Loading...
CM-2016-1079 - 4/15/2016Page I of 3 Contract Quantity Adjustment/Change Order ROl1N0 ROCK TEXAS rev, 01/16 Department: Utilities & Environmeental Services Project Name: Creekbend Blvd. Extension Project Date: 3/24/16 City Project Change Order/Quantity ID Number ST33CBDR Adjustment No. 3 Vendor CAPITAL EXCAVATION P.O. BOX 1301, AUSTIN, TX, 78767 512-440-1717 Company Name Address Phone No. Justification Restraints for existing waterlines to make tie-ins and allow water to be immediately returned to service. SUMMARY Original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Adjusted Contract Price [Original Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)]: Difference between Original and Adjusted Contract Prices: Original Contract Time: Time Adjustment by previous Quan. Adj./Change Order: Time Adjustment by this Quan. Adj./Change Order: New Contract Time: Submitted for Approval Amount % Change $8,089,168.50 $48,370.27 $0.00 $48,370.27' $8,137,538.77 $96,492.25 1% $32,091.20 0% $128,583.45 2% $8,266,122.22 $176,953.72 435 123 3 561 Prepared By: Logan Ginbey, Project Coordinator, Capital Excavation 4/1/16 ture Printed Name, Title, Company Date Approvals Contractor: ZLogan Ginbey, Project Coordinator, Capital Excavation 4/1/16 ignature / Printed Name, Title, Company Date City Project r� 4:5 1& Manager: /\. srqnhtLke Printed Name, Title Date Mayor/City// Manager L/LL�� Signature Printed Name, Title ' ✓ Date 040 Contract Quantity Adjustment/ Change Order ROUND ROCK IE -5 rev, 01/16 Project Name: Creekbend Blvd. Extension Project Quan. Adj./Change Order No Chance Order Data Pace 2 of 3 Item # Item Description Unit Qty. Unit Price Amount Contract Time Adjustment (Days) CO#3 Restrain Existing Water Lines LS 1 $32,091.20 $32,091.20 3 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTALS: $32,091.201 3 Contract Quantity Adjustment/ Change Order ROUNO ROCK TEXnS rev, 01/16 Project Name: Creekbend Blvd. Extension Project Quan. Adj./Change Order No Quantity Adiustment Data Page 3 of 3 Bid Item # Item Description Unit p Qty. Unit Price Amount Contract Time Adjustment $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTALS: 0.00 0 RESTRAIN EXISTING WATER LINES Capital Excavation Company PROJECT: CREEK BEND DATE: 3/21/2016 QUANTITY UNIT UNIT PRICE TOTALS Page 1 LABOR FOREMAN 25 HR $41.00 $1,025.00 LABOR 60 HR $13.00 $780.00 OPERATOR TRACKHOE/BACKHOE 60 HR $18.00 $1,080.00 OPERATOR WHEEL LOADER 31 HR $16.00 $496.00 PIPE LAYER 31 HR $15.00 $465.00 $3,846.00 MARK-UP @ 25% $961.50 SUBTOTAL: $4,807.50 BURDEN @ 55% $2,115.30 TOTAL LABOR $6,922.80 EQUIPMENT FOREMAN TRUCK 35 HR $12.35 $432.25 CAT 320 TRACKHOE 30 HR $40.00 $1,200.00 CAT 330 TRACKHOE 30 HR $61.00 $1,830.00 CAT 950 WHEEL LOADER 8 HR $45.00 $360.00 WATER TRUCK 2000 GAL 8 HR $15.00 $120.00 $3,942.25 MARK-UP @ 0% $0.00 TOTAL EQUIP $3,942.25 MATERIAL ACT 1 LS $16,980.92 $16,980.92 MARK-UP @ 25% $4,245.23 TOTAL MATL $21,226.15 SUB TOTAL TOTAL $32,091.20 $32,091.20 Page 1 U 0 a W W� (nN z i 0= uDD'u61 sa0•DN•9[x+i•0]\+114I�3�3311\00+]\W+B >t+o�7V+0l sa0%w�l\.tl 131I] Die .aaor� u ♦ ID •dad• I l o»S.Ov :Ohltl0 101d D 102/SI/S :3110 Q`a z 00 z N La >- oaY`d N z m o G IW— W a s Y X W W J o W LL] U > Qoo� .-L'v z� .� m co 0- uDD'u61 sa0•DN•9[x+i•0]\+114I�3�3311\00+]\W+B >t+o�7V+0l sa0%w�l\.tl 131I] Die .aaor� u ♦ ID •dad• I l o»S.Ov :Ohltl0 101d D 102/SI/S :3110 City of Round Rock IROUNO ROCK TEXAS Agenda Item Summary Agenda Number: Title: Consider executing Quantity Adjustment/Change Order No. 3 with Capital Excavation for the Creek Bend Boulevard Extension Project. Type: City Manager Item Governing Body: City Manager Approval Agenda Date: 4/15/2016 Dept Director: Michael Thane, Director of Utilities and Environmental Services Cost: Indexes: Attachments: CO-QANo.3_CapitalExcavation. pdf, LAF_QA-CONo.3_CapitalExcavation. pdf, CreekBend_Map.pdf Department: Utilities and Environmental Services Text of Legislative File CM -2016-1079 Consider executing Quantity Adjustment/Change Order No. 3 with Capital Excavation for the Creek Bend Boulevard Extension Project. The City is in construction of the Creek Bend Boulevard extension on the west side of Round Rock. This project will provide a new North/South road crossing of Brushy Creek, and greatly enhance mobility west of the IH -35 corridor, improving access for emergency services, the hospital, and Round Rock High School. The construction of water and wastewater improvements are necessary prior to the construction of the roadway improvements. In the course of construction, it became necessary to restrain the existing 16 -inch and 30 -inch waterlines that are owned by the City of Round Rock and the 24 -inch waterline belonging to Fern Bluff Municipal Utility District prior to the designed tie-ins. The total cost of this task was $32,091.20. The Utility staff recommends the City Manager execute Change Order/Quantity Adjustment No. 3 for the amount of $32,091.20, raising the amended Contract amount to $8,266,122.22. City of Round Rock Page 1 Printed on 411412016 Agenda Item Summary Continued (CM -2016-1079) Staff Recommends Approval. City of Round Rock Page 2 Printed on 411412016