R-06-11-09-11C3 - 11/9/2006RESOLUTION NO. R -06-11-09-11C3
WHEREAS, the City of Round Rock has previously entered into an
Agreement for Engineering Services ("Agreement") with HDR Engineering,
Inc. for Red Bud Lane (CR 122) from US 79 to CR 123, and
WHEREAS, HDR Engineering, Inc. has submitted Supplemental
Agreement No. 5 to the Agreement to modify the provisions for the scope
of services, and
WHEREAS, the City Council desires to enter into said Supplemental
Agreement No. 5 with HDR Engineering, Inc., Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS,
That the Mayor is hereby authorized and directed to execute on
behalf of the City Supplemental Agreement No. 5 to the Agreement with
HDR Engineering, Inc., a copy of same being attached hereto as Exhibit
"A" and incorporated herein for all purposes.
The City Council hereby finds and declares that written notice of
the date, hour, place and subject of the meeting at which this
Resolution was adopted was posted and that such meeting was open to the
public as required by law at all times during which this Resolution and
the subject matter hereof were discussed, considered and formally acted
upon, all as required by the Open Meetings Act, Chapter 551, Texas
Government Code, as amended.
RESOLVED this 9th day of November, 4J06
EST;
RMT
NY ayor
ity of Ro d Rock, Texas
CHRISTINE R. MARTINEZ, City
0:\wdox\RESOLUTI\R61109C3.WPD/rmc
cretary
STATE OF TEXAS
COUNTY OF WILLIAMSON
SUPPLEMENTAL AGREEMENT NO. 5
TO AGREEMENT FOR ENGINEERING SERVICES
FIRM: HDR Engineering, Inc. ("Engineer")
ADDRESS: 4401 Westgate Blvd., Austin, TX 78745
PROJECT: Red Bud Lane (CR 122) from US 79 to CR 123
This Supplemental Agreement No. 5 to Agreement for Engineering Services is made by and
between the City of Round Rock, Texas, hereinafter called the "City" and HDR Engineering,
Inc., hereinafter called the "Engineer".
WHEREAS, the City and Engineer executed an Agreement for Engineering Services,
hereinafter called the "Agreement", on the 22nd day of January, 2004 for Red Bud Lane (CR
122) from US 79 to CR 123, for the sum of $249,363.00; and
WHEREAS, on the 14th day of October, 2004, the City and Engineer executed Supplemental
Agreement No. 1 to amend the Agreement to modify the provisions for the scope of services, to
increase the compensation by $41,255.00 to a total of $290,618.00, and to modify the provision
for notices to proceed; and
WHEREAS, on the 13th day of January, 2005, the City and Engineer executed Supplemental
Agreement No. 2 to amend the Agreement to modify the provisions for the scope of services, to
increase the compensation by $21,872.00 to a total of $312,490.00; and
WHEREAS, on the 9th day of June, 2005, the City and Engineer executed Supplemental
Agreement No. 3 to amend the Agreement to modify the provisions for the scope of services and
to increase the compensation by $7,242.00 to a total of $319,732.00; and
WHEREAS, on the 1st day of December, 2005, the City and Engineer executed Supplemental
Agreement No. 4 to amend the Agreement to modify the provisions for the scope of services and
to increase the compensation by $23,643.00 to a total of $343,375.00; and
WHEREAS, it has become necessary to amend the Agreement to modify the provisions for the
scope of services and to increase the compensation by $215,370.00 to a total of $558,745.00; and
NOW THEREFORE, premises considered, the City and the Engineer agree that said
Agreement is amended as follows:
Supplemental Agreement
Hdr-redbud3; STO2REDBD; 105722
EXHIBIT
2
Rev.03/02/04
64836
I.
Article 2, Scope Of Services To Be Performed By Engineer and Exhibit B, Services To Be
Performed By The Engineer shall be amended as set forth in the attached Addendum To Exhibit
B.
II.
Article 4, Compensation and Exhibit D, Fee Schedule shall be amended by increasing by
$215,370.00 the lump sum amount payable under the Agreement for a total of $558,745.00, as
shown by the attached Addendum to Exhibit D.
IN WITNESS WHEREOF, the City and the Engineer have executed this Supplemental
Agreement in duplicate.
HDR ENGINEERING, INC.
By:
/0-25-0G
Date
CITY OF ROUND ROCK
By:
Nyle Maxwell, Mayor
Date
Supplemental Agreement
Hdr-redbud3; STO2REDBD; 105722
2
VED AS Tb FORM:
.�'
L. Sheets, City Attorney
Rev.03/02/04
64836
ADDENDUM TO EXHIBIT B
Services to be Provided by the Engineer
The changes to the scope of this project are as follows:
EXHIBIT B — SCOPE OF SERVICES
TASK 3 - SCHEDULING SERVICES
SCOPE STATEMENT AND OBJECTIVE
This Scope of Services is for HDR Engineering, Inc. ("HDR") to provide engineering and
construction contract administration services ("Services") to the Owner ("OWNER") related to the
Projects ("Projects").
SCOPE OF SERVICES
HDR will assist OWNER with ongoing Project implementation by conducting the following tasks:
TASK SERIES 2200 - SCHEDULE ADMINISTRATION
Objective: Obtain, through the Contractor, a detailed construction schedule that
meets the Contract Document requirements and is useful for monitoring
construction progress throughout the Project.
HDR Activities: 2205 - Review and Approval of Initial Construction Schedule
• Review schedule for major elements of the Project and for
conformance to any specified schedule sequences and completion
dates.
• Notify Contractor with acceptance or rejection noting deficiencies
and requesting correction of them and re -submittal.
• Meet with OWNER and Contractor to reconcile disputed schedule
deficiencies and document reconciliation of disputed deficiencies.
2215 - Review Actual Construction Against Schedule Status
• Identify critical path activities that have not reached scheduled
milestones.
• Identify critical path activities whose durations have not expired that
are obviously realizing lower productivity rates than reflected in the
schedule.
• Identify non-critical activities whose durations are about to equal or
exceed the remaining float along that path.
• Identify critical path activities that are scheduled to start but have not
been started.
• Notify Contractor in writing of schedule deficiencies and request a
corrective action plan and revised schedule indicating the means of
regaining schedule losses.
Task Deliverables: • Written rejection or acceptance of Initial schedule.
• Monthly construction progress reports for first 2 months of
Construction
• Written notification of schedule deficiencies.
For information submitted to OWNER, three (3) hard copies will be
provided.
Key Understandings
and Assumptions: • HDR is not responsible for the detailed planning, sequencing and
scheduling of the construction.
Information and
Services Provided
by Others:
EXHIBIT B — SCOPE OF SERVICES
• HDR is not responsible for the Contractor's failure to execute the
approved schedule.
• Timely input on schedule modifications and adjustments by
OWNER throughout the contract period.
EXHIBIT B — SCOPE OF SERVICES
TASK 4 - CONSTRUCTION ADMINISTRATION AND
MANAGEMENT
SCOPE STATEMENT AND OBJECTIVE
This Scope of Services is for HDR Engineering, Inc. ("HDR") to provide engineering and
construction contract administration services ("Services") to the Owner ("OWNER") related to the
Projects ("Projects").
• HDR's fee schedule is based on a construction duration of 30 weeks as specified
in the construction documents. Construction durations in excess of this time will
require a supplemental agreement for the extra time required for field
observation.
• HDR's fee schedule is based on a field representative in the field an average of
40 hours per week as required by actual construction times and operations and a
Senior Construction Engineer an average of 8 hours per week for the duration of
the 30 week construction schedule. Construction observation services in excess
of this time will require a supplemental agreement for the extra time required for
field observation.
SCOPE OF SERVICES
HDR will assist OWNER with ongoing Project implementation by conducting the following tasks:
TASK SERIES 100 - PROJECT MANAGEMENT
Objective: Provide management activities over Project duration including planning,
organizing and monitoring Project team activities.
