R-06-02-09-10C2 - 2/9/2006RESOLUTION NO. R -06-02-09-10C2 WHEREAS, the City of Round Rock has previously entered into a contract ("Contract") with RGM Constructors, L.P. for the Forest Creek and Double Creek Drive, Phase 2 Project, and WHEREAS, the Council has determined that it is necessary to make changes to the quantity of work to be performed or materials, equipment, or supplies to be provided, and WHEREAS, it has been determined that it is necessary to change said Contract in accordance with the attached Contract Change Order No. 3, Now Therefore BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS, That the Mayor is hereby authorized and directed to execute on behalf of the City Contract Change Order No. 3 to the Contract with RGM Constructors, L.P., a copy of said change order being attached hereto as Exhibit "A" and incorporated herein for all purposes. The City Council hereby finds and declares that written notice of the date, hour, place and subject of the meeting at which this Resolution was adopted was posted and that such meeting was open to the public as required by law at all times during which this Resolution and the subject matter hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act, Chapter 551, Texas Government Code, as amended. RESOLVED this 9th day of February, 7j ATTES r. NY WEL , Ma; or City of Round Rock, Texas CHRISTINE R. MARTINEZ, City Secretary CPFDesktop\::ODMA/WORLDOX/O:/WDOX/RESOLtTTI/R60209C2.WPD/sc CITY OF ROUND ROCK CONSTRUCTION CHANGE ORDER Page 1 of 1 DEPARTMENT: Transportation Services DATE: 1/23/2006 PROJECT: Forest Creek Drive/Doublecreek Drive CHANGE ORDER NO: 3 JUSTIFICATION: Phase 2 ORIGINAL CONTRACT PRICE: PREVIOUS CHANGE ORDERS: THIS CHANGE ORDER: CHANGE ORDERS TO DATE: $3,598,223.40 $165,272.30 $67,992.90 $233,265.20 CHANGE DATA ITEM # DESCRIPTION OF CHANGES UNIT QTY. UNIT PRICE AMOUNT ADDED DAYS CALENDAR/ WORKING Add 585 linear feet of 2" PVC Sch. 40 Conduit, complete per specifications for C3A1 $7.10/LF LF 585 $7.10 $4,153.50 Add one (1) each Concrete Valley Gutter including curb from PC to PT, complete per specifications for C3A2 $2,200.00 EA EA 1 $2,200.00 $2,200.00 Add one (1) lump sum for Temporary Traffic Control & Temporary Pavement Markings, inlcuding installation and C3A3 removal, complete per specifications LS 1 $33,529.34 $33,529.34 Add one (1) lump sum to remove and relocate existing street lights and median curb as requested by Public Works Dept, complete per C3A4 specifications LS 1 $11,261.00 $11,261.00 Add 512 linear feet of Dry Stack Rock Wall including concrete, rock and C3A5 mortar, complete per specifications LF 512 $32.00 $16,384.00 Add one (1) lump sum to reconstruct Concrete Driveways in Double Creek C3A6 Drive complete per specifications LS 1 $17,176.06 $17,176.06 Add one (1) lump sum to adjust existing utilities to the proposed finished grade, complete per C3A7 specifications LS 1 $3,012.00 $3,012.00 Add one (1) lump sum for additional traffic control rental, complete per C3A8 specifications LS 1 $4,000.00 $4,000.00 Add one (1) lump sum to replace the median, relocate light pole at Double Creek Farms, complete per C3A9 specifications LS 1 $5,977.00 $5,977.00 Delete one (1) each reinforced concrete residential driveway (15' C3D1 width) complete per specifications EA 1 ($2,500.00) ($2,500.00) Delete one (1) lump sum to install waterline improvements complete per C3D2 specifications EA 1 ($27,200.00) ($27,200.00) TOTAL: $67,992.90 0 SIGNATURE (ENGINEER 0'1/2- 41 I I 1 SIG PIATURE (CONTR4COR) PRINTED NAME TITLE: rc). 1-wfa DATE iDATE APPROVED: CITY OF ROUND ROCK PERCENT OF ORIGINAL CONTRACT PRICE THIS CHANGE ORDER: PREVIOUS CHANGE ORDER: 4.59% TOTAL % CHANGE: 6A8% ORIGINAL CONTRACT PRICE PLUS CHANGE ORDERS: $3,831,488.60 1.89% DATE constco2/forms6Ak .o 9 EXHIBIT 0 0 0 a) ci3 a) 0 1) a) 1. 