R-2016-3922 - 11/10/2016 RESOLUTION NO. R-2016-3922
WHEREAS,the City of Round Rock entered into a contract on September 11,2014 with Chasco
Constructors, Ltd., L.L.P., entitled "Agreement Between Owner and Construction Manager at Risk
Where Construction Manager at Risk Is Also the Constructor," and such contract is for construction of
the Public Safety Training Facility; and
WHEREAS,the terms of such contract require submission by Chasco Constructors,Ltd.,L.L.P.
of "Amendment No. 1 to Agreement Between Owner and Construction Manager at Risk," which
Amendment No. 1 is to set forth the Guaranteed Maximum Price as required in the contract;and
WHEREAS, the City Council wishes to accept such Amendment No. 1 to the referenced
Agreement,Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS,
That the Mayor is hereby authorized and directed to execute, on behalf of the City, Amendment
No. 1 with Chasco Constructors, Ltd., L.L.P. for the Guaranteed Maximum Price as stated therein, and
same is for construction of the Public Safety Training Facility, a copy of said Amendment No. 1 being
attached hereto as Exhibit"A" and incorporated herein for all purposes.
The City Council hereby finds and declares that written notice of the date,hour,place and subject
of the meeting at which this Resolution was adopted was posted and that such meeting was open to the
public as required by law at all times during which this Resolution and the subject matter hereof were
discussed, considered and formally acted upon, all as required by the Open Meetings Act, Chapter 551,
Texas Government Code, as amended.
RESOLVED this 10th day of November, 2016.
X 11-
, 1
City of Round Rock, Texas
ATTEST: � la {V�xz pt I � N)4ym � m
SARA L. WHITE, City Clerk
0112.1604;00366689
EXHIBIT
«A»
AMENDMENT NO. 1 TO AGREEMENT BETWEEN
OWNER AND CONSTRUCTION MANAGER AT RISK
Pursuant to Article 2, Subparagraph 2.7 of the previously-executed "Agreement Between Owner
and Construction Manager at Risk Where Construction Manager at Risk is Also the Constructor" ( the
Agreement),dated the 11"'day of the month of September,2014, by and between the City of Round Rock,
Texas (the Owner) and Chasco Constructors, Ltd., L.L.P. (the Construction Manager), for new
construction of a Public Safety Training Facility at 2701 North Mays Street, Round Rock, Texas (the
Project), the Owner and the Construction Manager hereby establish a Guaranteed Maximum Price, and
reiterate the scope of the Project and Completion Date for the Work as contained in the Agreement and as
set forth below.
Article 1
THE WORK
The scope of the Project included in this Amendment, and its Guaranteed Maximum Price, is for
the work in its entirety for the construction of the above-referenced Project.
Article 2
EXHIBITS
The following exhibit supplements this Agreement:
Exhibit"A" Section 1 "Description of Work": Document List, including Clarifications;
Assumptions; and Qualifications.
Section 2 "Cost Summary": Guaranteed Maximum Price, inclusive of the
Construction Manager's contingency, and additionally including Cost
Breakdown.
Article 3
GUARANTEED MAXIMUM PRICE
The Construction Manager's Guaranteed Maximum Price (the GMP) for the Work, including the
estimated Cost of the Work as defined in Article 6 and the Construction Manager's Fee as defined in
Article 5, is the sum of TWENTY-FIVE MILLION NINE HUNDRED SIXTY-TWO THOUSAND
SEVEN HUNDRED EIGHTEEN AND 00/100 DOLLARS($25,962,718.00).
This price is for the performance of the Work in accordance with the Contract Documents and
any attached exhibits.
00366402/ss2
1
Article 4
COMPLETION DATE
The Final Completion Date for the Project shall be no later than 540 calendar days from the date
established in the Notice.to Proceed,which shall be issued to the Construction Manager by the Owner.
OWNER: CONSTRUCTION MANAGER:
City of Round Rock,Texas Chasco Constructors 'L_.L.P.
By: By: i
Printed Name: Printed Name: Char es lace,Jr.
Title: Title: President
Date Signed: Date Signed:
FOR CITY,ATTEST:
By:
Sara L. White,City Clerk
FOR CITY,APPROVED AS TO FORIM:
By:
Stephan L. Sheets, City Attorney
2
®C ASCD
CONSTRUCTORS
Exhibit A
GMP Cost Estimate
City of Round Rock Public Safety Training Facility
Round Rock, Texas
October 17, 2016
ROUND ROCK TEMS
GENERAL SERVICES
Round Rock Public Safety Training Facility GMP Cost Estimate
Table of Contents
Section 1 Clarifications, Assumptions, and Qualifications
A. Document List................................................... . 3
B. General Requirements......................................... 13
C. Buildings &Training Areas in Base Budget
11) Main Building............................................... 15
21) One Story.................................................... 26
22) One Story w/Garage...................................... 28
23) Two Story w/Garage..................................... 31
24) Two Story Zero Lot w/Garage......................... 34
25) Two Story Zero Lot w/Garage......................... 37
26) One Story w/Garage...................................... 40
31) Outdoor Classroom and Shared Storage.......... 43
41) Fire Tower.................................................... 46
43) Fire Apartment.............................................. 49
44) Fire House.................................................... 52
> Site Infrastructure.......................................... 55
D. Alternates............................................................ 59
#1)EVOC
#2)Swift Water Rescue
#3)North Parking
#4)Fire Warehouse
E. Contingency........................................................ 62
F. Exclusions.......................................................... 62
G. Schedule............................................................. 63
Section 2 Cost Summary....................................................... 64
A. Base Bid GMP Cost Estimate with Price Breakdown
2
Round Rock Public Safety Training Facility GMP Cost Estimate
Section 1 - Clarifications, Assumptions, and Qualifications
A. Document List
Volume 1
Sheet Title Issue Date Issued By
CVR1 VOLUME 1 -COVER 8/29/2016
C0.01 SITE PLAN 8/29/2016 Hart, Gaugler&Associates
C0.02 SITE PLAN 8/29/2016 Hart, Gaugler&Associates
C0.03 GENERAL NOTES 8/29/2016 Hart, Gaugler&Associates
C1.00 DEMOLITION PLAN 8/29/2016 Hart, Gaugler&Associates
C1.01 DEMOLITION PLAN 8/29/2016 Hart,Gaugler&Associates
C1.02 PAVING&DIMENSION CONTROL 8/29/2016 Hart,Gaugler&Associates
C1.03 PAVING&DIMENSION CONTROL 8/29/2016 Hart, Gaugler&Associates
C1.04 PAVING&DIMENSION CONTROL 8/29/2016 Hart, Gaugler&Associates
C1.05 ENLARGED DETAILS 8/29/2016 Hart, Gaugler&Associates
C1.06 ENLARGED DETAILS 8/29/2016 Hart, Gaugler&Associates
C1.07 FUEL SPILL DETAIL 8/29/2016 Hart, Gaugler&Associates
C1.08 DRAFTING TANK DETAIL 8/29/2016 Hart, Gaugler&Associates
C1.09 TRENCH RESCUE DETAIL 8/29/2016 Hart,Gaugler&Associates
C1.10 TRACK PLAN VIEW 8/29/2016 Hart,Gaugler&Associates
C1.11 TRACK PAVEMENT MARKINGS AND SIGNAGE 8/29/2016 Hart, Gaugler&Associates
C1.12 TRACK PROFILE 8/29/2016 Hart,Gaugler&Associates