HDR Activities: 110 - Team Management and Project Control
• Resource management and allocation based on Project schedules
and activities.
• Budget and invoice management.
Meetings/Travel: • Local travel.
Key Understandings
and Assumptions:
• HDR's Project Manager will be responsible for coordinating
management activities.
• A Project kickoff meeting will be held to introduce OWNER and HDR
staff, outline Project goals, overall timetable and communicate
Project vision.
• OWNER will consolidate all comments on the Project Guide and
present them for discussion and resolution at a single meeting with
HDR representatives.
• An average of 1 meeting per month is assumed. Construction phase
meetings are not addressed under this Task Series.
• Quality audits are assumed to be conducted on a three-month (3)
basis.
• For the purpose of this Scope of Services, local travel is defined as
travel in the Round Rock and Project site areas.
Information and
Services Provided
by Others:
TASK SERIES 2000 -
Objective:
HDR Activities:
Meetings/Travel:
Task Deliverables:
Key Understandings
and Assumptions:
EXHIBIT B — SCOPE OF SERVICES
• HDR will produce and distribute meeting minutes for the meetings
defined in this Task Series.
• OWNER personnel will review required standards with HDR as a
preliminary activity to development of the Project Guide and provide
HDR with comments for final Guide development.
• OWNER to provide all available technical standards information and
response to questions posed by HDR in a timely manner.
• OWNER will endeavor to provide a minimum of 48 hours prior notice
for meetings identified in this Task Series.
MEETING ADMINISTRATION
Conduct and document construction phase meetings in order to facilitate
effective Project communications.
2005 - Preconstruction Conference
• Identify with OWNER and Contractor the parties to be included in the
meeting.
• Notify all parties as to the time and place of the meeting. Provide
preliminary agenda for attendee input.
• Prepare final meeting agenda and produce copies for all expected
participants for distribution at meeting.
• Prepare meeting place and provide for meeting documentation.
• Incorporate meeting discussions in final preconstruction meeting
minutes.
• Distribute meeting minutes to all persons in attendance and to
parties on meeting notice list not in attendance.
2010 — Weekly Construction Meetings
• Provide standard formats for meeting agenda, notes and attendance
rosters to promote consistent identification of meeting notes for filing
and cross referencing purposes.
• Establish date, place and agenda for regular construction meetings.
• Determine who is to be involved and notify them of schedule.
• Prepare agenda and distribute copies to those in attendance.
• Conduct meetings and document discussions.
• Distribute meeting minutes to all in attendance, and predetermined
attendees not in attendance, within one week of meeting.
• Local travel.
• Preconstruction Conference Meeting notification including agenda
items.
• Preconstruction Conference Meeting Minutes.
• Construction Meeting notification including agenda items.
• Minutes of each Construction Meeting.
• HDR will use its standard Construction Contract Administration forms
for conducting and documenting construction phase meetings.
Information and
Services Provided
by Others:
EXHIBIT B — SCOPE OF SERVICES
• One (1) Preconstruction Conference will be held per construction
contract.
• One (1) Construction Meeting each week.
• Preconstruction Conference to be held in meeting room provided by
the Owner. Construction Meetings to be held either in meeting room
provided by the Owner or in Contractor provided Construction Field
Office facility.
• OWNER will provide appropriate representation at all Construction
Meetings.
EXHIBIT B — SCOPE OF SERVICES
TASK SERIES 2100 - SUBMITTALS ADMINISTRATION
Objective: Provide administrative and technical support for the administration,
review and approval of Contractor's submittals to determine Contractor's
understanding of material and equipment requirements.
HDR Activities: 2105 - Review and Approval of Shop Drawing Submittal Schedule
• Review Shop Drawing Submittal Schedule.
• Notify Contractor of acceptance or rejection noting deficiencies and
requesting correction of them and resubmittal.
• Distribute copies of approved schedule to design team members
responsible for Shop Drawing reviews.
2110 - General Administration of Submittals
• Receive, log and distribute submittals received from Contractor to
design team for review.
• Provide timely review and re -distribution of Shop Drawings,
miscellaneous submittals, operation and maintenance manuals and
other submittal information.
• Establish organized storage for samples and a tracking log for
samples.
2115 - Review of Shop Drawing Status and Scheduling
• Review weekly the approved submitted schedule and the actual
Shop Drawing Log for comparison.
• Review Shop Drawing Submittal Log in regard to requirements that
all Shop Drawings must be submitted and approved prior to percent
completion defined in Contract Documents
• Utilize Shop Drawings Submittal Schedule as a checklist item for
application for payment.
• Notify Contractor of deficiencies.
• Address general status of Shop Drawings at Construction Meetings.
• Address Contractor's requests for Shop Drawing review of critical
equipment and materials prior to his having an approved submittal
schedule.
2125 - Evaluate Requests for Substitution
• Assist Owner with the review of substitution requests in terms of
quality, cost, constructability and secondary Project impact.
• Assist OWNER in negotiating any cost or time considerations,
additive or deductive, associated with a product substitution.
• Should there be more than ten (10) requests for substitution,
evaluate and process those substitution requests in accordance with
the Additional Service Clause of the agreement.
Meetings/Travel: • Local travel.
Task Deliverables:
• Action letter to Contractor on Schedule Acceptance or Rejection.
• Scheduling Notification to Design Team Shop Drawing Reviewers.
• Review comments on submittals with defined action.
• Weekly Shop Drawing Status Log (Shop Drawings with Contractor).
• Weekly Shop Drawing Status Log (Shop Drawings with HDR).
• Written notification of Shop Drawing Schedule deficiencies.
• Written response to Contractor's special requests for submittal
Key Understandings
and Assumptions:
Information and
Services Provided
by Others:
TASK SERIES 2300 -
Objective:
HDR Activities:
EXHIBIT B — SCOPE OF SERVICES
processing.
• Written approval or rejection of substitution requests.
For information submitted to OWNER, three (3) hard copies will be
provided.
• A maximum of 20 hours total is scoped for review of ten (10)
requests for substitution that may be made by the Contractor.
• It is assumed that the cost of reviewing Contractor's initial Shop
Drawing submittals and one resubmittal are included in this scope.
The review costs associated with any subsequent resubmittals will
be paid for by the Contractor.
• Detailed review of submittals/shop drawings for agreement or
conformance with design and specification details is outside of the
scope of this proposal. Detailed review should be provided by
designer(s).
None.
CONSTRUCTION OBSERVATION
Observe, record and report the Contractor's work progress to determine
the work is in general conformance with the requirements of the Contract
Documents. Document activity observed making note of deficiencies
and any issues requiring resolution.
2302 - General Construction Observation
• Obtain and file daily Contractor summary sheets defining specified
work completed and Contractor work force figures.
• Monitor construction activity to verify conformance with Contract
Documents and document activities and observations.
• Record weather condition information.
• Record Requests for Interpretation of Contract Document's
provisions.
• Note construction deficiencies and punch list items.
• Generate photographic or video documentation. (See Task 2324).
2304 - Site Conditions Review
• Periodically review overall condition of site for excessive construction
debris or erosion, and proper drainage and access
• Periodically review protection provisions for existing structures,
piping, trees and other items designated to be protected.
• Document deficiencies and notify the Contractor.
2306 - Structural Subgrade Review
• Review work and coordinate soil engineer and/or testing lab visits for
subgrade verification.
• Review work to verify no foundations or structural slabs on grade are
recommended for payment if concrete placement is made without
written soils lab approval of subgrade condition.
2308 - Coordinate and Review Soils Testing
EXHIBIT B — SCOPE OF SERVICES
• Establish communication of test result procedures and protocols with
testing service and Contractor.
