R-13-02-28-I6 - 2/28/2013RESOLUTION NO. R -13-02-28-I6
WHEREAS, the City of Round Rock has previously entered into a contract ("Contract") with
Chasco Constructors for the Round Rock Sports Complex Project, and
WHEREAS, the Council has determined that it is necessary to make adjustments/changes to
the quantity of work to be performed or materials, equipment, or supplies to be provided, and
WHEREAS, it has been determined that it is necessary to adjust/change the quantities in said
Contract in accordance with the attached Quantity Adjustment/Change Order No. 1, Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS,
That the Mayor is hereby authorized and directed to execute on behalf of the City, Quantity
Adjustment/Change Order No. 1 to the Contract with Chasco Constructors for the Round Rock Sports
Complex Project, a copy of said quantity adjustment/change order being attached hereto as Exhibit
"A" and incorporated herein for all purposes.
The City Council hereby finds and declares that written notice of the date, hour, place and
subject of the meeting at which this Resolution was adopted was posted and that such meeting was
open to the public as required by law at all times during which this Resolution and the subject matter
hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act,
Chapter 551, Texas Government Code, as amended.
RESOLVED this 28th day of February, 2013.
OP�7X--,�
ALAN MCGRAW, Mayor
City of Round Rock, Texas
ATTEST:
SARA L. WHITE, City Clerk
0: \wdox\SCC1nts\0112\ 1304\MUNICIPAL\00268728.DOC/rmc
City of Round Rock
�ROUNDROCKTEXAS
wxroa iwsswn rxosrcnnrtx
Agenda Item Summary
Agenda Number: 16.
Title: Consider a resolution authorizing the Mayor to execute Quantity
Adjustment/Change Order No. 1 with Chasco Constructors to upgrade to
LED Lighting in the Gymnasium and Parking Lot for the Round Rock
Sports Complex Project.
Type: Resolution
Governing Body: City Council
Agenda Date: 2/28/2013
Dept Director: Chad McDowell, General Service Director of General Services
Cost: $64,451.00
Indexes: General Self -Financed Construction; Venue Tax Project Fund
Attachments: Resolution, Exhibit "A", Chasco Led Lighting
Text of Legislative File 13-048
LED Lighting upgrades to the Gymnasium and Parking Lot at the Sports Center would provide savings over
conventional lighting due to longevity of the bulbs and the monthly energy cost savings. HCE Engineers, MEP
for the Sports Center researched this change request and recommend that LED Lighting be used in these two
areas as the payback for this investment would be covered in a three year span or less savings per year in
electrical costs and maintenance would be approximately $21,400.00 per year.
Staff recommends approval.
City of Round Rock Page 1 Printed on 2122/2013
We, 08/12
Department: General Services
Project
Name: Sports Center
City Project
ID Number
7ustif cation
Page l of 3
EXHIBIT
Contract Quantity Adjustment/ Change Order ,�A»
Date: 2/28/13
Change Order/Quantity
Adjustment No. 1
.ED Lighting upgrades to the Gymnasium and Parking Lot at the Sports Center would provide savings over conventional lighting due to
ongevity of the bulbs and the monthly energy cost savings. HCE Engineers, MEP for the Sports Center researched this change request and
ecommend that LED Lighting be used in these two areas as the payback for this Investment would be covered in a three year span and
;avings per year in electrical costs would be approximately $ per year.
5UMMARY
Original Contract Price:
Previous Quantity Adjustment(s):
This Quantity Adjustment:
Total Quantity Adjustment(s):
Total Contract Price with Quantity Adjustment(s):
Previous Change Order(s):
This Change Order:
Total Change Order(s) To Date:
Adjusted Contract Price (Original Contract Price Plus
Quantity Adjustment(s) Plus Change Order(s)]:
Difference between Original and Adjusted Contract Prices:
Original Contract Time:
Time Adjustment by previous Quan. Adj./Change Order:
Time Adjustment by this Quan. Adj./Change Order:
New Contract Time:
Prepared By:
Submitted for Approval
Amount % Change
$14,527,295.00
$0.00
$0.00:
$14,527,295.001
0.00
$64,451.00 0.00
$64,451.00 0.00
E$14,591,746.001
$64,451.00
3 -Dec -13
3 -Dec -13
Z-lf-13
Signature
Printed Name, Title, Company
Date
Approvals
r
Contractor:
Charles J Glace Jr. Chasco Constructors
�• Z 4 !