C1.13 TRACK PROFILE 8/29/2016 Hart,Gaugler&Associates
C1.14 SWIFT WATER PROFILE 8/29/2016 Hart,Gaugler&Associates
C2.00 EXISTING 100 YR DRAINAGE AREA MAP 8/29/2016 Hart, Gaugler&Associates
C2.01 100 YR DRAINAGE AREA MAP 8/29/2016 Hart, Gaugler&Associates
C2.02 100 YR DRAINAGE AREA MAP 8/29/2016 Hart, Gaugler&Associates
C2.03 DRAINAGE AREA MAP 25 YEAR STORM 8/29/2016 Hart, Gaugler&Associates
C2.04 DRAINAGE AREA MAP 25 YEAR STORM 8/29/2016 Hart, Gaugler&Associates
C2.05 STORM SEWER PLAN 8/29/2016 Hart, Gaugler&Associates
C2.06 STORM SEWER PLAN 8/29/2016 Hart, Gaugler&Associates
C2.07 STORM LINE PROFILE A&LAT Al 8/29/2016 Hart, Gaugler&Associates
C2.08 STORM LINE PROFILE LAT A2&LAT A2-1 8/29/2016 Hart,Gaugler&Associates
C2.09 STORM LINE PROFILE B, LAT B1 &LAT B2 8/29/2016 Hart, Gaugler&Associates
C2.10 STORM LINE PROFILE C 8/29/2016 Hart, Gaugler&Associates
C2.11 STORM LINE PROFILE LAT C1 &LAT C2 8/29/2016 Hart, Gaugler&Associates
C2.12 STORM LINE PROFILE D&LAT D1 8/29/2016 Hart, Gaugler&Associates
C2.13 STORM LINE PROFILE LAT D2, LAT D3,&LAT D4 8/29/2016 Hart, Gaugler&Associates
C2.14 STORM LINE PROFILE E&LAT E1 8/29/2016 Hart, Gaugler&Associates
C2.15 STORM LINE PROFILE LAT E2&LAT E3 8/29/2016 Hart, Gaugler&Associates
C2.16 STORM LINE PROFILE F&LAT F1 8/29/2016 Hart, Gaugler&Associates
C2.17 STORM LINE PROFILE G 8/29/2016 Hart, Gaugler&Associates
C2.18 STORM CALCULATIONS (1) 8/29/2016 Hart, Gaugler&Associates
C219 STORM CALCULATIONS (2) 8/29/2016 Hart, Gaugler&Associates
C2.20 STORM CALCULATIONS(3) 8/29/2016 Hart, Gaugler&Associates
3
Round Rock Public Safety Training Facility GMP Cost Estimate
C2.21 STORM CALCULATIONS TRACK 8/29/2016 Hart, Gaugler&Associates
C3.00 GRADING PLAN 8/29/2016 Hart, Gaugler&Associates
C3.01 GRADING PLAN 8/29/2016 Hart, Gaugler&Associates
C3.02 GRADING ENLARGED PLAN 8/29/2016 Hart,Gaugler&Associates
C3.03 GRADING ENLARGED PLAN 8/29/2016 Hart, Gaugler&Associates
C3.04 GRADING ENLARGED PLAN 8/29/2016 Hart, Gaugler&Associates
C3.05 GRADING ENLARGED PLAN 8/29/2016 Hart, Gaugler&Associates
C4.00 WATER UTILITY PLAN 8/29/2016 Hart, Gaugler&Associates
C4.01 SANITARY SEWER PLAN 8/29/2016 Hart, Gaugler&Associates
C4.02 SANITARY SEWER PLAN 8/29/2016 Hart,Gaugler&Associates
C4.03 SANITARY SEWER PROFILE A 8/29/2016 Hart, Gaugler&Associates
C4.04 SANITARY SEWER PROFILE B, B1 &B2 8/29/2016 Hart,Gaugler&Associates
C4.05 SANITARY SEWER PROFILE C 8/29/2016 Hart, Gaugler&Associates
C4.06 SANITARY SEWER PROFILE C 8/29/2016 Hart, Gaugler&Associates
C4.07 SANITARY SEWER PROFILE C1 8/29/2016 Hart, Gaugler&Associates
C4.08 WATER PROFILE LINE A 8/29/2016 Hart, Gaugler&Associates
C4.09 WATER PROFILE LINE A 8/29/2016 Hart, Gaugler&Associates
C4.10 WATER PROFILE LINE G 8/2912016 Hart,Gaugler&Associates
C5.00 TCEQ BMP MAP 8/29/2016 Hart, Gaugler&Associates
C5.01 EROSION CONTROL PLAN 8/29/2016 Hart, Gaugler&Associates
C5.02 EROSION CONTROL PLAN 8/29/2016 Hart, Gaugler&Associates
C5.03 EROSION CONTROL DETAILS 8/29/2016 Hart, Gaugler&Associates
C5.04 EROSION CONTROL DETAILS 8/29/2016 Hart, Gaugler&Associates
C6.00 CONSTRUCTION DETAILS 8/29/2016 Hart, Gaugler&Associates
C6.01 CONSTRUCTION DETAILS 8/29/2016 Hart, Gaugler&Associates
C6.02 CONSTRUCTION DETAILS 8/29/2016 Hart, Gaugler&Associates
C6.03 CONSTRUCTION DETAILS 8/29/2016 Hart, Gaugler&Associates
C6.04 CONSTRUCTION DETAILS 8/29/2016 Hart, Gaugler&Associates
C6.05 CONSTRUCTION DETAILS 8/29/2016 Hart, Gaugler&Associates
C6.06 CITY OF ROUND ROCK DETAILS 8/29/2016 Hart, Gaugler&Associates
C6.07 CITY OF ROUND ROCK DETAILS 8/29/2016 Hart, Gaugler&Associates
C6.08 CITY OF ROUND ROCK DETAILS 8/29/2016 Hart, Gaugler&Associates
C6.09 TANK AND STORM TROOPER DETAILS 8/29/2016 Hart, Gaugler&Associates
S001 GENERAL NOTES 8/29/2016 Hart, Gaugler&Associates
S002 STRUCTURAL PLAN 8/29/2016 Hart, Gaugler&Associates
A001 SITE SURVEY 8/29/2016 Brinkley Sargent Architects
A110 SITE DEMO PLAN 8/29/2016 Brinkley Sargent Architects
A111 SITE PLAN 8/29/2016 Brinkley Sargent Architects
A121 ENLARGED SITE PLANS&DETAILS(NON-VILLAGE) 8/29/2016 Brinkley Sargent Architects
A122 ENLARGED SITE PLANS&DETAILS(NON-VILLAGE) 8/29/2016 Brinkley Sargent Architects
Al 23 ENLARGED SITE PLANS&DETAILS(NON-VILLAGE) 8/29/2016 Brinkley Sargent Architects
A841 DOOR SCHEDULE, DOOR TYPES, PARTITION TYPES 8/29/2016 Brinkley Sargent Architects
A111 PARTIAL TRAINING GROUNDS SITE PLAN 8/29/2016 G2 Solutions Group
Al 12 TRENCH RESCUE CONFINED SPACE SITE PLAN 8/29/2016 G2 Solutions Group
Al 13 TRENCH RESCUE CONFINED SPACE DIMENSION PLANS 8/29/2016 G2 Solutions Group
A131 SITE DETAILS 8/29/2016 G2 Solutions Group
4
Round Rock Public Safety Training Facility GMP Cost Estimate
Al 32 SITE DETAILS 8/2912016 G2 Solutions Group
Al 33 SITE DETAILS 8/29/2016 G2 Solutions Group
Al 51 TRENCH RESCUE CONFINED SPACE ELEVATIONS 8/29/2016 G2 Solutions Group
Al 91 TRENCH RESCUE CONFINED SPACE ISOMETRIC VIEWS 8/29/2016 G2 Solutions Group
SC103 SECURITY DRAWING 8/29/2016 Datacom Design Group
E100 SITE PLAN-ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
E101 SCHEDULES, NOTES&LEGENDS-ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
E102 SCHEDULES- ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
E103 SCHEDULES-ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
E104 SCHEDULES-ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
E105 SCHEDULES- ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
E106 SCHEDULES-ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
E107 SCHEDULES-ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
E108 DETAILS-ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
EP211 FLOOR PLAN AREA A-POWER 8/29/2016 Hendrix Consulting Engineers
EP212 FLOOR PLAN AREA B-POWER 8/29/2016 Hendrix Consulting Engineers
EP213 FLOOR PLAN AREA C-POWER 8/29/2016 Hendrix Consulting Engineers
EP221 FLOOR PLANS-BLDGS 21-26-ELECTRICAL AND PLUMBING 8/29/2016 Hendrix Consulting Engineers
EPA211 FLOOR PLAN-APARTMENT-ELECTRICAL AND PLUMBING 8/29/2016 Hendrix Consulting Engineers
EPH211 FLOOR PLAN-HOUSE-ELECTRICAL AND PLUMBING 8/29/2016 Hendrix Consulting Engineers
EPS211 FLOOR PLAN-SHARED-ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
EPT211 FLOOR PLAN-TOWER-ELECTRICAL AND PLUMBING 8/29/2016 Hendrix Consulting Engineers
EPW211 FLOOR PLAN-WAREHOUSE-ELECTRICAL AND PLUMBING 8/29/2016 Hendrix Consulting Engineers
EP411 ROOF PLAN-ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
T101 SITE PLAN-COMMUNICATIONS 8/29/2016 Datacom Design Group
L-1 LANDSCPAE(1 of 4) 8/29/2016 City of Round Rock
L-2 LANDSCAPE(2 of 4) 8/29/2016 City of Round Rock
L-3 LANDSCAPE(3 OF 4) 8/29/2016 City of Round Rock
L-4 LANDSCAPE(4 OF 4) 8/29/2016 City of Round Rock
Volume 2
Sheet Title Issue Date Issued By
CVR2 VOLUME 2-COVER 8/29/2016
S001 GENERAL NOTES 8/29/2016 Hart,Gaugler and Associates
S002 TYPICAL DETAILS 8/29/2016 Hart, Gaugler and Associates
S101 FOUNDATION PLAN 8/29/2016 Hart, Gaugler and Associates
S102 FOUNDATION PLAN 8/29/2016 Hart,Gaugler and Associates
S103 FOUNDATION PLAN 8/29/2016 Hart,Gaugler and Associates