• Review all test results submitted to verify compliance with specified
requirements and maintain Project Log.
• Verify areas of failing compaction are corrected to specified criteria.
• Review soils testing lab invoice to avoid OWNER being charged for
failing tests. Issue payment recommendations to OWNER.
2310 - Coordinate and Review Concrete Testing
• Review concrete mix design with the Structural Engineer and
Contractor to establish specification compliance relative to addition
of water to concrete on site.
• Monitor sampling program to verify correct number of cylinders are
taken as called for in the specifications.
• Review field data to verify other items such as slump, air entrainment
and special admixtures are in accordance with the Contract
Documents.
• Review each failing compressive strength test to determine structural
implications and course of corrective action required.
• Notify Contractor of subsequent testing which is required.
2314 - Stored MaterialslEquipment Review
• Coordinate with Contractor to facilitate review of major items prior to
unloading and storage.
• Regularly review Contractor's storage areas to determine compliance
with the Contract Documents.
• Notify the Contractor of any damaged or improperly stored materials.
• Adjust payments properly for damaged or improperly stored
equipment.
2322 - Design Discipline Site Visitations
• Coordinate and conduct design discipline site and other visitations.
• Follow-up of any site deficiencies noted by design team members.
• In the event of visitation by regulatory officials, follow up with
telephone contact to get their impressions and comments.
• For special visitations, arrange that proper persons representing the
various interested parties are present.
2324 - Coordinate Project Photo and Video Documentation
• Develop and maintain a logging system to enable easy retrieval of
visual information.
• Video or photo document construction activities as deemed
appropriate.
2328 - Record Drawing Review
• Review monthly status of as -recorded drawings. Refer to Field
Order and CPR Logs to identify areas of construction revision.
• Notify Contractor in a timely fashion of noted deficiencies.
• Provide follow-up to verify Contractor brings as -recorded drawing
status up-to-date.
• Continually note items as they are noticed during regular field
observation duties for inclusion on monthly as -recorded updates.
• Report general status at Project meetings.
MeetingslTravel:
EXHIBIT B — SCOPE OF SERVICES
2330 - Develop a Progressive List of Items Requiring Correction
• Monitor construction throughout the Project duration and identify
deficient items.
• Provide Contractor with an updated list at monthly construction
meetings.
• As deficiencies are corrected, revise the list by deleting corrected
items.
• Distribute the deficiencies list updates to authorized parties.
• Utilize list to aid in identifying retainage amounts near Project
completion.
2340 - OWNER Notification of Accident Damage/Injury
• Maintain communications with Contractor's superintendent to
encourage prompt notification of accidents.
• Require lost -time accident reports at construction meetings.
• Upon observation or notification of an accident, take photographs
and/or videotape of accident scene, make written notes and notify
OWNER and HDR Project Manager.
• Local travel.
Task Deliverables: • Daily Field Report.
• Monthly Construction Progress Report.
• Notice of Non -Compliance Reports
• Monthly Project Status Report.
• Distribution protocol for testing service.
• Written recommendation for soils testing payment.
• Written notification of out -of -specification concrete and need for
subsequent testing or corrective action.
• Written notification of damaged or improperly stored materials with
adjustment to payment.
• Documentation of site visitation in Project Log. Field reports
documenting results of field visitation.
• Photo/video documentation of construction activities accessible
without an organized retrieval system.
• Written notification of deficiencies in Record Drawings.
• Monthly punch list of work.
• Documentation of accident damage/injury.
• Certificate of Substantial Completion.
For information submitted to OWNER, three (3) hard copies will be
provided.
Key Understandings
and Assumptions:
• HDR will use its standard Construction Contract Administration forms
for documenting construction observation and observation activities.
• HDR's fee schedule is based on an assumed construction duration
of 30 weeks. Construction durations in excess of this time will require
a supplemental agreement for the extra time required for field
observation.
• HDR's fee schedule is based on a field representative in the field an
average of 40 hours per week as required by actual construction
times and operations and a Construction Engineer an average of 8
Information and
Services Provided
by Others:
TASK SERIES 2400
ADMINISTRATION
Objective:
HDR Activities:
EXHIBIT B — SCOPE OF SERVICES
hours per week for the duration of the 30 week construction
schedule. Construction observations services in excess of this time
will require a supplemental agreement for the extra time required for
field observation.
• HDR will not supervise, direct or control Contractor's forces.
• HDR's construction observation will not be exhaustive and is not
intended to be sufficient enough to prevent Contractors from failing
to perform work in accordance with contract requirements. HDR will
act to have defective work corrected by the Contractors when HDR is
aware defective work exists.
• HDR will manage a maximum of 1 construction observers to provide
construction observation at the site of the Work, and will not be
required to assign personnel to this Task to the extent that a
construction observer is present on site at all times a Contractor is
working.
• HDR will not provide equipment for or conduct the testing of soils
and soils compaction, concrete sampling and testing or other
construction materials sampling and testing.
• OWNER to provide any special protocol to be used when non -
construction related personnel visit the site.
- CONTRACT INTERPRETATIONS AND MODIFICATIONS
Provide timely reviews and responses to Contractor requests for
interpretations or information and proposed modifications identified by
the Contractors, OWNER or HDR design and construction observation
team.
2405 - Coordinate Interpretations Review
• Receive, log and distribute Requests for Information (RFI) to
appropriate design team members for response.
• Review and respond to RFI's.
• Receive design team responses, log and distribute to Contractor.
• Prepare and issue response letters, Field Orders (FO's) or Change
Proposal Requests (CPR's) as required.
2410 - Administration of Changed Work.
• Initiate necessary changes in the form of CPR's.
• Review costs presented on CPR's by Contractor. Assist OWNER
with negotiation of final pricing as required.
• Review all CPR items and negotiated costs with OWNER for
OWNER's approval.
• Assemble approved CPR's periodically into Change Orders (CO's).
Include justification documents with each CO.
• Track CPR's and CO's through Contractor's acceptance, OWNER's
acceptance, Engineer's signature and OWNER executive action.
• Maintain current status log of all CPR's and CO's.
• For minor changes involving no cost and no time changes, issue
FO's.
• Review as -recorded drawings to verify changes in work are reflected
as applicable.
EXHIBIT B — SCOPE OF SERVICES
• Review pay requests to verify CO items are broken out and that
payment is not made until work is complete.
2415 - Coordinate and Issue Field Orders (FO's)
• Prepare technical description of the FO.
• Route FO through established clearinghouse for numbering, logging
and issuance to the Contractor.
• Obtain a copy, executed by the Contractor, and route copies to the
appropriate Project files.
2420 - Coordinate and issue Change Proposal Requests (CPR's)
• Collect technical information and evaluate proposed change.
Prepare technical description of the CPR using necessary graphic
details and specifications.
• Prepare Engineer's Opinion of Cost and evaluation of impact on
Contract Time.
• Route the CPR through established clearinghouse for numbering,
logging and issuance to the Contractor for pricing.
• Route copies to the appropriate Project files.
• Follow and report the status of CPR's using logs that track the dates
of:
- Retum from the Contractor with pricing;
- Engineer's review and recommendation of pricing; and,
- OWNER's acceptance.
• Assist OWNER with negotiations of cost and time.
2425 - Work Change Directives (WCD's)
• Evaluate field activities to determine need for issuance of Work
Change Directive when necessary to expedite extra work on a time
and materials basis.
• Observe time and material work and reconcile costs with Contractor
on a daily basis.
• Finalize WCD's in an appropriate Change Order when associated
work is complete.
2430 - Change Orders (CO's)
• Identify with the OWNER's designated representative the combining
of CPR's strategy and the timing of Change Orders.
• Update CPR and Change Order Logs and provide status reports
tracking the execution of Change Orders.
• Monitor Contractor progress payment applications to allow payment
only for executed Change Orders.