Signature
Printed Name, Title, Company
Date
City Project
Manager: /�/
Chad McDowell, Director General Services
Signature
Printed Name, Title
Date
Mayor/City
Manager Alan McGraw, Mayor _
Signature Printed Name, Title Date
Contract Quantity Adjustment/Change Order
rer, 08/12
Project Name: Sports Center
Quan. Adj./Change Order No.:
rk�--- e% dA— r% -&-
Page 2 of 3
Item # Item Description Unit Qty.
. Unit Price Amount
Contract
Time
Adjustment
us s
1 LED Lighting Gymnasium & Parking Lot 1 $64,451.00 $64,451.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
TOTALS: I $64451.OU,:_
0
Change
Order
PROJECT:
(name, address)
Round Rock Sports Events Center
2400 Chtsho!m Tred
Round Rock, TX
TO (CONTRACTOR):
(name, address)
Chasco Constructors
P.O. Box 1057
Round Rock, Texas 78680
The Contract is changed as folloms:
Distribution to:
$14,527,295
Net change by previously authorized Change Order!
50
The Contract Sum prior to this Change Order was
OWNER
The Contract Sum will be increased by this Change Order
!:
ENGINEER
S 14,591,746
The Date of Substantial Completion as of the date of this Change Order has been affected b)
CONTRACTOR
FIELD
CONSTRUCTION NIANAGER[_.�
Add and delete the following items as per the attached CHANGE LOG
Add LED Lighting Upgrades per Chasco CP -010
',ot votid ontil signed by the 0%ter. Architect and Convector.
Signame of the Contractor indicates his agreement hermift including env adjustment in the Conuttt Sum or Contract Time.
CHANGE ORDER NO: One(l)
DATE: 8 -Feb -13
PROJECT NO: 11154
CONTRACT DATE: 26 -Jan -12
CONTRACT FOR: General Construction
$64,451
TOTAL: $64,451
The Original Contract Sum was
$14,527,295
Net change by previously authorized Change Order!
50
The Contract Sum prior to this Change Order was
514,527,295
The Contract Sum will be increased by this Change Order
$64,451
The new Contract Stun including this Change Orderwill be
S 14,591,746
The Date of Substantial Completion as of the date of this Change Order has been affected b)
Marmon Mok
ARCHITECT
Address: 700 North St. Mars, Ste 1600
San Antonio, TX 78205
By:
Shawn Bacon
DATE:
Chasco Constructors, Ltd., L.L.P.
CONTRACTOR
Address: P.O. Box 1057
Round Rock, Texas 786/80
By: 1....
Charles J. Ulace, Jr.0
DATE: I lilt' i
January 30, 2013
Marmon Mok Architecture
700 N. St. Mary's, Suite I600
San Antonio, TX 78205
Attention: Shawn Bacon, AIA
Ref: City of Round Rock Sports Center — RFP fm• LCD Lighting Upgrades
Shawn:
I' 0. Box 1057
Round ]tock, Texas 73680
(512)244-0600
1-855-441-4109
I'ax: (512) 214-0439
rllai1 K 61'sco.coIII
Chasco Constructors has prepared pricing to change selected lighting fixtures from those originally
specified in the Construction Documents to LED fixtures. As per the LED Lighting Upgrade RFP dated
12-18, EL 102.1 -Revised and EL 102.2 Revised both dated 12-19-12 and all prepared by Hendrix
Consulting Engineers Ave hereby submit a cost of $64,451.00 for this change. The revised amount noted
below includes only the Gymnasium lighting and the parking lot lighting. We understand this change will
not be funded from the Owner's Bettennent Allowance, but will be an addition to the Contract so the
below price reflects insurance, fees and bond. The revised breakdown of cost is as follows:
LED Lighting Substitutions
Gymnasium Lighting
S
279400.00
Paridng Lot Lighting
S
29,750.00
Cost to Subcontractor
S
57,150.00
Subcontractor Fee and Bond Cost
S 3,653.00
Total Cost from Subcontractor
S
60,803.00
OH, Fee, Insurance and Bouds - 6%
5
3,648.00
Total
S
64,451.00
If you have any question regarding our proposal enclosed herein please let me know,
Sincerely,
Chasco Constructors
Scott Badgett
Vice President — Building Estimating
b CONCRETE CONTRACTORS
February 0, 2013
TO: City of Round Rock
212 Commerce Cove
Round Rock, TX 78664
ATT: Larry Madsen
RE: Round Rock Sports Center — Chasco Job No. 11154
CP -010 — LED Lighting Upgrades
P.O. Box 1057
Round Rock, TX 78680
(512) 244-0600
Fax (512) 244-0489
We hereby submit our Change Proposal for your consideration and approval to execute
a change to the contract for the above referenced project. For your review and per your
request, we have provided pricing for labor, equipment and material to make revisions
per Chasco Letter of January 30, 2013, see attached.