S104 FOUNDATION PLAN 8/29/2016 Hart, Gaugler and Associates
S201 ROOF FRAMING PLAN 8/29/2016 Hart, Gaugler and Associates
S202 ROOF FRAMING PLAN 8/29/2016 Hart,Gaugler and Associates
S203 ROOF FRAMING PLAN 8/29/2016 Hart, Gaugler and Associates
S204 CANOPY PLANS 8/29/2016 Hart, Gaugler and Associates
S301 FOUNDATION DETAILS 8/29/2016 Hart, Gaugler and Associates
S302 FOUNDATION DETAILS 8/29/2016 Hart, Gaugler and Associates
S303 FOUNDATION DETAILS 8/29/2016 Hart, Gaugler and Associates
S401 FRAMING DETAILS 8/29/2016 Hart, Gaugler and Associates
5
Round Rock Public Safety Training Facility GMP Cost Estimate
S402 FRAMING DETAILS 8/29/2016 Hart, Gaugler and Associates
S501 PANEL DETAILS&ELEVATIONS 8/29/2016 Hart, Gaugler and Associates
S502 PANEL ELEVATIONS 8/29/2016 Hart, Gaugler and Associates
S503 PANEL ELEVATIONS 8/29/2016 Hart, Gaugler and Associates
S504 PANEL ELEVATIONS 8/29/2016 Hart,Gaugler and Associates
A000 TEXAS ACCESSIBILITY STANDARDS 8/29/2016 Brinkley Sargent Architects
A201 CODE PLAN 8/29/2016 Brinkley Sargent Architects
A201 SLAB EDGE PLAN 8/29/2016 Brinkley Sargent Architects
A211 REFERENCE PLAN 8/29/2016 Brinkley Sargent Architects
A212 FLOOR PLAN-AREA'A'-WALL TAGS,DIMENSIONS 8/29/2016 Brinkley Sargent Architects
A213 FLOOR PLAN-AREA'B'-WALL TAGS, DIMENSIONS 8/29/2016 Brinkley Sargent Architects
A214 FLOOR PLAN-AREA'A'-EQUIPMENT, INTERIOR 8/29/2016 Brinkley Sargent Architects
ELEVATIONS
A215 FLOOR PLAN-AREA'B'-EQUIPMENT, INTERIOR 8/29/2016 Brinkley Sargent Architects
ELEVATIONS
A270 ENLARGED FLOOR PLANS 8/29/2016 Brinkley Sargent Architects
A271 STAIR PLAN,SECTION&DETAILS 8/29/2016 Brinkley Sargent Architects
A290 ROOF PLAN 8/29/2016 Brinkley Sargent Architects
A291 CANOPY 8/29/2016 Brinkley Sargent Architects
A292 ROOF DETAILS 8/29/2016 Brinkley Sargent Architects
A301 REFLECTED CEILING PLAN 8/29/2016 Brinkley Sargent Architects
A311 CEILING DETAILS 8/29/2016 Brinkley Sargent Architects
A401 BUILDING ELEVATIONS 8/29/2016 Brinkley Sargent Architects
A411 TILT WALL PANEL ELEVATIONS 8/29/2016 Brinkley Sargent Architects
A412 TILT WALL PANEL ELEVATIONS 8/29/2016 Brinkley Sargent Architects
A421 AXONOMETRIC VIEWS 8/29/2016 Brinkley Sargent Architects
A501 BUILDING SECTIONS 8/29/2016 Brinkley Sargent Architects
A502 BUILDING SECTIONS 8/29/2016 Brinkley Sargent Architects
A503 BUILDING SECTIONS 8/29/2016 Brinkley Sargent Architects
A511 WALL SECTIONS 8/29/2016 Brinkley Sargent Architects
A512 WALL SECTIONS 8/29/2016 Brinkley Sargent Architects
A513 WALL SECTIONS 8/29/2016 Brinkley Sargent Architects
A521 SECTION DETAILS 8/29/2016 Brinkley Sargent Architects
A522 SECTION DETAILS 8/29/2016 Brinkley Sargent Architects
A523 SECTION DETAILS 8/29/2016 Brinkley Sargent Architects
A524 SECTION DETAILS 8/29/2016 Brinkley Sargent Architects
A601 PLAN DETAILS 8/29/2016 Brinkley Sargent Architects
A602 PLAN DETAILS 8)29/2016 Brinkley Sargent Architects
A701 PARTITION TYPES 8/29/2016 Brinkley Sargent Architects
A702 DOOR SCHEDULE DOOR TYPES 8/29/2016 Brinkley Sargent Architects
A703 DOOR DETAILS 8/29/2016 Brinkley Sargent Architects
A704 DOOR DETAILS 8/29/2016 Brinkley Sargent Architects
A810 EQUIPMENT AND FINISH SCHEDULE 8/29/2016 Brinkley Sargent Architects
A811 FINISH LEGEND AND NOTES 8/29/2016 Brinkley Sargent Architects
A812 FINISH PLAN 8/29/2016 Brinkley Sargent Architects
A821 FINISH DETAILS 8/29/2016 Brinkley Sargent Architects
A901 INTERIOR ELEVATIONS 8/29/2016 Brinkley Sargent Architects
A902 INTERIOR ELEVATIONS 8/29/2016 Brinkley Sargent Architects
6
Round Rock Public Safety Training Facility GMP Cost Estimate
A903 INTERIOR ELEVATIONS 8/29/2016 Brinkley Sargent Architects
A904 INTERIOR ELEVATIONS 8/29/2016 Brinkley Sargent Architects
A905 INTERIOR ELEVATIONS 8/29/2016 Brinkley Sargent Architects
A921 MILLWORK SECTIONS 8/29/2016 Brinkley Sargent Architects
A922 MILLWORK SECTIONS 8/29/2016 Brinkley Sargent Architects
A923 MILLWORK SECTIONS-LOBBY 8/29/2016 Brinkley Sargent Architects
M101 SCHEDULES, NOTES,&LEGENDS-MECHANICAL 8/29/2016 Hendrix Consulting Engineers
M102 SCHEDULES-MECHANICAL 8/2912016 Hendrix Consulting Engineers
M103 SCHEDULES-MECHANICAL 8/29/2016 Hendrix Consulting Engineers
M104 SCHEDULES-MECHANICAL 8/29/2016 Hendrix Consulting Engineers
M105 SCHEDULES-MECHANICAL 8/29/2016 Hendrix Consulting Engineers
M106 PIPING DIAGRAM 8/29/2016 Hendrix Consulting Engineers
M107 PIPING AND WIRING DIAGRAM 8/29/2016 Hendrix Consulting Engineers
M108 WIRING DIAGRAM 8/29/2016 Hendrix Consulting Engineers
M109 PIPING DIAGRAM 8/29/2016 Hendrix Consulting Engineers
M110 PIPING AND WIRING DIAGRAM 8/29/2016 Hendrix Consulting Engineers
M111 WIRING DIAGRAM 8/29/2016 Hendrix Consulting Engineers
M112 PIPING AND WIRING DIAGRAMS 8/29/2016 Hendrix Consulting Engineers
M113 KITCHEN HOOD INFORMATION 8/29/2016 Hendrix Consulting Engineers
M114 KITCHEN HOOD INFORMATION 8/29/2016 Hendrix Consulting Engineers
M115 KITCHEN HOOD INFORMATION 8/29/2016 Hendrix Consulting Engineers
M116 KITCHEN HOOD INFORMATION 8/29/2016 Hendrix Consulting Engineers
M117 KITCHEN HOOD INFORMATION 8/29/2016 Hendrix Consulting Engineers
Ml 18 DETAILS-MECHANICAL 8/29/2016 Hendrix Consulting Engineers
M119 DETAILS-MECHANICAL 8/29/2016 Hendrix Consulting Engineers
M211 FLOOR PLAN-AREA A-MECHANICAL 8/29/2016 Hendrix Consulting Engineers
M212 FLOOR PLAN-AREA B-MECHANICAL 8/29/2016 Hendrix Consulting Engineers
M213 FIRING RANGE COORDINATION-MECHANICAL 8/29/2016 Hendrix Consulting Engineers
M311 MECHANICAL SECTION REFERENCE PLAN 8/29/2016 Hendrix Consulting Engineers
M312 MECHANICAL SECTIONS 8/29/2016 Hendrix Consulting Engineers
M313 MECHANICAL SECTIONS 8/29/2016 Hendrix Consulting Engineers
M314 MECHANICAL SECTIONS 8/29/2016 Hendrix Consulting Engineers
E101 SCHEDULES, NOTES,&LEGENDS-ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
E102 SCHEDULES-ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
E103 SCHEDULES-ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
E104 SCHEDULES-ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
E105 SCHEDULES-ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
E106 SCHEDULES-ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
E107 SCHEDULES-ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
E108 DETAILS-ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
EL211 FLOOR PLAN-AREA A-LIGHTING 8/29/2016 Hendrix Consulting Engineers
EL212 FLOOR PLAN-AREA B-LIGHTING 8/29/2016 Hendrix Consulting Engineers
EL213 FLOOR PLAN-AREA C-LIGHTING 8/29/2016 Hendrix Consulting Engineers
EP211 FLOOR PLAN-AREA A-POWER 8/29/2016 Hendrix Consulting Engineers
EP212 FLOOR PLAN-AREA B-POWER 8/29/2016 Hendrix Consulting Engineers
EP212 FLOOR PLAN-AREA C-POWER 8/29/2016 Hendrix Consulting Engineers
7
Round Rock Public Safety Training Facility GMP Cost Estimate
EP411 ROOF PLAN-ELECTRICAL 8/29/2016 Hendrix Consulting Engineers
P101 SCHEDULES, NOTES&LEGENDS-PLUMBING 8/29/2016 Hendrix Consulting Engineers
P102 DETAILS-PLUMBING 8/29/2016 Hendrix Consulting Engineers
P103 DETAILS-PLUMBING 8/29/2016 Hendrix Consulting Engineers