Meetings/Travel: • Local travel.
Task Deliverables: • Written responses to RFI's.
• Monthly summary of RFI processing and status.
• Field Orders.
• Monthly summary of Field Order status.
• Change Proposal Requests (CPR).
• Estimates of cost and time for each CPR.
• Monthly summary of CPR status.
• Work Change Directives.
• Change Order prepared for execution by Contractor and OWNER.
Key Understandings
and Assumptions:
Information and
Services Provided
by Others:
TASK SERIES 2500 -
Objective:
HDR Activities:
EXHIBIT B — SCOPE OF SERVICES
• Monthly summary of Change Order status.
For information submitted to OWNER, three (3) hard copies will be
provided.
• HDR will use its standard Construction Contract Administration forms
for documenting contract interpretation and modification activities.
• Distribution and numbers of various change documents will be
determined at the Preconstruction Conference.
• Engineering and design tasks required to develop Change Proposal
Requests (CPR's) for issuance to contractor is not part of this scope.
These tasks to be performed by design engineering staff under
separate scope.
• Timely, organized review and execution of changed work
documents.
MEASUREMENT AND PAYMENT ADMINISTRATION
Obtain a reasonably balanced distribution of costs to the various
elements of the total construction in the Contractor's Schedule of Values
(cost breakdown) to serve as a basis for progress payments and
determination of cost impact of changes.
2505 - Review and Approval of Schedule of Values
• Review cost breakdown by comparison to Engineer's Opinion of
Probable Construction Cost back-up file.
• Notify Contractor of acceptance/rejection noting exceptions to
obvious or apparent areas of unbalanced costs.
• Meet with OWNER and Contractor to reconcile disputed areas of
apparent unbalanced costs.
• Document reconciliation of disputed items.
2510 - Review and Process Application for Payment
• Review draft application for payment in comparison to measured or
estimated quantities. Make notations of:
Deficient work not recommended for payment until corrected;
Deletion of payment for stored materials and/or equipment which
do not have approved Shop Drawings and/or proper invoices;
and
Reduction of value for partially completed items claimed as
complete.
Retum a copy of the reviewed draft to the Contractor.
• Conduct review of storage areas and verify existence of invoiced
materials/equipment and proper storage.
• Meet with Contractor to reconcile discrepancies.
• Review revised application for payment and, if appropriate, advise
Contractor to submit the required number of copies.
• Execute completed application for payment indicating amount
recommended for payment and transmit to OWNER for processing
of payment.
EXHIBIT B — SCOPE OF SERVICES
• Review progress of corrective action on punch list items and
periodically update and re -issue.
2615 - Issue Certificate of Substantial Completion and Punch List
• Review the findings of the substantial completion observation with
OWNER and jointly determine the status of the Work.
• Address comments from either OWNER or the Contractor regarding
the tentative date of substantial completion or the punch list.
2625 — Not Used
2630 - Review Final Completion Submittal
• Verify submittal of all required documents.
• Review for completeness and compliance with Contract provisions.
• Notify OWNER and Contractor of date of final observation.
• Determine if OWNER requires (or is required by State Statute) Lien
Waivers and Consent of Surety.
2635 - Conduct Final Completion Observation
• Schedule the final observation date and notify the Contractor and
OWNER.
• Assemble the various final completion submittal documents for the
final observation meeting and review them with the various parties.
• Conduct the final observation.
2640 - Recommend Final Payment
• Finalize all Project costs and determine the final adjusted amounts
for construction as well as reimbursements for engineering services
owed to OWNER by the Contractor.
• Obtain Contractor's signature on any required Contractor's
Certification or Affidavits.
• Process and sign Final Application for Payment.
• Prepare transmittal letter indicating recommendation for Final
Payment and stating whether or not Engineer is aware of any
outstanding issues that preclude issuance of Final Payment.
MeetingslTravel: • Local travel.
Task Deliverables:
• Substantial completion checklist.
• Three (3) CD ROM and six (6) hard copies of Record Drawings.
• Written notification of deficiencies that must be remedied before
proceeding with substantial completion.
• Substantial completion punch list.
• Certificate of Substantial Completion.
• Written notification of date of final observation.
• Written notification of date and time of final observation.
• Recommendation for final payment.
• Copy of final storage records for Project documentation stored by
HDR.
• Three (3) hard copies of specific Project information specifically
requested by OWNER for its files.
For information submitted to OWNER, three (3) hard copies will be
provided.
EXHIBIT B — SCOPE OF SERVICES
Key Understandings
and Assumptions: • Only one substantial completion and one final observation is
anticipated.
Information and
Services Provided
by Others:
• Participation in substantial completion observation.
• Participation in final completion observation.
ADDENDUM TO EXHIBIT D
Fee Schedule
The changes to the fee schedule for this project are as follows:
EXHIBIT D - FEE SCHEDULE
Project Name: CR 122 (Red Bud Lane)
HDR Engineering, Inc.
N
D
N
0
O
0
0
V
a CI
IS w
CO
N
w
c0
ri
tri
0
Nr
N
M
ssificatlons
CADD
V'
N
H
CD
W
!-
for the CIa
Senior
Engineer
V'
E
7
O
=
PM
V
N
N
M
Project
Principal
Per Diem Services
(Task 1 - Revise Storm Sewer Plans to Accommodate new
Red Bud Phase II Storm Sewer System
(Task 2 - UPRR Coordination and Scheduling
I Monthly Meetings (6 Total)
Coordination of Agreement, review of agreement, and
coordination of the UPRR Signal Installations
GRAND TOTAL NOT-TOEXCEED PER DIEM SERVICES $215,370
EXHIBIT D - FEE SCHEDULE
J
3
W
0
tem
a 0
F
V%
0^
0
0
q
4
W
0
N
O_
H
O
F
ID
fications
m
m
L
U
co
coa
I Hours for the Classi
2
a
a
Q c
as
Per Diem Services
'Task 3 - Scheduling Services
Review of Contractor's Construction Schedule &
Review of Monthly Updates (First 2 Months Only)
EXHIBIT D - FEE SCHEDULE
Project Name; CR 122 (Red Bud Lane)
HDR Engineering, Inc.
C
0
O
0
CO
U
o
CA
N69
CO
N
CO
0
v
(9
0
fa
0
CU
co"
69
0
v
0
C9
0
v
Co
f9
`r'
r
M
0
49
F
88
1032
220
80
`"
ns
U
•Q m
a�
v
cg
00
0
80
urs for the Classificatio
Senior
Engineer
N
0
,-
in
M
C(V
PM
CO
sr
CO
0
0
00
0
2
Project
Principal
Per Diem Services
Task 4 - Construction Administration and Management
Project Management
Pre -Con Meetings
Submittal Administration
Construction Observation and Administration
Construction Administration (RFI's, FCC's, etc.)
Measurement and Payment Administration
Project Close-out
Direct Expenses
Truck Expenses ($1100/Month at 6 1/2 Months)
General Office Supplies including printing
Nl ana a3
C)
a)
0
a)
J
m
N
DATE: November 2, 2006
SUBJECT: City Council Meeting - November 9, 2006
ITEM: *11.C.3. Consider a resolution authorizing the Mayor to execute a
Supplemental Agreement #5 with HDR Engineering, Inc. for
engineering services for Red Bud Lane (CR 122) from CR 123 to
US 79.
Department: Transportation Services
Staff Person: Thomas G. Martin, P. E., Director of Transportation Services
Justification:
This Supplemental Contract is for the construction inspection and engineering services for
the duration of construction activities for the Red Bud Lane (CR 122) Bridge Project.
Funding:
Cost:
Source of funds:
$215,370
4B -RR Transportation Development Corp
Outside Resources: HDR Engineering, Inc.