Changes per attached Chasco CP No. 010 Pricing Sheet dated February 8, 2013:
$64,451.00
If approved, this change will result in a change to the Contract Amount by the sum of
$64,451.00. Please indicate if we are to proceed with this work by February 28,
2013. if approved, this CP will be incorporated into the next Owner Change Order.
Respectfully,
APPROVED BY:
Date
CHASCO CONSTRUCTORS
Scott Badgett
Vice President — Building Estimating
cc: File: 107 02_001
Field —
Ir �i,HRSCO
��ORSTAQCTORS
Chasco CP No: CP -010
Arch. PR No: NIA
Change Proposal Pricing Sheet
Rond Rock Sports Center
11154
Architect Project No: 11037
CO February 2013
Prepared by: Scott Badgett
Description: Chanoe selected If in fixtures from those orioinally spa m d (n Ute ConsW lion D m ntc In I FA firtnrea ax par th 1 cn
C Ing Upgrade RFP dated 12-18 EL 102 1-ReWsed and EL 102 2 Revised both gated 12-19-12 and all Prepared by Hendrix
Cnsultino Enalneem. The amount noted below in as oniv the Gymnasium lights and the parking lot liohOng
Further destdptan:
Overhead
•:e -SUBCONTRACT
UNIT TOTAL TOTAL
e .
Sales Tax Materials (only)
0.000%
$Q
SUBTOTAL
$62,627
Fee
1.250%
EMM, :r :r :r
SUBTOTAL
$63,410
Insurance
0.642%
$407
P&P Bond
1.000%
S634
DRANO TOTAL
$64,451
�- - •
���� rrr
rrr .r :r .r :r
Further destdptan:
Overhead
3.000°%
$1,624
Sales Tax Materials (only)
0.000%
$Q
SUBTOTAL
$62,627
Fee
1.250%
$783
SUBTOTAL
$63,410
Insurance
0.642%
$407
P&P Bond
1.000%
S634
DRANO TOTAL
$64,451
EXECUTED
ORIGINAL
DOCUMENT
FOLLOW
rev, Della
Department:
Project
Name:
General Services
Sports Center
Contract Quantity Adjustment/Change Order
Date: 2/28/13
City Project Change Order/Quantity
ID Number Adjustment No. 1
Justification
LED Lighting upgrades to the Gymnasium and Parking Lot at the Sports Center would provide savings over conventional lighting due to
longevity of the bulbs and the monthly energy cost savings. HCE Engineers, MEP for the Sports Center researched this change request and
recommend that LED Lighting be used In these two areas as the payback for this Investment would be covered in a three year span and
savings per year In electrical costs would be approximately $ per year.