P211 FLOOR PLAN-AREA A-PLUMBING 8/29/2016 Hendrix Consulting Engineers
P212 FLOOR PLAN-AREA B-PLUMBING 8/29/2016 Hendrix Consulting Engineers
P213 FLOOR PLAN-AREA C-PLUMBING 8/29/2016 Hendrix Consulting Engineers
P411 ROOF PLAN-PLUMBING 8/29/2016 Hendrix Consulting Engineers
T001 LEGEND AND NOTES-COMMUNICATIONS 8/29/2016 Datacom Design Group
T212 FLOOR PLAN-AREA'A'-COMMUNICATIONS 8/29/2016 Datacom Design Group
T213 FLOOR PLAN-AREA'B'-COMMUNICATIONS 8/29/2016 Datacom Design Group
T301 TELECOM ROOM-COMMUNICATIONS 8/29/2016 Datacom Design Group
T302 TELECOM ROOM-COMMUNICATIONS 8/29/2016 Datacom Design Group
T303 AV ROOM-COMMUNICATIONS 8/29/2016 Datacom Design Group
T401 GENERAL DETAILS-COMMUNICATIONS 8/29/2016 Datacom Design Group
SC101 SECURITY DRAWING-FLOOR PLAN LEVEL(ACCESS 8/29/2016 Datacom Design Group
CONTROL)
SC102 SECURITY DRAWING-FLOOR PLAN LEVEL 1 (VIDEO 8/29/2016 Datacom Design Group
SURVEILLANCE)
Volume 3
Sheet Title Issue Date Issued By
CVR3 VOLUME 3-COVER 8/29/2016
S001 GENERAL NOTES 8/29/2016 Hart, Gaugler and Associates
S211 POLICE TACTICAL BUILDING 21 FOUNDATION PLAN 8/29/2016 Hart, Gaugler and Associates
S212 POLICE TACTICAL BUILDING 21 ROOF FRAMING PLAN 8/29/2016 Hart, Gaugler and Associates
3311 POLICE TACTICAL BUILDING 22 FOUNDATION PLAN 8/29/2016 Hart, Gaugler and Associates
S312 POLICE TACTICAL BUILDING 22 ROOF FRAMING PLAN 8/29/2016 Hart, Gaugler and Associates
S411 POLICE TACTICAL BUILDING 23 FOUNDATION PLAN 8/29/2016 Hart,Gaugler and Associates
S412 POLICE TACTICAL BUILDING 23 FLOOR&ROOF FRAMING 8/29/2016 Hart,Gaugler and Associates
PLAN
S511 POLICE TACTICAL BUILDING 24&25 FOUNDATION PLAN 8/29/2016 Hart, Gaugler and Associates
S512 POLICE TACTICAL BUILDING 24&25 FLOOR&ROOF 8/29/2016 Hart, Gaugler and Associates
FRAMING PLAN
S611 POLICE TACTICAL BUILDING 26 FOUNDATION PLAN 8/29/2016 Hart, Gaugler and Associates
S612 POLICE TACTICAL BUILDING 26 ROOF FRAMING PLAN 8/29/2016 Hart, Gaugler and Associates
S711 SHARED STORAGE BUILDING 31 FOUNDATION PLAN 8/29/2016 Hart, Gaugler and Associates
S712 SHARED STORAGE BUILDING 31 ROOF FRAMING PLAN 8/29/2016 Hart, Gaugler and Associates
S800 FOUNDATION DETAILS 8/29/2016 Hart, Gaugler and Associates
S901 ROOF FRAMING DETAILS 8/29/2016 Hart, Gaugler and Associates
A000 TEXAS ACCESSIBILITY STANDARDS 8/29/2016 Brinkley Sargent Architects
A031 CODE PLAN- BLDG 31 8/29/2016 Brinkley Sargent Architects
A221 PLANS AND ELEVATIONS-BLDG 21 8/29/2016 Brinkley Sargent Architects
A261 BUILDING SECTIONS-BLDG 21 8/29/2016 Brinkley Sargent Architects
A321 PLANS AND ELEVATIONS-BLDG 22 8/29/2016 Brinkley Sargent Architects
A361 BUILDING SECTIONS-BLDG 22 8/29/2016 Brinkley Sargent Architects
A421 FLOOR PLANS/REFLECTED CEILING PLANS-BLDG 23 8/29/2016 Brinkley Sargent Architects
A431 STAIR PLANS/STAIR SECTIONS-BLDG 23 8/29/2016 Brinkley Sargent Architects
A451 BUILDING ELEVATIONS&AXONS-BLDG 23 8/29/2016 Brinkley Sargent Architects
A461 BUILDING SECTIONS-BLDG 23 8/29/2016 Brinkley Sargent Architects
8
Round Rock Public Safety Training Facility GMP Cost Estimate
A521 FLOOR PLANS/RCP&ROOF PLAN-BLDGS 24&25 8/29/2016 Brinkley Sargent Architects
A531 STAIR PLANS/STAIR SECTIONS-BLDGS 24&25 8/29/2016 Brinkley Sargent Architects
A551 BUILDING ELEVATIONS&AXONS-BLDGS 24&25 8/29/2016 Brinkley Sargent Architects
A561 BUILDING SECTIONS-BLDGS 24&25 8/29/2016 Brinkley Sargent Architects
A621 FLOOR PLAN/RCP&ROOF PLAN-BLDG 26 8/29/2016 Brinkley Sargent Architects
A651 BUILDING ELEVATIONS&AXONS-BLDG 26 8/29/2016 Brinkley Sargent Architects
A661 BUILDING SECTIONS-BLDG 26 8/29/2016 Brinkley Sargent Architects
A721 FLOOR PLAN/RCP&ROOF PLAN-BLDG 31 8/29/2016 Brinkley Sargent Architects
A751 BUILDING ELEVATIONS&AXONS-BLDG 31 8/29/2016 Brinkley Sargent Architects
A761 BUILDING SECTIONS-BLDG 31 8/29/2016 Brinkley Sargent Architects
A791 INTERIOR ELEVATIONS&MILLWORK SECTIONS-BLDG 31 8/29/2016 Brinkley Sargent Architects
A811 ROOF DETAILS 8/29/2016 Brinkley Sargent Architects
A821 PLAN&SECTION DETAILS 8/29/2016 Brinkley Sargent Architects
A841 DOOR SCHEDULE, DOOR TYPES, PARTITION TYPES 8/29/2016 Brinkley Sargent Architects
A842 DOOR DETAILS 8/29/2016 Brinkley Sargent Architects
EP221 FLOOR PLANS-BLDGS 21-26-ELECTRICAL AND PLUMBING 8/29/2016 Hart, Gaugler and Associates
EPS211 FLOOR PLAN-SHARED-ELECTRICAL 8/29/2016 Hart,Gaugler and Associates
PS211 FLOOR PLAN -SHARED-PLUMBING 8/29/2016 Hart,Gaugler and Associates
Volume 4
Sheet Title Issue Date Issued By
CVR4 VOLUME 4-COVER 8/29/2016
S001 GENERAL NOTES 8/29/2016 Hart, Gaugler and Associates
S111 APARTMENT BUILDING 43 FOUNDATION PLAN 8/29/2016 Hart, Gaugler and Associates
S112 APARTMENT BUILDING 43 FLOOR FRAMING PLANS 8/29/2016 Hart, Gaugler and Associates
S121 WAREHOUSE BUILDING 42 FOUNDATION PLAN 8/29/2016 Hart,Gaugler and Associates
S122 WAREHOUSE BUILDING 42 FLOOR FRAMING PLANS 8/29/2016 Hart, Gaugler and Associates
S123 WAREHOUSE BUILDING 42 HIGH ROOF FRAMING PLAN 8/29/2016 Hart,Gaugler and Associates
S131 HOUSE BUILDING 44 FOUNDATION PLAN 8/29/2016 Hart, Gaugler and Associates
S132 HOUSE BUILDING 44 FLOOR&ROOF FRAMING PLANS 8/29/2016 Hart, Gaugler and Associates
S141 TOWER BUILDING 41 FOUNDATION AND FLOOR FRAMING 8/29/2016 Hart, Gaugler and Associates
PLANS
S142 TOWER BUILDING 41 FLOOR FRAMING PLANS 8/29/2016 Hart, Gaugler and Associates
S151 CONFINED SPACE TRENCH RESCUE BUILDING 45 8/29/2016 Hart,Gaugler and Associates
FOUNDATION PLAN
S301 FOUNDATION DETAILS 8/29/2016 Hart,Gaugler and Associates
S302 FOUNDATION DETAILS 8/29/2016 Hart,Gaugler and Associates
S303 FOUNDATION DETAILS 8/29/2016 Hart,Gaugler and Associates
S401 FRAMING DETAILS 8/29/2016 Hart,Gaugler and Associates
A211 TOWER SITE PLAN BLDG.41 8/29/2016 G2 Solutions Group, Inc.
A221 1 ST THRU ROOF FLOOR PLANS BLDG.41 8/29/2016 G2 Solutions Group, Inc.
A222 1ST THRU ROOF SLOPE&DRAINAGE PLANS BLDG.41 8/29/2016 G2 Solutions Group, Inc.
A223 1ST THROUGH ROOF DIMENSION PLANS BLDG.41 8/29/2016 G2 Solutions Group, Inc.
A224 1ST THRU 5TH FLOOR REFLECTED CEILING PLANS BLDG. 8/29/2016 G2 Solutions Group, Inc.
41
A231 ENLARGED FLOOR PLANS BLDG.41 8/29/2016 G2 Solutions Group, Inc.
A232 ENLARGED STAIR PLANS BLDG.41 8/29/2016 G2 Solutions Group, Inc.
A241 ROOF PLAN BLDG.41 8/29/2016 G2 Solutions Group, Inc.
A251 EXTERIOR BUILDING ELEVATIONS BLDG.41 8/29/2016 G2 Solutions Group, Inc.
9
Round Rock Public Safety Training Facility GMP Cost Estimate
A261 BUILDING SECTIONS BLDG.41 8/29/2016 G2 Solutions Group, Inc.
A271 INTERIOR ELEVATIONS BLDG.41 8/29/2016 G2 Solutions Group, Inc.
A281 DOOR,WINDOW&FINISH SCHEDULES BLDG.41 8/29/2016 G2 Solutions Group, Inc.
A291 ISOMETRIC VIEWS BLDG.41 8/29/2016 G2 Solutions Group, Inc.
A311 WAREHOUSE SITE PLAN BLDG.42 8/29/2016 G2 Solutions Group, Inc.
A321 1ST&2ND FLOOR PLANS BLDG.42 8/29/2016 G2 Solutions Group, Inc.
A322 1 ST&2ND FLOOR SLOPE&DRAINAGE PLANS BLDG.42 8/29/2016 G2 Solutions Group, Inc.
A323 IST&2ND FLOOR DIMENSION PLANS BLDG.42 8/29/2016 G2 Solutions Group, Inc.
A324 IST&2ND FLOOR REFLECTED CEILING PLANS BLDG.42 8/29/2016 G2 Solutions Group, Inc.