Background Information:
In August, 2005, the City Council approved an Advance Funding Agreement with TxDOT to
replace the existing 2 -lane bridge on Red Bud Lane (CR 122) with a new 4 -lane bridge.
Ninety percent of the cost of the new bridge is being provided by the FHWA through TxDOT.
It is necessary for the City to conduct an environmental assessment for Brushy Creek in this
area to receive FHWA funding.
Public Comment: N/A
EXECUTED
DOCUMENT
FOLLOWS
STATE OF TEXAS
COUNTY OF WILLIAMSON
SUPPLEMENTAL AGREEMENT NO. 5
TO AGREEMENT FOR ENGINEERING SERVICES
FIRM: HDR Engineering, Inc. ("Engineer")
ADDRESS: 4401 Westgate Blvd., Austin, TX 78745
PROJECT: Red Bud Lane (CR 122) from US 79 to CR 123
This Supplemental Agreement No. 5 to Agreement for Engineering Services is made by and
between the City of Round Rock, Texas, hereinafter called the "City" and HDR Engineering,
Inc., hereinafter called the "Engineer".
WHEREAS, the City and Engineer executed an Agreement for Engineering Services,
hereinafter called the "Agreement", on the 22nd day of January, 2004 for Red Bud Lane (CR
122) from US 79 to CR 123, for the sum of $249,363.00; and
WHEREAS, on the 14th day of October, 2004, the City and Engineer executed Supplemental
Agreement No. 1 to amend the Agreement to modify the provisions for the scope of services, to
increase the compensation by $41,255.00 to a total of $290,618.00, and to modify the provision
for notices to proceed; and
WHEREAS, on the 13th day of January, 2005, the City and Engineer executed Supplemental
Agreement No. 2 to amend the Agreement to modify the provisions for the scope of services, to
increase the compensation by $21,872.00 to a total of $312,490.00; and
WHEREAS, on the 9th day of June, 2005, the City and Engineer executed Supplemental
Agreement No. 3 to amend the Agreement to modify the provisions for the scope of services and
to increase the compensation by $7,242.00 to a total of $319,732.00; and
WHEREAS, on the 1st day of December, 2005, the City and Engineer executed Supplemental
Agreement No. 4 to amend the Agreement to modify the provisions for the scope of services and
to increase the compensation by $23,643.00 to a total of $343,375.00; and
WHEREAS, it has become necessary to amend the Agreement to modify the provisions for the
scope of services and to increase the compensation by $215,370.00 to a total of $558,745.00; and
NOW THEREFORE, premises considered, the City and the Engineer agree that said
Agreement is amended as follows:
Supplemental Agreement
Hdr-redbud3; STO2REDBD; 105722
i2 -04,-11-09-1)C3
Rev.03/02/04
64836
I.
Article 2, Scope Of Services To Be Performed By Engineer and Exhibit B, Services To Be
Performed By The Engineer shall be amended as set forth in the attached Addendum To Exhibit
B.
II.
Article 4, Compensation and Exhibit D, Fee Schedule shall be amended by increasing by
$215,370.00 the lump sum amount payable under the Agreement for a total of $558,745.00, as
shown by the attached Addendum to Exhibit D.
IN WITNESS WHEREOF, the City and the Engineer have executed this Supplemental
Agreement in duplicate.
HDR ENGINEERING, INC.
/c4''4.
Jo_ t5.— OG
Date
CITY OF
By:
N, xwell 1 ayor
11-oq-occ
Date
Supplemental Agreement
Hdr-redbud3; STO2REDBD; 105722
2
N
L.
Steph . L. Sheets, City Attorney
Rev.03/02/04
64836
ADDENDUM TO EXHIBIT B
Services to be Provided by the Engineer
The changes to the scope of this project are as follows:
EXHIBIT B — SCOPE OF SERVICES
TASK 3 - SCHEDULING SERVICES
SCOPE STATEMENT AND OBJECTIVE
This Scope of Services is for HDR Engineering, Inc. ("HDR") to provide engineering and
construction contract administration services ("Services") to the Owner ("OWNER') related to the
Projects ("Projects").
SCOPE OF SERVICES
HDR will assist OWNER with ongoing Project implementation by conducting the following tasks:
TASK SERIES 2200 - SCHEDULE ADMINISTRATION
Objective: Obtain, through the Contractor, a detailed construction schedule that
meets the Contract Document requirements and is useful for monitoring
construction progress throughout the Project.
HDR Activities: 2205 - Review and Approval of Initial Construction Schedule
• Review schedule for major elements of the Project and for
conformance to any specified schedule sequences and completion
dates.
• Notify Contractor with acceptance or rejection noting deficiencies
and requesting correction of them and re -submittal.
• Meet with OWNER and Contractor to reconcile disputed schedule
deficiencies and document reconciliation of disputed deficiencies.
2215 - Review Actual Construction Against Schedule Status
• Identify critical path activities that have not reached scheduled
milestones.
• Identify critical path activities whose durations have not expired that
are obviously realizing lower productivity rates than reflected in the
schedule.
• Identify non-critical activities whose durations are about to equal or
exceed the remaining float along that path.
• Identify critical path activities that are scheduled to start but have not
been started.
• Notify Contractor in writing of schedule deficiencies and request a
corrective action plan and revised schedule indicating the means of
regaining schedule losses.
Task Deliverables: • Written rejection or acceptance of Initial schedule.
• Monthly construction progress reports for first 2 months of
Construction
• Written notification of schedule deficiencies.
For information submitted to OWNER, three (3) hard copies will be
provided.
Key Understandings
and Assumptions: • HDR is not responsible for the detailed planning, sequencing and
scheduling of the construction.
Information and
Services Provided
by Others:
EXHIBIT B — SCOPE OF SERVICES
• HDR is not responsible for the Contractor's failure to execute the
approved schedule.
• Timely input on schedule modifications and adjustments by
OWNER throughout the contract period.
EXHIBIT B — SCOPE OF SERVICES
TASK 4 - CONSTRUCTION ADMINISTRATION AND
MANAGEMENT
SCOPE STATEMENT AND OBJECTIVE
This Scope of Services is for HDR Engineering, Inc. ("HDR") to provide engineering and
construction contract administration services ("Services") to the Owner ("OWNER") related to the
Projects ("Projects").
• HDR's fee schedule is based on a construction duration of 30 weeks as specified
in the construction documents. Construction durations in excess of this time will
require a supplemental agreement for the extra time required for field
observation.
• HDR's fee schedule is based on a field representative in the field an average of
40 hours per week as required by actual construction times and operations and a
Senior Construction Engineer an average of 8 hours per week for the duration of
the 30 week construction schedule. Construction observation services in excess
of this time will require a supplemental agreement for the extra time required for
field observation.
SCOPE OF SERVICES
HDR will assist OWNER with ongoing Project implementation by conducting the following tasks:
TASK SERIES 100 - PROJECT MANAGEMENT
Objective: Provide management activities over Project duration including planning,
organizing and monitoring Project team activities.
HDR Activities: 110 - Team Management and Project Control
• Resource management and allocation based on Project schedules
and activities.
• Budget and invoice management.
Meetings/Travel: • Local travel.
Key Understandings
and Assumptions:
• HDR's Project Manager will be responsible for coordinating
management activities.
• A Project kickoff meeting will be held to introduce OWNER and HDR
staff, outline Project goals, overall timetable and communicate
Project vision.
• OWNER will consolidate all comments on the Project Guide and
present them for discussion and resolution at a single meeting with
HDR representatives.
• An average of 1 meeting per month is assumed. Construction phase
meetings are not addressed under this Task Series.
• Quality audits are assumed to be conducted on a three-month (3)
basis.
• For the purpose of this Scope of Services, local travel is defined as
travel in the Round Rock and Project site areas.