Pagel of 3
SUMMARY
Amount % Change
Original Contract Price:
$14,527,295.00
Previous Quantity Adjustment(s):
This Quantity Adjustment:
$0.00`
Total Quantity Adjustment(s):
$0.00
Total Contract Price with Quantity Adjustment(s):
$14,527,295.00
Previous Change Order(s):
0.00
This Change Order:
$64,451.00 0.00
Total Change Order(s) To Date:
$64,451.00 0.00
Adjusted Contract Price [Original Contract Price Plus
Quantity Adjustment(s) Plus Change Order(s)]:
$14 591,746.00
Difference between Original and Adjusted Contract Prices:
$64,451.00
Original Contract Time:
3 -Dec -13
Time Adjustment by previous Quan. Adj./Change Order:
Time Adjustment by this Quan. Adj./Change Order:
New Contract Time:
3 -Dec -13
Submitted1b r Approval
/
Prepared By: � "�/ r�AL-�
Larry Madsen Construction Manager
1—(fev3
Signature
Printed Name, Title, Company
Date
Approvals
Contractor:
Charles J Glace Jr. Chasco Constructors
Signature
City Project
Printed Name, Title, Company
Date
Manager: �
Chad McDowell Director General Services
—//—/
Mayor/CityManagery
NJ
ure
Printed Name, Title
Date
n
Alan McGraw Mayor
Z •Z� •�3
nature
Printed Name, Title
Date
Contract Quantity Adjustment/Change Order
_ �ran_voktx�: �e.0
rei, 08/12
Project Name: Sports Center
Quan. Adj./Change Order No.:
Change Order Data
Page 2 of 3
Contract
Time
Adjustment
item # Item Description Unit Unit Price Amount
1 LED Lighting Gymnasium & Parking Lot i $64,451.00 $64,451.00
$0.00
0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
0.00
Change
Order
PROJECT:
(name, address)
Round Rock Sports Evmts Conler
2400 gdsholm Trol
Round Rode, TX
TO (CONTRACTOR):
(name, address)
Chasco Constructors
P.O. Box 1057
Round Rock, Texas 78680
The Contract is changed as follons:
Distribution to:
OWNER
ENGINEER
NX
CONTRACTOR
FIELD
CONSTRUCTION MANAGERL
Add and delete the follo%ving items as per the attached CHANGE LOG
Add LED Lighting Upgrades per Chasco CP -010
Not %slid unit siated by the Owner. Architect and Contractor.
SiManue of the Contractor indicates his agreement herewith, inclttdina anv adiustment in the Contract Sun or Contract Time
CHANGE ORDER NO: One(l)
DATE: 8 -Feb -13
PROJECT NO: 11154
CONTRACT DATE:
CONTRACTFOR:
$64,451
TOTAL: $64,451
The Original Contract Sum was $14,527,295
Net change by previously authorized Change Order.c S0
The Contract Sum prior to this Change Order mas $14,527,295
The Contract Sum will be increased by this Change Order $64,451
The new Contract Sum including this Change Order will be $14,591,746
The Date of Substantial Completion as of the date of this Change Order has been affected b)
Marmon Mok
ARCHITECT
Address: 700 North St. Marys, Ste 1600
San Antonio, TX 78205
By:
Shawn Bacon
DATE:
Chasco Constructors, Ltd., L.L.P.