A331 ENLARGED FLOOR PLANS BLDG.42 8/29/2016 G2 Solutions Group, Inc.
A332 ENLARGED STAIR PLANS BLDG.42 8/29/2016 G2 Solutions Group, Inc.
A341 ROOF DRAINAGE PLAN& ROOF PLAN BLDG.42 8/29/2016 G2 Solutions Group, Inc.
A351 EXTERIOR BUILDING ELEVATIONS BLDG.42 8/29/2016 G2 Solutions Group, Inc.
A361 BUILDING SECTIONS BLDG.42 8/29/2016 G2 Solutions Group, Inc.
A371 INTERIOR ELEVATIONS BLDG.42 8/29/2016 G2 Solutions Group, Inc.
A381 DOOR,WINDOW&FINISH SCHEDULES BLDG.42 8/29/2016 G2 Solutions Group, Inc.
A391 ISOMETRIC VIEWS BLDG.42 8/29/2016 G2 Solutions Group, Inc.
A411 APARTMENT SITE PLAN BLDG.43 8/29/2016 G2 Solutions Group, Inc.
A421 1ST&2ND FLOOR PLANS BLDG.43 8/29/2016 G2 Solutions Group, Inc.
A422 1ST&2ND FLOOR SLOPE&DRAINAGE PLANS BLDG.43 8/29/2016 G2 Solutions Group, Inc.
A423 1ST&2ND FLOOR DIMENSION PLANS BLDG.43 8/29/2016 G2 Solutions Group, Inc.
A424 1ST&2ND FLOOR REFLECTED CEILING PLANS BLDG.43 8/29/2016 G2 Solutions Group, Inc.
A431 ENLARGED FLOOR PLANS BLDG.43 8/29/2016 G2 Solutions Group, Inc.
A432 ENLARGED STAIR PLANS BLDG.43 8/29/2016 G2 Solutions Group, Inc.
A441 ROOF PLAN &ROOF SLOPE&DRAINAGE PLAN BLDG.43 8/29/2016 G2 Solutions Group, Inc.
A451 EXTERIOR BUILDING ELEVATIONS BLDG.43 8/29/2016 G2 Solutions Group, Inc.
A461 BUILDING SECTIONS BLDG.43 8/29/2016 G2 Solutions Group, Inc.
A471 INTERIOR ELEVATIONS BLDG.43 8/29/2016 G2 Solutions Group, Inc.
A481 DOOR,WINDOW, &FINISH SCHEDULES BLDG.43 8/29/2016 G2 Solutions Group, Inc.
A491 ISOMETRIC VIEWS BLDG.43 8/29/2016 G2 Solutions Group, Inc.
A511 HOUSE SITE PLAN BLDG.44 8/29/2016 G2 Solutions Group, Inc.
A521 1ST&2ND FLOOR PLANS BLDG.44 8/29/2016 G2 Solutions Group, Inc.
A522 1ST&2ND FLOOR SLOPE&DRAINAGE PLANS BLDG.44 8/29/2016 G2 Solutions Group, Inc.
A523 IST&2ND FLOOR DIMENSION PLANS BLDG.41 8/29/2016 G2 Solutions Group, Inc.
A524 IST&2ND FLOOR REFLECTED CEILING PLANS BLDG.44 8/29/2016 G2 Solutions Group, Inc.
A531 ENLARGED FLOOR&STAIR PLANS BLDG.44 8/29/2016 G2 Solutions Group, Inc.
A541 ROOF PLAN BLDG.44 8/29/2016 G2 Solutions Group, Inc.
A551 EXTERIOR BUILDING ELEVATIONS BLDG.44 8/29/2016 G2 Solutions Group, Inc.
A561 BUILDING SECTIONS BLDG.44 8/29/2016 G2 Solutions Group, Inc.
A571 INTERIOR ELEVATIONS BLDG.44 8/29/2016 G2 Solutions Group, Inc.
A581 DOOR,WINDOW&FINISH SCHEDULES BLDG.44 8/29/2016 G2 Solutions Group, Inc.
A591 ISOMETRIC VIEWS BLDG.44 8/29/2016 G2 Solutions Group, Inc.
A811 ROOF DETAILS 8/29/2016 G2 Solutions Group, Inc.
A812 ROOF DETAILS 8/29/2016 G2 Solutions Group, Inc.
A821 WALL DETAILS 8/29/2016 G2 Solutions Group, Inc.
A831 EXTERIOR DETAILS 8/29/2016 G2 Solutions Group, Inc.
t
10
Round Rock Public Safety Training Facility GMP Cost Estimate
A841 INTERIOR DETAILS 8/29/2016 G2 Solutions Group, Inc.
A842 INTERIOR DETAILS 8/29/2016 G2 Solutions Group, Inc.
A845 DOOR DETAILS 8/29/2016 G2 Solutions Group, Inc.
A846 DOOR DETAILS 8/29/2016 G2 Solutions Group, Inc.
A847 WINDOW DETAILS 8/29/2016 G2 Solutions Group, Inc.
EPA211 FLOOR PLAN-APARTMENT-ELECTRICAL AND PLUMBING 8/29/2016 G2 Solutions Group, Inc.
EPH211 FLOOR PLAN-HOUSE-ELECTRICAL AND PLUMBING 8/29/2016 G2 Solutions Group, Inc.
EPT211 FLOOR PLAN-TOWER-ELECTRICAL AND PLUMBING 8/29/2016 G2 Solutions Group, Inc.
EPW211 FLOOR PLAN-WAREHOUSE-ELECTRICAL AND PLUMBING 8/29/2016 G2 Solutions Group, Inc.
Volume 5
Sheet Title Issue Date Issued BV
CVR5 VOLUME 5-COVER 8/29/2016
AVIO01 LEGENDS AND NOTES-INFRASTRUCTURE AUDIO VISUAL 8/26/2016 Datacom Design Group
AV1212 FLOOR PLAN-AREA W-INFRASTRUCTURE AUDIO VISUAL 8/26/2016 Datacom Design Group
AV1213 FLOOR PLAN-AREA'B'-INFRASTRUCTURE AUDIO VISUAL 8/26/2016 Datacom Design Group
AV1312 RCP-AREA'A'-INFRASTRUCTURE AUDIO VISUAL 8/26/2016 Datacom Design Group
AVI313 RCP-AREA'B'-INFRASTRUCTURE AUDIO VISUAL 8/26/2016 Datacom Design Group
AV1401 GENERAL DETAILS-INFRASTRUCTURE AUDIO VISUAL 8/26/2016 Datacom Design Group
AV1402 GENERAL DETAILS-INFRASTRUCTURE AUDIO VISUAL 8/26/2016 Datacom Design Group
AVS403 AUDIO VISUAL ONE-LINE DETAILS 8/26/2016 Datacom Design Group
AVS404 AUDIO VISUAL ONE-LINE DETAILS 8/26/2016 Datacom Design Group
SPECIFICATIONS—1395 Pages 8/29/2016 Brinkley Sargent Architects
GEOTECHNICAL REPORT—64 Pages 8/31/2015 Rock Engineering&Testing
Laboratory, Inc.
Addendum A
Volume 1
C1.06 ENLARGED DETAILS 9/2/2016 Hart, Gaugler and Associates
C1.09 TRENCH RESCUE DETAIL 9/2/2016 Hart,Gaugler and Associates
C3.00 GRADING PLAN 9/2/2016 Hart, Gaugler and Associates
C3.03 GRADING ENLARGED PLAN 9/2/2016 Hart, Gaugler and Associates
C3.04 GRADING ENLARGED PLAN 9/2/2016 Hart, Gaugler and Associates
C6.01 CONSTRUCTION DETAILS 9/2/2016 Hart, Gaugler and Associates
Volume 3
S211 POLICE TACTICAL BUILDING 21 FOUNDATION PLAN 9/1/2016 Hart, Gaugler and Associates
S311 POLICE TACTICAL BUILDING 22 FOUNDATION PLAN 9/1/2016 Hart, Gaugler and Associates
S411 POLICE TACTICAL BUILDING 23 FOUNDATION PLAN 9/1/2016 Hart, Gaugler and Associates
S511 POLICE TACTICAL BUILDING 24&25 FOUNDATION PLAN 9/1/2016 Hart, Gaugler and Associates
S611 POLICE TACTICAL BUILDING 26 FOUNDATION PLAN 9/1/2016 Hart,Gaugler and Associates
S711 SHARED STORAGE BUILDING 31 FOUNDATION PLAN 9/1/2016 Hart,Gaugler and Associates
S712 SHARED STORAGE BUILDING 31 ROOF FRAMING PLAN 9/1/2016 Hart,Gaugler and Associates
S800 FOUNDATION DETAILS 9/1/2016 Hart,Gaugler and Associates
S901 ROOF FRAMING DETAILS 9/1/2016 Hart,Gaugler and Associates
Volume 4
3001 GENERAL NOTES 9/2/2016 Hart,Gaugler and Associates
S111 APARTMENT BUILDING 43 FOUNDATION PLAN 9/2/2016 Hart, Gaugler and Associates
S112 APARTMENT BUILDING 43 FLOOR FRAMING PLANS 9/212016 Hart,Gaugler and Associates
S121 WAREHOUSE BUILDING 42 FOUNDATION PLAN 9/2/2016 Hart,Gaugler and Associates
11
Round Rock Public Safety Training Facility GMP Cost Estimate
S122 WAREHOUSE BUILDING 42 FLOOR FRAMING PLANS 9/2/2016 Hart, Gaugler and Associates
S123 WAREHOUSE BUILDING 42 HIGH ROOF FRAMING PLAN 9/2/2016 Hart, Gaugler and Associates
S131 HOUSE BUILDING 44 FOUNDATION PLAN 9/2/2016 Hart, Gaugler and Associates
S132 HOUSE BUILDING 44 FLOOR&ROOF FRAMING PLANS 9/2/2016 Hart, Gaugler and Associates
S141 TOWER BUILDING 41 FOUNDATION AND FLOOR FRAMING 9/2/2016 Hart, Gaugler and Associates
PLANS
S142 TOWER BUILDING 41 FLOOR FRAMING PLANS 9/2/2016 Hart, Gaugler and Associates
S151 CONFINED SPACE TRENCH RESCUE BUILDING 45 9/2/2016 Hart, Gaugler and Associates
FOUNDATION PLAN
S301 FOUNDATION DETAILS 9/2/2016 Hart, Gaugler and Associates
S302 FOUNDATION DETAILS 9/2/2016 Hart, Gaugler and Associates
S303 FOUNDATION DETAILS 9/2/2016 Hart, Gaugler and Associates
S401 FRAMING DETAILS 9/2/2016 Hart,Gaugler and Associates
A521 1ST, 2ND&ATTIC FLOOR PLANS BLDG.44 9/2/2016 G2 Solutions Group, Inc.