Information and
Services Provided
by Others:
TASK SERIES 2000 -
Objective:
HDR Activities:
Meetings/Travel:
Task Deliverables:
Key Understandings
and Assumptions:
EXHIBIT B — SCOPE OF SERVICES
• HDR will produce and distribute meeting minutes for the meetings
defined in this Task Series.
• OWNER personnel will review required standards with HDR as a
preliminary activity to development of the Project Guide and provide
HDR with comments for final Guide development.
• OWNER to provide all available technical standards information and
response to questions posed by HDR in a timely manner.
• OWNER will endeavor to provide a minimum of 48 hours prior notice
for meetings identified in this Task Series.
MEETING ADMINISTRATION
Conduct and document construction phase meetings in order to facilitate
effective Project communications.
2005 - Preconstruction Conference
• Identify with OWNER and Contractor the parties to be included in the
meeting.
• Notify all parties as to the time and place of the meeting. Provide
preliminary agenda for attendee input.
• Prepare final meeting agenda and produce copies for all expected
participants for distribution at meeting.
• Prepare meeting place and provide for meeting documentation.
• Incorporate meeting discussions in final preconstruction meeting
minutes.
• Distribute meeting minutes to all persons in attendance and to
parties on meeting notice list not in attendance.
2010 — Weekly Construction Meetings
• Provide standard formats for meeting agenda, notes and attendance
rosters to promote consistent identification of meeting notes for filing
and cross referencing purposes.
• Establish date, place and agenda for regular construction meetings.
• Determine who is to be involved and notify them of schedule.
• Prepare agenda and distribute copies to those in attendance.
• Conduct meetings and document discussions.
• Distribute meeting minutes to all in attendance, and predetermined
attendees not in attendance, within one week of meeting.
• Local travel.
• Preconstruction Conference Meeting notification including agenda
items.
• Preconstruction Conference Meeting Minutes.
• Construction Meeting notification including agenda items.
• Minutes of each Construction Meeting.
• HDR will use its standard Construction Contract Administration forms
for conducting and documenting construction phase meetings.
Information and
Services Provided
by Others:
EXHIBIT B — SCOPE OF SERVICES
• One (1) Preconstruction Conference will be held per construction
contract.
• One (1) Construction Meeting each week.
• Preconstruction Conference to be held in meeting room provided by
the Owner. Construction Meetings to be held either in meeting room
provided by the Owner or in Contractor provided Construction Field
Office facility.
• OWNER will provide appropriate representation at all Construction
Meetings.
EXHIBIT B — SCOPE OF SERVICES
TASK SERIES 2100 - SUBMITTALS ADMINISTRATION
Objective: Provide administrative and technical support for the administration,
review and approval of Contractor's submittals to determine Contractor's
understanding of material and equipment requirements.
HDR Activities: 2105 - Review and Approval of Shop Drawing Submittal Schedule
• Review Shop Drawing Submittal Schedule.
• Notify Contractor of acceptance or rejection noting deficiencies and
requesting correction of them and resubmittal.
• Distribute copies of approved schedule to design team members
responsible for Shop Drawing reviews.
2110 - General Administration of Submittals
• Receive, log and distribute submittals received from Contractor to
design team for review.
• Provide timely review and re -distribution of Shop Drawings,
miscellaneous submittals, operation and maintenance manuals and
other submittal information.
• Establish organized storage for samples and a tracking log for
samples.
2115 - Review of Shop Drawing Status and Scheduling
• Review weekly the approved submitted schedule and the actual
Shop Drawing Log for comparison.
• Review Shop Drawing Submittal Log in regard to requirements that
all Shop Drawings must be submitted and approved prior to percent
completion defined in Contract Documents
• Utilize Shop Drawings Submittal Schedule as a checklist item for
application for payment.
• Notify Contractor of deficiencies.
• Address general status of Shop Drawings at Construction Meetings.
• Address Contractor's requests for Shop Drawing review of critical
equipment and materials prior to his having an approved submittal
schedule.
2125 - Evaluate Requests for Substitution
• Assist Owner with the review of substitution requests in terms of
quality, cost, constructability and secondary Project impact.
• Assist OWNER in negotiating any cost or time considerations,
additive or deductive, associated with a product substitution.
• Should there be more than ten (10) requests for substitution,
evaluate and process those substitution requests in accordance with
the Additional Service Clause of the agreement.
Meetings/Travel: • Local travel.
Task Deliverables:
• Action letter to Contractor on Schedule Acceptance or Rejection.
• Scheduling Notification to Design Team Shop Drawing Reviewers.
• Review comments on submittals with defined action.
• Weekly Shop Drawing Status Log (Shop Drawings with Contractor).
• Weekly Shop Drawing Status Log (Shop Drawings with HDR).
• Written notification of Shop Drawing Schedule deficiencies.
• Written response to Contractor's special requests for submittal
Key Understandings
and Assumptions:
Information and
Services Provided
by Others:
TASK SERIES
Objective:
EXHIBIT B — SCOPE OF SERVICES
processing.
• Written approval or rejection of substitution requests.
For information submitted to OWNER, three (3) hard copies will be
provided.
• A maximum of 20 hours total is scoped for review of ten (10)
requests for substitution that may be made by the Contractor.
• It is assumed that the cost of reviewing Contractor's initial Shop
Drawing submittals and one resubmittal are included in this scope.
The review costs associated with any subsequent resubmittals will
be paid for by the Contractor.
• Detailed review of submittals/shop drawings for agreement or
conformance with design and specification details is outside of the
scope of this proposal. Detailed review should be provided by
designer(s).
None.
2300 - CONSTRUCTION OBSERVATION
HDR Activities:
Observe, record and report the Contractor's work progress to determine
the work is in general conformance with the requirements of the Contract
Documents. Document activity observed making note of deficiencies
and any issues requiring resolution.
2302 - General Construction Observation
• Obtain and file daily Contractor summary sheets defining specified
work completed and Contractor work force figures.
• Monitor construction activity to verify conformance with Contract
Documents and document activities and observations.
• Record weather condition information.
• Record Requests for Interpretation of Contract Documents
provisions.
• Note construction deficiencies and punch list items.
• Generate photographic or video documentation. (See Task 2324).
2304 - Site Conditions Review
• Periodically review overall condition of site for excessive construction
debris or erosion, and proper drainage and access
• Periodically review protection provisions for existing structures,
piping, trees and other items designated to be protected.
• Document deficiencies and notify the Contractor.
2306 - Structural Subgrade Review
• Review work and coordinate soil engineer and/or testing lab visits for
subgrade verification.
• Review work to verify no foundations or structural slabs on grade are
recommended for payment if concrete placement is made without
written soils lab approval of subgrade condition.
2308 - Coordinate and Review Soils Testing
EXHIBIT B — SCOPE OF SERVICES
• Establish communication of test result procedures and protocols with
testing service and Contractor.
• Review all test results submitted to verify compliance with specified
requirements and maintain Project Log.
• Verify areas of failing compaction are corrected to specified criteria.
• Review soils testing lab invoice to avoid OWNER being charged for
failing tests. Issue payment recommendations to OWNER.
2310 - Coordinate and Review Concrete Testing
• Review concrete mix design with the Structural Engineer and
Contractor to establish specification compliance relative to addition
of water to concrete on site.
• Monitor sampling program to verify correct number of cylinders are
taken as called for in the specifications.
• Review field data to verify other items such as slump, air entrainment
and special admixtures are in accordance with the Contract
Documents.
• Review each failing compressive strength test to determine structural
implications and course of corrective action required.
• Notify Contractor of subsequent testing which is required.
2314 - Stored Materials/Equipment Review
• Coordinate with Contractor to facilitate review of major items prior to
unloading and storage.
• Regularly review Contractor's storage areas to determine compliance
with the Contract Documents.
• Notify the Contractor of any damaged or improperly stored materials.
• Adjust payments properly for damaged or improperly stored
equipment.
