R-06-02-23-10C4 - 2/23/2006RESOLUTION NO. R -06-02-23-10C4 WHEREAS, the City of Round Rock has previously entered into a contract ("Contract") with F.T. Woods Construction Services, Inc. for the construction of the East Water Transmission Line, Phase 3A-2, and WHEREAS, the Council has determined that it is necessary to make changes to the quantity of work to be performed or materials, equipment, or supplies to be provided, and WHEREAS, it has been determined that it is necessary to change said Contract in accordance with the attached Contract Change Order No. 1, Now Therefore BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS, That the Mayor is hereby authorized and directed to execute on behalf of the City Contract Change Order No. 1 to the Contract with F.T. Woods Construction Services, Inc. for the construction of the East Water Transmission Line, Phase 3A-2, a copy of said change order being attached hereto as Exhibit "A" and incorporated herein for all purposes. The City Council hereby finds and declares that written notice of the date, hour, place and subject of the meeting at which this Resolution was adopted was posted and that such meeting was open to the public as required by law at all times during which this Resolution and the subject matter hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act, Chapter 551, Texas Government Code, as amended. RESOLVED this 23rd day of February, 2006. @PFDesktop\::ODMA/WORLDOX/0:/WDOX/RESOLUTI/R60223C4.WPD/rmc Y , Mayor City of Round Rock, Texas CHRISTINE R. MARTINEZ, City Secret 2 Y .o EXHIBIT nAn Project Name: East Water Transmission Line, Phase 3A-2 Project Owner: City of Round Rock 212 Commerce Cove, Round Rock, TX 78664 Change Order No. 1 HDR Project No.: 07225-16810 Project Contractor: FT Woods Construction Services 1966 S. Austin Ave., Georgetown, TX 78626 Date of Issuance: January 20, 2006 Date of Contract: June 06, 2005 Date of Notice to Proceed: August 22, 2005 Original Completion Date: March 20, 2006 Contract Period: 210 Calendar Days It is agreed to modify the Contract referred to above as follows• CPR # ITEM AND DESCRIPTION OF CHANGES COCHANGE IN NTRACT PRICE CHANGE IN CONTRACT TIME 1 Lower 36 IN line $ 29,100.00 5 2 Landscaping, sidewalks, deduct 11.25 degree bend, add two 45 degree bends $ 26 328.91 5 Difference Net $ 55,428.91 10 Summary: It is agreed to modify the Contract referred to above as follows: Contract Price prior to this Change Order Contract Time prior to this Change Order $ 723,388.00 Net Increase (decrease) of this Change Order $ 55,428.91 Revised Contract Price with all approved Change Orders $ 778,816.91 210 days — March 20, 2006 Net Increase (decrease) of this Change Order 10 Revised Contract Time with all approved Change Orders 220 days - March 30, 2006 The changes included in this Change Order are to be accomplished in accordance with the terms, stipulations and conditions of the original Contract as though included therein. Accepted for C/ntractor by: L- 1 Recommended for Approbal by (HDR Engineering, Inc.): Approved for Owner by: Approved: (Other - when required) Attest: Date: (Z41/0/, Date: / Y -e Date: Date: Distribution: EKOwner [Contractor D Office 0 Field 0 Other f d s�n t� .°t .�� +� 'k�r�`���' ��' �,�.a�,-.� 1 � �� � nl� y, �i�'k�� f�`��. w y�y 'S�,b:•d *'t,`x^34 (� a;s„` +�' ''.:.".�" f4. n>�gvi � .. .� � (,.. +�<a nt �' zz �R # N � ��- a �,�,� Awa,....�� ' �•p. k �x Union Pacific Rail Road di l z F � kyi R ��?'yy`m''"°'� a"$ Rap '� , �,�}�r �.,,� � -" �� �.a�,�,�. �� , �� �� �s 123 g w , East Waterline 1 sf b Phase 3-A I J s .,,,•.a :� s ,4 qF ��•d � ^.�C a �a t!P °�h� �y5; :aC�f 4 r� a4,a�yJs E.,y. ��- & � a '+� f.��` �.� �iI�+�5 `�' y�... � �• g 4 r"A R'�.yy. -'j ' ) � N i�'« t $ ,� 4 'ar rr; S 1 - T-�•�k!H 'kms^-�y�9 Itl1, f1'•, r' .y w E NOT To SCALE EAST" I TETRA, . M/�`ISSION LINE — AS 4�m /A ROUND RACK,TEXAS ��"» /g'V� � PUPPoIC P\SIGN PNOSPERIiY S:iGraphics=UNCI^14ENGINE^112OMWATERU-IIE TRNS,2.MXD DATE: February 16, 2006 SUBJECT: City Council Meeting - February 23, 2006 ITEM: *10.C.4. Consider a resolution authorizing the Mayor to execute Change Order No. 1 with F.T. Woods Construction Services, Inc. for the construction of the East Water Transmission Line, Phase 3A-2. Department: Water and Wastewater Utilities Staff Person: Tom Clark, Director Justification: This Change Order is to lower the water line at the intersection of Highway 79 and Redbud Lane to avoid the foundation of traffic signal poles. Funding: Cost: $55,428.91 Source of funds: Capital Project Funds (Self -Financed Utility) Outside Resources: F.T. Woods Construction Services, Inc. Background Information: Change Order Number One is for additional costs associated with boring and installing the 36" water line under US 79 four feet lower than originally bid. This was required to avoid the foundation of existing and future locations of the foundations for the traffic light poles at the intersection of US 79 and Red Bud Lane. This change order includes additional costs to the contractor due to necessary adjustments to the PRV vault location, alignment of the 36" water line around a lending power pole and costs associated with removal and replacement of sidewalk, drainage structure and landscaping that was installed by a developer after the project was awarded. Public Comment: N/A Change Order No. 1 Project Name: East Water Transmission Line, Phase 3A-2 HDR Project No.: 07225-16810 Project Owner: City of Round Rock 212 Commerce Cove, Round Rock, TX 78664 Date of Issuance: January 20, 2006 Project Contractor: FT Woods Construction Services 1966 S. Austin Ave., Georgetown, TX 78626 Date of Contract: June 06, 2005 Date of Notice to Proceed: August 22, 2005 Original Completion Date: March 20, 2006 Contract Period: 210 Calendar Days It is agreed to modify the Contract referred to above as follows: CPR # ITEM AND DESCRIPTION OF CHANGES CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME 1 Lower 36 IN line $ 29,100.00 5 2 Landscaping, sidewalks, deduct 11.25 degree bend, add two 45 degree bends $ 26,328.91 5 Difference Net $ 55,428.91 10 Summary: It is agreed to modify the Contract referred to above as follows: Contract Price prior to this Change Order Contract Time prior to this Change Order $ 723,388.00 Net Increase (decrease) of this Change Order $ 55,428.91 Revised Contract Price with all approved Change Orders $ 778,816.91 210 days - March 20, 2006 Net Increase (decrease) of this Change Order 10 Revised Contract Time with all approved Change Orders 220 days - March 30, 2006 The changes included in this Change Order are to be accomplished in accordance with the terms, stipulations and conditions of the original Contract as though included therein. Accepted for ntractor by: Recommended for Approtial by (HDR Engineering, Inc.): rr e Approved fo Date: (Z(//c42 Date: f z4,r' Appr. -d: �� er - when quired) Distribution: Owner E Contractor 2 -04 -OR iocA 0 Office ❑ Field 0 Other