGER ACTION
Required for Submission of ALL City Council and City Manager Items
Department Name: PARD
Project Mgr/Resource: Aileen Dryden
Council Action:
ORDINANCE
Project Name: Lake Creek Park Improvement
ContractorNendor: Playworks, Inc.
El RESOLUTION
Agenda Wording
City Manager Approval
CMA Wording
Consider issuing a Purchase Order to Playworks, Inc. for installation of support piers and a park pavilion for the Lake Creek Park
Improvement Project.
Attorney Approval
fAttorney
Notes/Comments
Date 7/1 ) t'
O:\wdox\SCCInts\0123\1300\MISC100277951.XLS Updated 6/3/08
PlayWorks, Inc.
Toll free: (800) 726-1816 Free Fax: (800) 560-9150
New Mexico Texas
9430 San Mateo., NE, Unit G 4743 Iberia Ave., Suite C
Albuquerque, NM 87113 Dallas, TX 75207
(505) 899-1762 (972) 488-9356
6/26/2013
PRICES AND PROJECT QUOTATION
PRICES shown in all of our Quotations are subject to change without notice. QUOTATION: Is for acceptance within a maximum of 30 days
from date of Quotation and prices are guaranteed only for installations scheduled within one year from date of quotation.
TERMS & CONDITIONS
New accounts, nontax funded customers: 50% deposit and provide credit application. Balance due next 15 days or upon completion if installed
by PlayWell. Bonded public project terms: Bonding information and credit application required. Deposit may be required. Late penalties may
apply.
SURFACING REQUIRED!
IMPORTANT! The PlayWell Group and Playworld Systems, Inc. strongly recommend the use of resilient surfacing material under and around
all playground equipment. Refer to the Consumer Product Safety Commission's Publication Number 325, Handbook for Public Playground
Safety, for suggested guidelines. See catalog for use zone dimensions.
OWNER
All playground equipment and surfaces must be maintained and /or inspected on a regular basis. The recommended minimum is once a week.
Educate users in safe use of play equipment. Information signage is highly recommended to inform adults of their playground supervision
responsibilities.
DELIVERY TIME
Approximate Time to Deliver Materials is six weeks from the week the order is entered plus a few days for transit. Submittal approvals if
required will add additional time to the delivery schedule Order will be placed after deposits are received, credit is approved, and /or full
payment for material is made. Visa, MasterCard, and American Express accepted. Please disregard if you have established prior credit with
us. Please contact your Sales Consultant for additional information.
ROCK CLAUSE
PlayWorks, Inc. reserves the right to charge for additional manpower and equipment rental if subcontractors encounter rock that cannot be
penetrated to drill installation holes with a mechanical auger. Every effort will be made prior to installation to determine if additional rock
charges will be required. Your PlayWell Sales Associate will notify you and meet you at the work site to review the conditions requiring
additional charges.
SITE ACCESS NOTE
The site for equipment to be installed must be accessible by trucks, trailers, Bobcats and/or a tractor -trailer. In the event this equipment is
used at your site, please note there may be signs of access afterwards. We will try to keep this to a minimum. Please note, we are not
responsible for repairing sod, fixing concrete curbs, or sidewalks due to machinery trying to access the site through or over these items, unless
specifically spelled out in the above quotation! If the site is not accessible due to fences, landscaping, sprinkler systems, etc., please address
this issue with your PlayWell Sales Associate. PlayWell will review possible altemate means of access and include additional charges if
required in your proposal. Please discuss any concerns you may have about site conditions with your PlayWell Sales Associate prior to
accepting our proposal.
C M -\ 3-01 - t yip
ON SITE SECURITY
PlayWell Group installation sub -contractors install caution tape around the immediate work area. Tape is to be removed and disposed of by
the customer a minimum of 24 hours after completion. Orange Safety fencing or other security will be furnished for an additional charge.
Please contact your Sales Associate to request a quote.
UNDERGROUND UTILITIES NOTE
It is the customer's responsibility to locate ALL underground utilities in the area of installation and have them marked unless prior
arrangements are made. Please refer to Arkansas OneCall a minimum of 48 hours prior to digging. There are some public utilities that will
locate and mark their own lines if the customer calls them directly. Utilities usually require notification a minimum of 5-7 days prior to digging
when Dig Test is not used. Utility location includes but is not limited to power, water, gas, sewer, telephone, and cable television. We must
receive a faxed/mailed copy of the report from Dig Tess or the company that marks the locations of your lines before digging will start.
TRASH DISPOSAL
PlayWorks, Inc. installation sub -contractors will break down and consolidate all packing materials as much as possible. If a
customer -furnished dumpster is provided onsite, we will place trash within the dumpster. Haul off and disposal of trash at no additional
amount.
SITE COMMENTS
Site preparation by others is not listed on this quote. Site must be level, free of utilities, and rock. Site must be accessible to work trucks and
equipment. Install schedule based on site readiness, delivery of product, weather, and the results of weather on the site itself. No site security
provided after hours if not listed on this quote.
Installation will be orde ediately — -ceipt of w=pproval. Please fax all pages.
,40111,
SIGNATURE:
DATE 4 �(' —/ , ✓
PlayWorks, Inc.
Toll free: (800) 726-1816
New Mexico
9430 San Mateo., NE, Unit G
Albuquerque, NM 87113
(505) 899.1762
Free Fax: (800) 560-9150
Texas
4743 Iberia Ave., Suite C
Dallas, TX 75207
(972) 488-9356
INSTALLATION QUOTE
SQ -20779
6/26/2013
Customer
Contact
Ship To
City of Round Rock
City of Round Rock
City of Round Rock/Lake
Creek Park
221 E Main Street
David Buzzell
Aileen Dryden
Round Rock TX 78664
301 W. Bagdad, Ste 250
TBD
UNITED STATES
ROUND ROCK TX 78664
ROUND ROCK TX 78664
Tel: (512)-341-3355
UNITED STATES
UNITED STATES
Fax: (512)-218-5548
Tel: (512)-341-3355
Fax: (512)-218-5548
Account
Terms
Due Date
Account Rep
Schedule Date
235
UPON COMPLETION
6/26/2013
Carl Simmons
8/26/2013
Quotation
PO #
Reference
Ship VIA
Page
Printed
SQ -20779
Default Carrier
3
6!2612013
5:35:37PM
L
Item
Description
Qty
Price
UM
Discount
Amount
1
BuyBoard
BUYBOARD
1
$0.00
EA
$0.00
2
This is a BuyBoard Purchasing
Cooperative Quote. Pricing Reflects
BuyBoard Discounts as Listed on
Web Site www.buyboard.com Under
The Vendor Listing For The PlayWell
Group, Inc. #346-10 Expires
09/30/2013
3
4
IW -INSTALL
WIP Installation of Icon
1
$8,033.87
EA
$8,033.87
RH24x36M2V-P4
5
IW -CON -PIER
WIP Installation of Concrete Pier
6
$603.23
EA
$3,619.38
2' Diam x 3' Deep Non -Engineered
Concrete Footers
This Quotation is good for 30 Days from the date listed
Tax Details
Taxable
$0.00
above. We appreciate the opportunity to quote and look
EXEMPT $0.000
forward to serving your needs. To order, please fax this
signed form including color choices, if necessary, and
confirm the shipping address. This ship date is
approximate. We reserve the right to change and collect
Total Tax
$0.00
interest in the amount of 1.5% per month if payment is not
Exempt
$11,653.25
received in full in accordance with the terms set forth.
Play Safely and PlayWell.
Total
$11,653.25
Customer
PO No.
Balance
$11,653.25
Approved
By: Date: