CM-2014-365'ROUND ROCK. TEXAS PURPOSE nawn PROSPrnne City of Round Rock Agenda Item Summary Agenda Number: Title: Type: Governing Body: Agenda Date: Dept Director: Cost: Indexes: Attachments: Department: Consider executing Quantity Adjustment/Change Order No. 1 with AgH2O Holdings, L.L.C. for the 105 East Liberty Street Parking Lot Project. City Manager Item City Manager Approval 3/28/2014 Gary D. Hudder, Transportation Director $16,163.00 General Self -Financed Construction LAF - Quantity Adjustment -Change Order #1 w- AgH2O Holdings (00295318xA08F8), Chang Order -Adjustment Signed Copy 3-21-14 Transportation Department Text of Legislative File CM -2014-365 On September 10, 2013 the City Council awarded the construction services contract for 105 East Liberty Street Parking Lot Improvement to AGH2O Holdings, LLC at the cost of $483.645.75. The initial contract was for the construction of a parking lot with 54 new parking spaces from the existing 22 space parking lot. These improvements will include and increase of parking area along with new lighting and landscaped areas. Quantity Adjustment/Change Order No. 1 is needed to raise elevation on the dumpster pad and apron for dumpster pad, the demo and disposal of additional subbase in the alley. Also to install 20 LF of galvanized railing. The cost of this addtional work is $16,163.00. The total cost of the construction contract would be $499,808.75 Staff recommends approval City of Round Rock Page 1 Printed on 3/27/2014 LEGAL DEPARTMENT APPROVAL FOR CITY COUNCIL/CITY MANAGER ACTION Required for Submission of ALL City Council and City Manager Items Department Name: Transportation Project Mgr/Resource: Chris Cervenka ElCouncil Action: ORDINANCE Agenda Wording Project Name: 105 East Liberty Street Parking Lot ContractorNendor: AgH2O Holdings, L.L.C. n RESOLUTION f]City Manager Approval CMA Wording Consider executing Quantity AdjustmentlChange Order No. 1 with AgH2O Holdings, L.L.C. for the 105 East Liberty Street Parking Lot Project. Attorney Approval Attorney Notes/Comments Date ,3 it O:\wdox\SCCInts\0199\1395\MISC\00295318.XLS Updated 6/3/08 rev, 08/12 Department: Transportation Contract Quantity Adjustment/Change Order Project 105 E Libery Existing Parking Lot Name: Improvments City Project ID Number AAO2DTNLND Justification Page 1 of 3 Date: 3/4/14 Change Order/Quantity Adjustment No. 1 Quantity Adjustment/Changer Order #1 is need to raise elevation on the dumpster pad and apron for dumpster pad, the demo and disposal of additional subbase in alley. Also to install 20 LF of galvinized railing. SUMMARY Original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Adjusted Contract Price [Original Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)]: Difference between Original and Adjusted Contract Prices: Original Contract Time: Time Adjustment by previous Quan. Adj./Change Order: Time Adjustment by this Quan. Adj./Change Order: New Contract Time: Submitted for Approval Prepared By: Amount $483,645.75 $3,250.00 $3,250.00 $486,895.75 $12,913.00 $12,913.00 $499,808.75 $16,163.00 90 10 100 0/0 Change 0.00 0.03 0.03 Contractor: S' nature J City • oject Mana[jer: Mayor/City Manager CM -2014-365 Printed Name, Title, Company Date Approvals GOA/. - MC7/1 VZOPY Printed Name, Title, Company Date Managt! Printed Name, Title J 3/tgft1 Date Ste,e MrwoorCity 11Jlanaye_ a3AJ'Oy Printed Name, Title Date rev, 08/12 Contract Quantity Adjustment/Change Order Project Name: 105 E Libery Existing Parking Lot Improvments Quan. Adj./Change Order No.: 1 Change Order Data Page 2 of 3 Item # Item Description Unit Qty. Unit Price Amount Contract Time Adjustment (Days) 44 Additional Demo, Disposal, Subbase for Alley at Apron LS 1 $5,750.00 $5,750.00 5 45 Furnish and Install 20 LF GaIv. Rail LS 1 $3,125.00 $3,125.00 46 Additional Mobilization for Aphalt work LS 1 $1,875.00 $1,875.00 47 Furnish and Instal Two(2) 240V, 12 Circuit Lighing contactors, Photocell and Enclosures LS 1 $2,163.00 $2,163.00 2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTALS: $12913.00 7 R(N NI, RO A Il XAS rev, 08/12 Contract Quantity Adjustment/Change Order Project Name: 105 E Libery Existing Parking Lot Improvments Quan. Adj./Change Order No.: 1 Quantity Adjustment Data Page 3 of 3 Bid Item # Item Description Unit Qty. Unit Price Amount Contract Time Adjustment (nays) 16 Additional Concrete Work to Raise Dumpster Pad and Apron LS 1 $3,250.00 $3,250.00 3 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTALS: $3,250.00 3