0 a) 0 a) ..o DATE: February 2, 2006 SUBJECT: City Council Meeting - February 9, 2006 ITEM: *10.C.2. Consider a resolution authorizing the Mayor to execute Change Order No. 3 with RGM Constructors, L.P. for the construction of Forest Creek Drive and Double Creek Drive, Phase 2. Department: Transportation Services Staff Person: Thomas G. Martin, P. E., Director Justification: This Change Order will provide monies for the connection of two roadways to Forest Creek Drive, which were constructed prior to the award of bid for this project. The two roads are Rusk Road West and Paradise Ridge which required installation of additional utility and drainage improvements, installation of waterline, storm sewer improvements and paving. Funding: Cost: $ 67, 992.90 Source of funds: 4B Corporation (1/2 cent Sales Tax) & Private Developers Outside Resources: RGM Constructors, L.P. Background Information: This project was awarded by the City Council on August 26, 2004 as R -04-08-26-13E4 in the amount of $ $3,598,273.40. Completion of the arterials Forest Creek Drive and Doublecreek Drive will provide a four lane divided roadway, with curb and gutter section and is in accordance with the City's Master Transportation Plan. Public Comment: N/A CITY OF ROUND ROCK CONSTRUCTION CHANGE ORDER DEPARTMENT: Transportation Services PROJECT: Forest Creek Drive/Doublecreek Drive Phase 2 ORIGINAL CONTRACT PRICE: PREVIOUS CHANGE ORDERS: THIS CHANGE ORDER: CHANGE ORDERS TO DATE: $3,598,223.40 $165,272.30 $67,992.90 $233,265.20 CHANGE DATA Page 1 of 1 DATE: 1/23/2006 CHANGE ORDER NO: 3 JUSTIFICATION: ITEM # DESCRIPTION OF CHANGES UNIT QTY. UNIT PRICE AMOUNT ADDED DAYS CALENDAR! WORKING Add 585 linear feet of 2" PVC Sch. 40 Conduit, complete per specifications for C3A1 $7.10/LF LF 585 $7.10 $4,153.50 Add one (1) each Concrete Valley Gutter including curb from PC to PT, complete per specifications for C3A2 $2,200.00 EA EA 1 $2,200.00 $2,200.00 Add one (1) lump sum for Temporary Traffic Control & Temporary Pavement Markings, inlcuding installation and C3A3 removal, complete per specifications LS 1 $33,529.34 $33,529.34 Add one (1) lump sum to remove and relocate existing street lights and median curb as requested by Public Works Dept, complete per C3A4 specifications LS 1 $11,261.00 $11,261.00 Add 512 linear feet of Dry Stack Rock Wall including concrete, rock and C3A5 mortar, complete per specifications LF 512 $32.00 $16,384.00 Add one (1) lump sum to reconstruct Concrete Driveways in Double Creek C3A6 Drive complete per specifications LS 1 $17,176.06 $17,176.06 Add one (1) lump sum to adjust existing utilities to the proposed finished grade, complete per C3A7 specifications LS 1 $3,012.00 $3,012.00 Add one (1) lump sum for additional traffic control rental, complete per C3A8 specifications LS 1 $4,000.00 $4,000.00 Add one (1) lump sum to replace the median, relocate light pole at Double Creek Farms, complete per C3A9 specifications LS 1 $5,977.00 $5,977.00 Delete one (1) each reinforced concrete residential driveway (15' C3D1 width) complete per specifications EA 1 ($2,500.00) ($2,500.00) Delete one (1) lump sum to install waterline improvements complete per C3D2 specifications EA 1 ($27,200.00) ($27,200.00) TOTAL: $67,992.90 0 PREPARED BY: SI ATURE (E GI ) 14 SIGNATU E (CONT TOR) PRINTED NAME Pikt11. r� TITLE: APPROVED. CITY OF2' • DATE Z.4/0(.. /DATE PERCENT OF ORIGINAL CONTRACT PRICE THIS CHANGE ORDER: 1.89% PREVIOUS CHANGE ORDER: 4.59% TOTAL % CHANGE: 6.48% ORIGINAL CONTRACT PRICE PLUS CHANGE ORDERS: $3,831,488.60 -oma R-44,-04-09 Wel.) DATE constco2Jforms6/Ik