2322 - Design Discipline Site Visitations
• Coordinate and conduct design discipline site and other visitations.
• Follow-up of any site deficiencies noted by design team members.
• In the event of visitation by regulatory officials, follow up with
telephone contact to get their impressions and comments.
• For special visitations, arrange that proper persons representing the
various interested parties are present.
2324 - Coordinate Project Photo and Video Documentation
• Develop and maintain a logging system to enable easy retrieval of
visual information.
• Video or photo document construction activities as deemed
appropriate.
2328 - Record Drawing Review
• Review monthly status of as -recorded drawings. Refer to Field
Order and CPR Logs to identify areas of construction revision.
• Notify Contractor in a timely fashion of noted deficiencies.
• Provide follow-up to verify Contractor brings as -recorded drawing
status up-to-date.
• Continually note items as they are noticed during regular field
observation duties for inclusion on monthly as -recorded updates.
• Report general status at Project meetings.
EXHIBIT B — SCOPE OF SERVICES
2330 - Develop a Progressive List of Items Requiring Correction
• Monitor construction throughout the Project duration and identify
deficient items.
• Provide Contractor with an updated list at monthly construction
meetings.
• As deficiencies are corrected, revise the list by deleting corrected
items.
• Distribute the deficiencies list updates to authorized parties.
• Utilize list to aid in identifying retainage amounts near Project
completion.
2340 - OWNER Notification of Accident Damage/Injury
• Maintain communications with Contractor's superintendent to
encourage prompt notification of accidents.
• Require lost -time accident reports at construction meetings.
• Upon observation or notification of an accident, take photographs
and/or videotape of accident scene, make written notes and notify
OWNER and HDR Project Manager.
Meetings/Travel: • Local travel.
Task Deliverables:
Key Understandings
and Assumptions:
• Daily Field Report.
• Monthly Construction Progress Report.
• Notice of Non -Compliance Reports
• Monthly Project Status Report.
• Distribution protocol for testing service.
• Written recommendation for soils testing payment.
• Written notification of out -of -specification concrete and need for
subsequent testing or corrective action.
• Written notification of damaged or improperly stored materials with
adjustment to payment.
• Documentation of site visitation in Project Log. Field reports
documenting results of field visitation.
• Photo/video documentation of construction activities accessible
without an organized retrieval system.
• Written notification of deficiencies in Record Drawings.
• Monthly punch list of work.
• Documentation of accident damage/injury.
• Certificate of Substantial Completion.
For information submitted to OWNER, three (3) hard copies will be
provided.
• HDR will use its standard Construction Contract Administration forms
for documenting construction observation and observation activities.
• HDR's fee schedule is based on an assumed construction duration
of 30 weeks. Construction durations in excess of this time will require
a supplemental agreement for the extra time required for field
observation.
• HDR's fee schedule is based on a field representative in the field an
average of 40 hours per week as required by actual construction
times and operations and a Construction Engineer an average of 8
Information and
Services Provided
by Others:
TASK SERIES 2400
ADMINISTRATION
Objective:
HDR Activities:
EXHIBIT B — SCOPE OF SERVICES
hours per week for the duration of the 30 week construction
schedule. Construction observations services in excess of this time
will require a supplemental agreement for the extra time required for
field observation.
• HDR will not supervise, direct or control Contractor's forces.
• HDR's construction observation will not be exhaustive and is not
intended to be sufficient enough to prevent Contractors from failing
to perform work in accordance with contract requirements. HDR will
act to have defective work corrected by the Contractors when HDR is
aware defective work exists.
• HDR will manage a maximum of 1 construction observers to provide
construction observation at the site of the Work, and will not be
required to assign personnel to this Task to the extent that a
construction observer is present on site at all times a Contractor is
working.
• HDR will not provide equipment for or conduct the testing of soils
and soils compaction, concrete sampling and testing or other
construction materials sampling and testing.
• OWNER to provide any special protocol to be used when non -
construction related personnel visit the site.
- CONTRACT INTERPRETATIONS AND MODIFICATIONS
Provide timely reviews and responses to Contractor requests for
interpretations or information and proposed modifications identified by
the Contractors, OWNER or HDR design and construction observation
team.
2405 - Coordinate Interpretations Review
• Receive, log and distribute Requests for Information (RFI) to
appropriate design team members for response.
• Review and respond to RFI's.
• Receive design team responses, log and distribute to Contractor.
• Prepare and issue response letters, Field Orders (FO's) or Change
Proposal Requests (CPR's) as required.
2410 - Administration of Changed Work.
• Initiate necessary changes in the form of CPR's.
• Review costs presented on CPR's by Contractor. Assist OWNER
with negotiation of final pricing as required.
• Review all CPR items and negotiated costs with OWNER for
OWNER's approval.
• Assemble approved CPR's periodically into Change Orders (CO's).
Include justification documents with each CO.
• Track CPR's and CO's through Contractor's acceptance, OWNER's
acceptance, Engineer's signature and OWNER executive action.
• Maintain current status log of all CPR's and CO's.
• For minor changes involving no cost and no time changes, issue
FO's.
• Review as -recorded drawings to verify changes in work are reflected
as applicable.
EXHIBIT B — SCOPE OF SERVICES
• Review pay requests to verify CO items are broken out and that
payment is not made until work is complete.
2415 - Coordinate and Issue Field Orders (FO's)
• Prepare technical description of the FO.
• Route FO through established clearinghouse for numbering, logging
and issuance to the Contractor.
• Obtain a copy, executed by the Contractor, and route copies to the
appropriate Project files.
2420 - Coordinate and issue Change Proposal Requests (CPR's)
• Collect technical information and evaluate proposed change.
Prepare technical description of the CPR using necessary graphic
details and specifications.
• Prepare Engineer's Opinion of Cost and evaluation of impact on
Contract Time.
• Route the CPR through established clearinghouse for numbering,
logging and issuance to the Contractor for pricing.
• Route copies to the appropriate Project files.
• Follow and report the status of CPR's using logs that track the dates
of:
- Retum from the Contractor with pricing;
- Engineer's review and recommendation of pricing; and,
- OWNER's acceptance.
• Assist OWNER with negotiations of cost and time.
2425 - Work Change Directives (WCD's)
• Evaluate field activities to determine need for issuance of Work
Change Directive when necessary to expedite extra work on a time
and materials basis.
• Observe time and material work and reconcile costs with Contractor
on a daily basis.
• Finalize WCD's in an appropriate Change Order when associated
work is complete.
2430 - Change Orders (CO's)
• Identify with the OWNER's designated representative the combining
of CPR's strategy and the timing of Change Orders.
• Update CPR and Change Order Logs and provide status reports
tracking the execution of Change Orders.
• Monitor Contractor progress payment applications to allow payment
only for executed Change Orders.
Meetings/Travel: • Local travel.
Task Deliverables:
• Written responses to RFI's.
• Monthly summary of RFI processing and status.
• Field Orders.
• Monthly summary of Field Order status.
• Change Proposal Requests (CPR).
• Estimates of cost and time for each CPR.
• Monthly summary of CPR status.
• Work Change Directives.
• Change Order prepared for execution by Contractor and OWNER.
Key Understandings
and Assumptions:
Information and
Services Provided
by Others:
TASK SERIES 2500 -
Objective:
HDR Activities:
EXHIBIT B — SCOPE OF SERVICES
• Monthly summary of Change Order status.
For information submitted to OWNER, three (3) hard copies will be
provided.
• HDR will use its standard Construction Contract Administration forms
for documenting contract interpretation and modification activities.
• Distribution and numbers of various change documents will be
determined at the Preconstruction Conference.
• Engineering and design tasks required to develop Change Proposal
Requests (CPR's) for issuance to contractor is not part of this scope.
These tasks to be performed by design engineering staff under
separate scope.