CONTRACTOR
Address: P.O. Box 1057
Round Rock, Texas 786%80
By: `^^
Ct ar es J. Glace,
DATE: '�'' Ilb-
26 -Jan -12
General Construction
§ONSTRUCTORS
January 30, 2013
Marmon Mok Architecture
700 N. St. Mary's, Suite 1600
San Antonio, TX 78205
Attention: Shawn Bacon, AIA
Ref: City of Round Rock Sports Center — RFP for LED Lighting Upgrades
Shawn:
1? O. Box 1057
Round Rock, Texas 78680
(512)244-0600
1-855-441-4109
Fax: (512) 244-0489
111,111@chasco.com
chasco.com
Chasco Constructors has prepared pricing to change selected lighting fixtures from those originally
specified in the Construction Documents to LED fixtures. As per the LED Lighting Upgrade RFP dated
12-18, EL 102.1 -Revised and EL 102.2 Revised both dated 12-19-12 and all prepared by Hendrix
Consulting Engineers we hereby submit a cost of $64,451.00 for this change. The revised amount noted
below includes only the Gymnasium lighting and the parking lot lighting. We understand this change will
not be funded from the Owner's Betterment Allowance, but will be an addition to the Contract so the
below price reflects insurance, fees and bond. The revised breakdown of cost is as follows:
LED Lighting Substitutions
Gymnasium Lighting
$
27,400.00
Parking Lot Lighting
$ 29,750.00
Cost to Subcontractor
$
57,150.00
Subcontractor Fee and Bond Cost
$ 3.653.00
Total Cost from Subcontractor
$
60,803.00
OH, Fee, Insurance and Bonds - 6%
$
3,648.00
Total
$
64,451.00
If you have any question regarding our proposal enclosed herein please let me know,
Sincerely,
Chasco Constructors
l
Scott Badgett
Vice President — Building Estimating
®N AMERICAN SOCIETY OF �
C'ON'CRETE CONTRA( TORS �1
�+ HASCO
I.idHSTAUCTOAS
February 8, 2013
TO: City of Round Rock
212 Commerce Cove
Round Rock, TX 78664
ATT: Larry Madsen
RE: Round Rock Sports Center — Chasco Job No. 11154
CP -010 — LED Lighting Upgrades
P.O. Box 1057
Round Rock, TX 78680
(612) 244-0600
Fax (612) 244-0489
We hereby submit our Change Proposal for your consideration and approval to execute
a change to the contract for the above referenced project. For your review and per your
request, we have provided pricing for labor, equipment and material to make revisions
per Chasco Letter of January 30, 2013, see attached.
Changes per attached Chasco CP No. 010 Pricing Sheet dated February 8, 2013:
$64,451.00
If approved, this change will result in a change to the Contract Amount by the sum of
$64,451.00. Please indicate if we are to proceed with this work by February 28,
2013. If approved, this CP will be incorporated into the next Owner Change Order.
Respectfully,
APPROVED BY:
Date
CHASCO CONSTRUCTORS
1
Scott Badgett
Vice President — Building Estimating
cc: File: 107_02 001
Field
09M1ISSTIRIUCTOnS
Cheaco CP No: CP -010
Arch. PR No: N/A
Chance Propoaal Pricina Sheet
Rond Rack Sports Center
11154
Architect Project No: 11037
08 February 2013
Prepared by: Scott Sadgett
Description: Chane selected iiahtina fixtures from those oriainalN oeci8ed in the C 1Qn� cion D.,�uments to LED fixl nnn nn ner et,o t an
lighting L12grade RFP dated 12-18. EL 1021 -Revised and EL 102.2 Revised both dated 12-19-12 and all
COflsuNnO Eneers Tymnn
'm Itohts end the parkin lot liohtina
LABORTOTAL UNIT I TOTAL
NIT
UNIT I TOTALrA
$1,824
Sales Tex Materials (only)
0.000%
$0
SUBTOTAL
$82,627
Fee
1.250%
$783
SUBTOTAL
$83,410
Insurance
0.842%
S407
P&P Bond
1.000%
$834
DRANO TOTAL
$84,451
Further description:
Overhead
3.000%
$1,824
Sales Tex Materials (only)
0.000%
$0
SUBTOTAL
$82,627
Fee
1.250%
$783
SUBTOTAL
$83,410
Insurance
0.842%
S407
P&P Bond
1.000%
$834
DRANO TOTAL
$84,451
LEGAL DEPARTMENT APPROVAL FOR CITY COUNCIL/CITY MANAGER ACTION
Required for Submission of ALL City Council and City Manager Items
Department Name: General Services Project Name: Round Rock sports Complex
Project Mgr/Resource: Larry Madsen Contractor/Vendor: Chasco Constructors ^
a Council Action:
ORDINANCE
E] RESOLUTION
Agenda Wording
Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 1 with Chasco Constructors to
upgrade to LED lighting in the Gymnasium and Parking Lot for the Round Rock Sports Complex Project.
0city Manager Approval
LMA Wo
Attorney Approval
Attorney
Date4 1
2,
0:lwdox\SCClntsl0199171631MISC100268391.XLS Updated 6/3/08