A524 1ST&2ND FLOOR REFLECTED CEILING PLANS BLDG.44 9/2/2016 G2 Solutions Group, Inc.
Addendum B
Volume 1
CVR1 VOLUME 1 -COVER 9/7/2016
Volume 2
CVR2 VOLUME 2-COVER 9/7/2016
S101 FOUNDATION DETAILS 917/2016 Hart,Gaugler and Associates
S303 FOUNDATION DETAILS 9/7/2016 Hart, Gaugler and Associates
A211 REFERENCE PLAN 91712016 Hart, Gaugler and Associates
A214 FLOOR PLAN-AREA'A'-EQUIPMENT, INTERIOR 9/7/2016 Hart, Gaugler and Associates
ELEVATIONS
A401 BUILDING ELEVATIONS 9/7/2016 Hart, Gaugler and Associates
A524 SECTION DETAILS 9[7/2016 Hart, Gaugler and Associates
Volume 3
CVR3 VOLUME 3-COVER 9[7/2016
S001 GENERAL NOTES 9/7/2016 Hart, Gaugler and Associates
S901 ROOF FRAMING DETAILS 9/7/2016 Hart, Gaugler and Associates
MS211 FLOOR PLAN-SHARED-MECHANICAL 9/7/2016 Hart, Gaugler and Associates
Volume 4
CVR4 VOLUME 4-COVER 9/7/2016
A812 ROOF DETAILS 917/2016 G2 Solutions Group, Inc.
Volume 5
CVR5 VOLUME 5-COVER 917/2016
Addendum C
Volume 2
A811 FINISH LEGEND AND NOTES 9/12/2016 Brinkley Sargent Architects
A812 FINISH PLAN Brinkley Sargeht Architects
M102 SCHEDULES-MECHANICAL 9/12/2016 Hart, Gaugler and Associates
M103 SCHEDULES-MECHANICAL Hart,Gaugler and Associates
M211 FLOOR PLAN-AREA A-MECHANICAL Hart, Gaugler and Associates
M212 FLOOR PLAN-AREA B-MECHANICAL Hart,Gaugler and Associates
Addendum D
Volume 2
A702 DOOR SCHEDULE DOOR TYPES 9/15/2016 Brinkley Sargent Architects
12
Round Rock Public Safety Training Facility GIVIP Cost Estimate
B. General Requirements
Design Services
■ Architectural and Engineering design services are excluded
■ Geotechnical Engineering and soils analysis reports are excluded
Supervision and Administration
■ Project supervision includes a Project Superintendent with Project Management, Safety
Coordinator, Estimating, and Administrative Assistant as necessary to complete the
project as scheduled
■ Document Reproduction as required for shop drawings
■ Postage and delivery services
Temporary Facilities
■ Project field office
■ Project office supplies
■ Project office equipment as required
■ Project sign and safety signs
■ Temporary toilets
■ Site fencing and gates
■ Barricades and guard rails as required
Proiect Services
■ Field engineering and layout
■ General cleanup and trash haul off
■ Final cleaning
■ After hours or weekend job site security is not included in our price
Personnel Hoisting
■ None required for this project
Temporary Utilities
■ Field telephone service
■ Project electrical service
Equipment
■ Project pickup trucks
■ Expendable tools
■ Small equipment rental
Permits, Bonds, and Insurance
■ The cost of all site and building permits is excluded in the budget
■ Mechanical, Electrical, & Plumbing trade permits are included
13
Round Rock Public Safety Training Facility GMP Cost Estimate
■ Plan review Fees are excluded
■ Price excludes Utility connection fees, Impact fees, and Assessment fees
■ General Liability, Auto, Worker Compensation, and Builders Risk Insurance are included
■ The price includes the cost of performance and payment bonds
Project Schedule, Weather, and Work Hours
Schedule
■ The Project Schedule will include pre-construction and construction activities and when
fully developed will serve as the basis for the time required to complete the project
Work Hours
■ Normal working days are Monday through Friday, excluding holidays. Work may take
place at night or on weekends as coordinated with the Owner
Environmental
■ We have assumed that all environmental investigations and permits will be accomplished
and paid for by the Owner if required
■ The handling or abatement of hazardous materials is not included in this estimate
Building Inspections
■ Inspections will be provided as required by local jurisdiction
Jobsite Equipment
■ Scaffolding and hoisting for construction access
■ Equipment for excavation, structural steel, and concrete construction
■ Small tools and equipment as required by trade
Layout & Engineering
■ Layout and engineering as required
Materials Testing
■ The cost of materials testing is to be by the Owner. The cost of re-testing due to test
failures shall be by the Construction Manager
BIM CAD Coordination
■ Layout and CAD services for construction as required
Temporary Power and Lighting
■ Price includes electrical power consumption and temporary lighting required for construction.
Electrical service costs shall be transferred to the Owner when permanent power is hooked
up and operational
14
Round Rock Public Safety Training Facility GMP Cost Estimate
C. Buildings & Training Areas in Base Budget
11) Main Building
General Description
65,345sf single story building, slab on grade with piers, combination of tilt walls to 25' and stud
framing to 30', structural steel, low slope TPO roof, standard office finishes, fire sprinkled
Site Layout, BIM/CAD As-Built Coordination
■ Layout all site work and CAD services for construction
Temporary Power and Lighting
• Temporary power and lighting
■ Construction power
Mock-Up Panel
■ Allow the sum of$30,000 for a Mock-Up panel per the project documents
Project Equipment
e Skytrack/heavy moving equipment
Items Excluded in Original RFP
• Field engineering 10 wk
■ Small tools 65,345 sf
• Ice, water, and cups 8 mo
■ Waste containers 38 ea
• General clean up 52 wk
■ Plan reproduction 1 Is
■ As built drawings 1 Is
■ Final cleaning 65,345 sf
Fencinq
Interior fencing and gates
Building Pads
• Select fill building pad
• Subgrade prep
Landscaping & Irrigation
• Trees
• Ornamental trees
• Shrubs and Groundcovers
® Lawn - Bermuda Grass, Hydromulch and 4" deep topsoil
15
Round Rock Public Safety Training Facility GMP Cost Estimate
■ Miscellaneous materials
• Irrigation system
Building Concrete
■ Drilled piers
■ Fine grade slabs
■ Grade beams
■ Vapor barrier
■ Form slabs
■ Concrete slab on grade
■ Anchor bolt assemblies
■ Rebar
■ Sawcut
• Steps and ramps
■ Tiered floor areas in Classrooms
■ Termite control
® Pier Unit Prices plus and minus from embedment depth in documents:
24" dia. Add $52/ If and Deduct$10.00 / If
30" dia. Add $69/ If and Deduct$13.00 / If
36" dia. Add $87/ If and Deduct$17.00 / If
Tilt Wall Concrete
• All insulated and non-insulated tilt-wall panels
■ Integral color at tilt wall panels where required
• Form.liners
• Installation of all structural and miscellaneous embeds (furnished by others)
■ Tilt-wall braces including rental, installation to wall panels prior to erection and removal after
erection
■ Panel layout and lifting assistance
■ Panel shimming and grouting
■ Engineered panel drawings
• All reinforcing materials including masonry reinforcing
■ Lifting and bracing insert materials and installation
• Stiff backs and lifting rebar
• Clean and patch tilt-walls after erection
Masonry
■ CMU block as per plans and specifications
■ Mortars as specified
■ Reinforced unit masonry
■ Joint reinforcement
• Grout
• Bond beams
■ Reinforcing steel
• Masonry anchors
• Weeps & Control joints
• Mock-up panels as specified
• Clean down of masonry
16
Round Rock Public Safety Training Facility GMP Cost Estimate
Structural and Miscellaneous Steel
■ Fabricate steel
■ Erect steel
■ Erect Decking
■ Erect tilt-wall panels
■ Columns
■ Beams
■ Architectural steel
• Anchor bolt assemblies
• Beam seats
• Studs
■ Channels
• Concrete embeds
■ Tilt-wall embeds
■ Pour stops
■ Joist seats
■ Joist and bridging
■ Joist and bridging anchors
■ Roof deck
• Roof ladders
• Operable partition support framing
■ Bolts &fasteners for structural/misc. Steel
■ Roof opening frames
■ Misc. Angles, plate, tube & channel
■ Countertop support brackets
• All required anchor bolts, expansion bolts and other required fasteners
■ All bollards at the site and all handrails at site steps as shown on civil drawings
• Metal grates and frames
■ All materials shall either be prime finished or galvanized as indicted and/or specified
• Includes a $50,000 allowance for Miscellaneous steel items not specifically identified or sized
■ Includes staircase with roof hatch or pulley system for taking filters up to roof at Range
Finish Carpentry, Cabinets and Countertops
■ Millwork
• Engineered stone tops
■ Additional custom millwork at Reception
■ Stainless steel countertops
• Butcher Block top
• Metal Panels MWP1
• Metal Panels MWP2
• Metal Panels MWP3
■ Precast concrete counter at Lobby Reception
17