• Timely, organized review and execution of changed work
documents.
MEASUREMENT AND PAYMENT ADMINISTRATION
Obtain a reasonably balanced distribution of costs to the various
elements of the total construction in the Contractor's Schedule of Values
(cost breakdown) to serve as a basis for progress payments and
determination of cost impact of changes.
2505 - Review and Approval of Schedule of Values
• Review cost breakdown by comparison to Engineer's Opinion of
Probable Construction Cost back-up file.
• Notify Contractor of acceptance/rejection noting exceptions to
obvious or apparent areas of unbalanced costs.
• Meet with OWNER and Contractor to reconcile disputed areas of
apparent unbalanced costs.
• Document reconciliation of disputed items.
2510 - Review and Process Application for Payment
• Review draft application for payment in comparison to measured or
estimated quantities. Make notations of:
Deficient work not recommended for payment until corrected;
Deletion of payment for stored materials and/or equipment which
do not have approved Shop Drawings and/or proper invoices;
and
Reduction of value for partially completed items claimed as
complete.
Return a copy of the reviewed draft to the Contractor.
• Conduct review of storage areas and verify existence of invoiced
materials/equipment and proper storage.
• Meet with Contractor to reconcile discrepancies.
• Review revised application for payment and, if appropriate, advise
Contractor to submit the required number of copies.
• Execute completed application for payment indicating amount
recommended for payment and transmit to OWNER for processing
of payment.
Meetings/Travel:
Task Deliverables:
Key Understandings
and Assumptions:
Information and
Services Provided
by Others:
EXHIBIT B — SCOPE OF SERVICES
• Distribute executed copies as established in preconstruction
conference minutes.
• Monitor total payments to adjust retainage amounts as specified in
the Contract Documents.
• As Project nears completion, and at OWNER's direction, adjust
retainage from fixed percent to only enough retainage to provide for
work completion.
• Local travel.
• Written review comments of Schedule of Values as required until
schedule is acceptable.
• Written review comments of each Application of Payment as required
until each payment is acceptable.
• Recommendation for OWNER payment.
For information submitted to OWNER, three (3 hard copies will be
provided.
None.
• Timely execution of Contractor payment.
• OWNER input for resolution of disputed items on Contractor's pay
requests.
TASK SERIES 2600 - PROJECT CLOSEOUT
Objective:
HDR Activities:
Conduct an orderly and properly documented Project closeout.
2605 - Review Substantial Completion Submittal
• Receive and review Contractor's required substantial completion
submittal and determine if Project is ready for substantial completion
observation.
• Develop substantial completion submittal checklist.
• Verify submittal of all required documents.
• Review Contractor Record Drawings.
• Perform drafting of Record Drawing revisions on reproducible set
and transmit to OWNER.
• Review other substantial completion submittal documents for
completeness and compliance with Contract provisions.
• Schedule substantial completion observation.
2610 - Conduct Substantial Completion Observation
• Notify design team members of date or substantial completion
observation.
• Notify OWNER's designated representative of the date of the
substantial completion observation.
• Prepare and distribute the punch list format to the parties conducting
the observation.
• Compile the punch list, review with OWNER and transmit to the
Contractor.
EXHIBIT B — SCOPE OF SERVICES
• Review progress of corrective action on punch list items and
periodically update and re -issue.
2615 - Issue Certificate of Substantial Completion and Punch List
• Review the findings of the substantial completion observation with
OWNER and jointly determine the status of the Work.
• Address comments from either OWNER or the Contractor regarding
the tentative date of substantial completion or the punch list.
2625 — Not Used
2630 - Review Final Completion Submittal
• Verify submittal of all required documents.
• Review for completeness and compliance with Contract provisions.
• Notify OWNER and Contractor of date of final observation.
• Determine if OWNER requires (or is required by State Statute) Lien
Waivers and Consent of Surety.
2635 - Conduct Final Completion Observation
• Schedule the final observation date and notify the Contractor and
OWNER.
• Assemble the various final completion submittal documents for the
final observation meeting and review them with the various parties.
• Conduct the final observation.
2640 - Recommend Final Payment
• Finalize all Project costs and determine the final adjusted amounts
for construction as well as reimbursements for engineering services
owed to OWNER by the Contractor.
• Obtain Contractor's signature on any required Contractor's
Certification or Affidavits.
• Process and sign Final Application for Payment.
• Prepare transmittal letter indicating recommendation for Final
Payment and stating whether or not Engineer is aware of any
outstanding issues that preclude issuance of Final Payment.
Meetings/Travel: • Local travel.
Task Deliverables: • Substantial completion checklist.
• Three (3) CD ROM and six (6) hard copies of Record Drawings.
• Written notification of deficiencies that must be remedied before
proceeding with substantial completion.
• Substantial completion punch list.
• Certificate of Substantial Completion.
• Written notification of date of final observation.
• Written notification of date and time of final observation.
• Recommendation for final payment.
• Copy of final storage records for Project documentation stored by
HDR.
• Three (3) hard copies of specific Project information specifically
requested by OWNER for its files.
For information submitted to OWNER, three (3) hard copies will be
provided.
EXHIBIT B — SCOPE OF SERVICES
Key Understandings
and Assumptions: • Only one substantial completion and one final observation is
anticipated.
Information and
Services Provided
by Others:
• Participation in substantial completion observation.
• Participation in final completion observation.
ADDENDUM TO EXHIBIT D
Fee Schedule
The changes to the fee schedule for this project are as follows:
EXHIBIT D - FEE SCHEDULE
Project Name: CR 122 (Red Bud Lane)
HDR Engineering, Inc.
C
l9
N
0
O
0
F-
O
0
0
a
N'
49
0
of
00
N
$3,840 l
0
1.6
69
0
Vim'
N
M
ssifications
0
24
0
0
0
F
CO
W,-
for the Cia
Senior
Engineer
.4-
E E
PM
0
0
=
a
N
N
M
Project
Principal
Per Diem Services
'Task 1 - Revise Storm Sewer Plans to Accommodate new
Red Bud Phase II Storm Sewer System
'Task 2 - UPRR Coordination and Scheduling
Monthly Meetings (6 Total)
Coordination of Agreement, review of agreement, and
coordination of the UPRR Signal Installations
GRAND TOTAL NOT-TOEXCEED PER DIEM SERVICES $215,370
EXHIBIT D - FEE SCHEDULE
Project Name: CR 122 (Red Bud Lane)
Consultant: HDR Engineering, Inc.
V)
H
O
U
$10,240.00 I
a
N
o
T.;
Oc,0
1—
to5
O
=
W
V
w
'a3 m
m
•
U 0
y
cp
1 Hours for the Classi
Wd
Project
Principal
Per Diem Services
Task 3 - Scheduling Services
Review of Contractor's Construction Schedule &
Review of Monthly Updates (First 2 Months Only)
EXHIBIT D - FEE SCHEDULE
Project Name: CR 122 (Red Bud Lane)
HDR Engineering, Inc.
C
0
0
1—
N
0
0
1,
c;
N
0
CO
toc°Do
H
0
f9
$10,440
$115,240 I
0
N
HEA
0
CO
0
v
CO
V3
LO0
fA
fA
O0
F
DI
88
DI
c+)
o
0O
N
Co
co
r
r
Hours for the Classifications
Project
Rep.
v
m
CO
a,
s—
0
Tr
80
Senior
Engineer
N
120 I
co
M
N
d
m
v
m
m
co
co
Project
Principal
Per Diem Services
Task 4 - Construction Administration and Management
Project Management
Pre -Con Meetings
Submittal Administration
Construction Observation and Administration
Construction Administration (RFI's, FCC's, etc.)
Measurement and Payment Administration
Project Close-out
Direct Expenses
Truck Expenses ($1100/Month at 6 1/2 Months)
General Office Supplies including printing