Round Rock Public Safety Training Facility GMP Cost Estimate
Waterproofing, Dampproofing, Caulking & Sealants
■ Fluid-Applied Weather Barrier behind metal panels
• Sealant at both sides of tilt-wall panel joints
■ Polyurethane sealant at slab-on-grade control joints
■ Sealant at chamfer joint at top of insulated panels per 5/A521
Roofing and Sheet Metal
• Firestone Thermoplastic Polyolefin (TPO) Roofing — Main Building
• Install two (1) layers of 2.5" polyiso, mechanically fastened, with a 1/2" Isogard cover board
with polyisocya n u rate crickets, adhered with low-rise foam insulation adhesive
• Install a 60 mil TPO white membrane fully adhered to field of roof and parapet walls
• Install required TPO walk pads at roof hatches and roof access ladders only
• Fabricate and install TPO coated metal scuppers. (Shop Fabricated)
• Fabricate and install 24 ga. prefinished copings, conductor boxes, downspouts,visible counter
flashings, and edge metal. (Shop Fabricated)
■ Fabricate and install 24 ga. galvanized non-visible counter flashing at siding walls. (Shop
Fabricated)
■ Furnish and install two(2)48"x 96"steel roof hatches with aluminum covers per Spec.Section
77200 with safety guard rail systems
• TPO Manufacturer's 15 Year Warranty
• 2 Year Workmanship Warranty
■ Corrugated Metal Roofing and Siding — Main Building
• Furnish and install Morin 22 gauge prefinished"BR-28"MP-4 corrugated panels with matching
trim and flashings at Entry Canopy and small canopy on South Elevation of Main Building per
Spec. Section 074213
• Furnish and install Dri-Design MP-1, MP-2, MP-3, and MP-5 over a 2"foil faced rigid insulation
with sub-framing (insulation, weather barrier and sub-framing by others) and matching trim
per Spec. Section 074213
• Furnish and install MBCI 20 gauge prefinished "FW-120 Flush Panels" MP-6 at equipment
screen with matching trim and sub-framing per Spec. Section 074213. These panels quoted
with standard factory colors only
• Furnish and install Morin X-16 .040"prefinished perforated panels on Sun Shades on the West
Elevation of the Main Building. Sun Shade frames by steel contractor
■ 2 Year Workmanship Warranty
• Commissioning requirements as specified
Doors, Frames, and Hardware
• Hollow metal door leaves 37 ea
■ Hollow metal frames 79 ea
■ Plam door eaves 49 ea
• Hardware 107 ea
• Security Hardware 1 Is
• Install doors & hdw 1 Is
• Handle & Sort Doors, Frames & Hdw. 107 ea
18
Round Rock Public Safety Training Facility GMP Cost Estimate
Coiling and Overhead Doors
■ Fire Apparatus Bay Doors Model 521
■ Aluminum clear anodized, Low E glass, One row only
■ Insulated aluminum panels, Perimeter seals, Electric operation, Qty. 4 Doors# 1501A,B,C,D-
14'x14'
■ Insulated Thermacore Model 592, Factory standard finish
Y Door41105A-10'X10'-Manual push up
■ 1502C- 10'X10'-Motor operated
• 1504C, 1504D -10'X14'-Motor operated
Model 627 Insulated coiling doors
o Door# 16098-10'X10' Motor operated
Y #1612A, 1612B -12'X12' Manual operated
0 #1615B-8'X8'- Manual operated
#1611A-6'X8' Non Insulated- Motor Operated
■ #1611 C-1 0'X8'Non Insulated Manual operated
■ 1- Dock leveler Equal to RiteHite RHM. Mechanical leveler Model WL860 by Serco. 6'x8'.
30,000 Ib capacity
■ Weather seals, 2-Dock bumpers steel wrapped, Equal to Ritehite Doksaver
Glass, Glazing and Storefronts
■ Exterior aluminum storefront systems and windows
• Exterior aluminum sunshade louvers where shown and as per detail 10/A522
® Interior aluminum storefront systems
• Interior security glazing where indicated and as specified
• Aluminum Speak-A-Round Frames at Lobby
■ Aluminum storefront doors with hardware as shown and scheduled
• All other exterior and interior glazing as shown and specified
EIFS
■ EIFS at north wall of main building
■ EIFS at Clerestory and above doors on South end wall of main building
Drywall, Insulation, and Acoustical
■ Cold formed framing
■ Drywall and metal studs
■ Thermal insulation at exterior stud framed walls
■ Exterior gyp sheathing
■ Rigid and batt insulation at tilt wall furouts and at exterior walls under metal panels
■ Zee furring for metal panels
■ Rough carpentry attached to metal studs, parapet cap, back of parapet, in wall blocking
■ Tile backer board behind ceramic tile
■ Acoustical ceilings
• Acoustic wall panels FWAP1, FWAP2, & FWAP3
• Aluminum partition Closures (Mullion Mates) i.e., A703 / 16 & 17
• Open cell specialty ceilings
® Installation only of frames in drywall partitions
■ 7/16" Ballistic Material in walls at reception desk (see Sheet A923)
19
Round Rock Public Safety Training Facility GMP Cost Estimate
• Shop drawings as required
• All rough carpentry, metal and/or wood blocking, all miscellaneous wood blocking above
ceilings and in walls for toilet partitions and accessories and other wall or ceiling mounted
items
Ceramic Tile
• Mortar beds at shower stalls only
• Laticrete 9234 waterproofing / crack suppression at all floors, shower stall walls, and toilet
walls to 4' above finish floor, extending on side walls 2' out per specifications
■ Schluter Schiene, stainless steel, metal edges strips figured at all locations as detailed and
specified
• All tile figured to be thinset or medium set type installations
■ All grout figured to be single component premium grout, no sealer required, as specified. Kraft
paper floor protection figured at all floor tile (single installation, no removal)
■ 3 % owner's attic stock included
Flooring
■ Install Shaw and Mohawk carpet tiles where specified
• Install Johnsonite rubber flooring where specified
• Install Johnsonite rubber base where specified
■ Diamond polished concrete flooring -5,776 sf
■ Sealed concrete finish -41,099 sf
Painting and Finishing
■ Painting of exterior ferrous, aluminum and galvanized metal substrates where shown and/or
specified
■ Painting of interior zinc coated and ferrous metal where shown and/or as specified
■ Painting for all exterior concrete, masonry and wood where shown
■ All interior painting and finishing as specified
■ All interior concrete, masonry and wood primers and finishing as specified on section 09 90
00
■ Tape, float and paint drywall surfaces
■ Paint hollow metal frames and doors
■ Masonry unit block surfaces fillers as indicated
■ Paint rails, stairs, exposed steel and exposed wood panel substrates
• Provide all cosmetic interior caulking and fire taping as per specifications
■ Paint graphics in Firing Range
Signage
■ Building Plaque
• Interior ADA Braille signs
• Interior firearms range rules panel signs
■ Exterior non-lit foam Police Badge sign
■ Exterior Non-Lit. Foam Fire Badge Sign
• Exterior Lit. Cast Letter Sign w/ Logo
20
Round Rock Public Safety Training Facility GMP Cost Estimate
Equipment
Peg board w/hooks (CFCI)
■ AED cabinet, coordinate relocation of AED units to new cabinets with owner(CFCI)
■ Fire extinguisher quote (CFCI)
■ Marker boards (CFCI)
■ S.S. deal tray (CFCI)
ff Pass through locker(CFCI)
■ Pallet rack(OFCI)
■ Dock Leveller(CFCI) in OH door pricing
■ Dock Bumpers (CFCI) in OH door pricing
■ Lockers (CFCI) as mfg. by ASI storage -91 ea
a Benches (CFCI) 10 ea
a Commercial range (OFCI)
■ Stainless steel back splash at range (CFCI)
■ Full size ice maker(OFCI)
■ 48" range hood (in mechanical)
O Gym wall pad (OFCI)
■ 18x18 laundry chute door(CFCI)
■ Magnetic tool holder- 24" black (OFCI)
■ 3 tier vertical ladder rack (CFCI)
■ CPAT station 1 -stair climb (OFCI)
o CPAT station 3 - equipment carry (OFCI)
a CPAT station 2 - ladder raise & extension (OFCI)
■ CPAT station 5 -forcible entry (OFCI)
■ CPAT station 6—search (OFCI)
■ CPAT station 7—rescue (OFCI)
■ CPAT station 8 -ceiling breach & pull (OFCI)
■ Ceiling mounted punching bag (OFCI)
■ Exercise rack - rogue monster m-20 (OFCI)
■ Exercise rack - rogue monster m-24 (OFCI)
■ Dumbell rack (OFCI)
■ Indoor rower(OFCI)
■ Vertical air compressor(CFCI)
Mecho shades -with motors and manual operation (CFCI)
Double crash rail (CFCI)
Wire mesh partitions at cage & enclosure 1503 (CFCI)
Knox Box
■ Knox box 2 ea
Moveable Panels
■ Moveable panels -type 1 150 ea
• Moveable panels -type 2 5 ea
■ Moveable columns 40 ea
21
Round Rock Public Safety Training Facility GMP Cost Estimate
Toilet Partitions & Accessories
• Floor mounted overhead braced solid polymer partitions with aluminum continuous brackets.
Color to be selected from manufacture standard full range color selection
■ Wall mounted urinal screens
■ Toilet accessories as scheduled
Operable Partition
• Operable Partiton 12' tall x 42' 6" by Modernfold
■ Encore 4" thick manual single panel with white steel track and storage pocket door
• STC of 54
Flagpoles
a Four(4) each flag poles with lighted becons
Elevator
■ ThyssenKrupp Elevator will furnish the necessary labor and material to install a hoistway
entrance to be used for training purposes only, which is not part of a functioning elevator
■ Scope of work includes:
■ Hoistway Door Equipment: tracks & hangers, interlocks & pickups, reel closers
■ Hoistway Entrance: frame, 2 speed center opening hoistway doors, sills, sill supports
■ Fixtures: intermediate hall lantern and chime, intermediate hall buttons
Fire Protection
■ One wet pipe fire sprinkler system and one dry pipe fire sprinkler system
• (for lead room) in Main building, fully heated, 65,000 sf
e Installation shall be in accordance with NFPA 13
• Upright sprinkler heads will be brass
• Pendants to be white semi-recessed
■ All pipe and fittings to be domestic
■ All pipe to be black schedule 40
■ All pendant heads to be Victaulic aqua flex, flexible type drops
• Rooms 1501, 1502 and 1504 to be sprinkled ordinary hazard, the rest of the main building to
be
■ light hazard
• Includes two visual inspections only
■ Commissioning requirements as specified
Plumbing
• PVC waste and vent below slab to 5' outside building line
• Cast Iron waste and vent above slab
• Copper domestic water
• Insulation of domestic water
• PVC below slab storm drain
■ Cast Iron above slab storm with HD couplings
• Black iron gas pipe
■ Gas regulators
22
Round Rock Public Safety Training Facility GMP Cost Estimate
■ Fixtures
■ Trench Drains
■ Drains and carriers
■ Fire caulk for this scope of work
■ RPZ (2)
■ PRV (2)
■ Air Pipe system
HVAC
■ Seventeen (17) Carrier RTU's with accessories
■ Two (2)Valent MAU's with accessories
■ Seven (7)Toshiba ductless split systems with accessories
■ Fourteen (14)Toshiba VRF FCU's with accessories
■ Two (2)Toshiba VRF HP's with accessories
■ Nine (9) unit heaters with accessories
■ One (1) dehumidifier with accessories
■ Eight (8) duct silencers with accessories
■ One (1)Airhawk vehicle exhaust system for Apparatus Bay with accessories
■ Vehicle exhaust system with NO2/CO sensors, control panel for AREA A vehicle bay
■ Fifteen (15) roof-mounted exhaust fans with accessories
■ One (1) inline exhaust fan with accessories
■ Eleven (11')wall-mounted oscillating fans with accessories
■ One (1) kitchen exhaust hood with fire Ansul system as per plans
■ One (1) roof-mounted kitchen exhaust fan with accessories as per plans
■ One (1) roof-mounted kitchen supply fan with accessories as per plans
■ Furnish and install associated sheet metal (supply/return/transfer) ductwork per SMACNA
standards
■ All concealed low pressure round ductwork to be internally lined spiral seam pipe
■ Air devices & dampers as per plans
■ Insulation of ductwork and refrigerant piping as per plans
■ Condensate and refrigerant piping as required
■ Fire proofing and fire sealants for HVAC penetrations of rated assemblies
■ Pre-construction check-out, DDC controls, and start-up by Automated Logic
■ Certified Test and Air Balance by NEBB/AABC certified contractor
■ Coordinate with Commissioning Agent and complete commissioning requirements as
specified
Electrical
■ Basic electrical materials and methods
■ Raceways
■ Wire
■ Cable
■ Connectors
■ Outlets
■ Pull and junction boxes
■ Switches and receptacles
■ Panel boards
■ Disconnects
■ Over current protection devices
■ Fuses
23
Round Rock Public Safety Training Facility GMP Cost Estimate
■ Equipment and raceway support systems
■ Switchboards
■ Transient voltage surge suppression
■ Grounding and bonding
■ Transformers
■ Interior lighting
■ Site lighting
■ All structured cabling systems (infrastructure only, no cabling or devices)
■ Fire alarm system (complete)
■ Items specified for fire alarm above and beyond code
■ Security system (infrastructure only, no cabling or devices)
■ Lightning protection system (complete)
■ Backfill and compaction of any underground electrical
■ Electrical service entrance
■ Telephone service entrance
■ Telephone raceway system
■ Electrical identification
■ Wiring devices
■ Supporting devices
■ Cabinets and enclosures as per electrical plan notes
■ Trenching
■ Fire proofing and fire sealants to be provided for electrical penetrations of rated assemblies
■ Warranties and maintenance manuals
■ Coordinate with Commissioning Agent and complete commissioning requirements as
specified
Security Systems
■ Card access and security per Entech
■ (4)ACX5740 access control controller
■ (4) xPBD4 expansion module
■ (26) Card Readers compatible with existing access cards
■ (1) Bio-reader card reader and interface
■ (1)Enclosure for access control controller with surge suppression, low voltage distribution and
lock power distribution.
■ (5) Interior Domed Camera's
■ (6) Exterior Camera's
■ (1) Exterior PTZ Camera
■ (1) 24TB server for up to 30 days of camera storage
■ (lot) Low voltage cable for access control system
■ (lot) Programming of access control controller and surveillance system
AV Systems
■ Audio Video Systems infrastructure per section 27 41 17
■ Audio Video Systems per section 27 41 16
Technology Systems
■ Technology infrastructure and cabling as per specifications
24
Round Rock Public Safety Training Facility GMP Cost Estimate
Firing Range Equipment
Shooting Range Equipment as per Action Target
■ 75' wide, 50yd tactical shooting distance
Heavy Duty Total Containment Trap
■ 3/8" AR500 steel (rifle rated)
■ Dust collection unit(DCU)
■ Auger lead collection system
Side Wall Protection Near Bullet Trap
■ 12' wide x 8' tall wall protection
■ Two (2)walls, front of bullet trap
■ 1/4" AR500 steel
Power-90 Tactical Turning Targets
■ Twenty-four(24) turning targets
• Inverted installation behind final overhead baffle
• Can be individually controlled or in unison
• Lap-top computer with SmartRange operating software
■ Air Command wireless control
• Air compressor and all necessary hardware
Dual Running Man Pro, Track Runner Target System
■ Dual Track runner targets
■ Individually controlled
■ hand-held tablet controller
Tactical Overhead Baffle Package (50 yards)
■ Continual coverage all down range (tactical shooting)
■ Rifle rated 3/8"AR500 steel
■ 1/2" painted plywood fascia
■ Sound absorbent fascia
Complete Factory Installation
Wall Mounted Sound Abatement Material
■ 2" charcoal PEPP
■ Approximately 4,250 square feet total
■ Range wall behind shooters (estimated 10' x 75')
■ Range side walls near shooters (estimated two walls of 10' x 175')
■ All glue and necessary installation equipment
• Factory installation (glued to walls)
Firing Range HVAC Systems
■ R-AMPS0374 by Rushing Air
■ (2)Two - Roof Top Units
■ 100%Treated Fresh Air Units +/- 350-500 Drop or Rise from ambient air temperature
■ Gas Heated -1,800,000 BTU Per RTU
■ Primary Diffuser
• Lag Diffuser- (Patented Live Diffuser)
• Digital Remote Module w/Ambient Controls
■ Factory Roof Curb Adaptors
• Keyed Remote Fire Alarm Terminal - MRT BacNet Protocol
■ (2) Two - FFX Custom Utility Exhaust Systems
• Pre-Staged & MERV 14 Filtration Or HEPA Filtration (99.7% Particulate Capture Rate)
• Custom Double Insulated Duct
25
Round Rock Public Safety Training Facility GMP Cost Estimate
■ Laminar Air Flow To Meet& Surpass OSHA& EPA Guidelines
N Rushing Air Will Schedule & Provide All Equipment Logistics. All City & Local Codes Shall
Apply
■ 1 Year Live Monitoring -5 Year Parts Only Warranty-5 Year Compressor Parts Only-10 Year
Heat Exchanger Warranty-5 Year Labor Warranty
21) One Story
General Description
1,908sf single story shell building, structural CMU, wood trusses, pitched roof with shingles,
aluminum police slider windows
Site Layout, BIM/CAD/As Built Coordination
■ Layout all site work and CAD services for construction
Temporary Power and Lighting
■ Temporary power and lighting
• Construction power
Building Pad
■ Select fill building pad
■ Subgrade prep
Items Excluded in Original RFP
• Field engineering 3 wk
■ Small tools 1 Is
• Ice, water, and cups 7 mo
■ Waste containers 2 ea
• General clean up 10 wk
■ Plan reproduction 1 Is
■ As built drawings 1 Is
• Final clean 1 bldg
Fencing
■ 6' Standard wood fence - 156 If
• Wood swing gates - 2 ea
Ground Cover at Police & Fire Buildings
• Decomposed granite 3,991 sf
■ Artificial Turf including liner, nailer, flex base curb and turf
with infill material 1,833 sf
Building Concrete
Structural concrete 2,117 sf
26
Round Rock Public Safety Training Facility GMP Cost Estimate
Masonry
■ CMU block-Type I and Type II -all natural gray plain
■ Exterior block to have integral waterproofing
■ Mortars as specified
■ Reinforced unit masonry
■ Joint reinforcement
■ Grout
• Bond beams
• Reinforcing steel
• Masonry anchors
■ Weeps
• Control joints
■ Clean down of masonry
Structural Steel
■ Fabricate Steel -Window frame angles - 7 ea
■ Erect frames
Rough Carpentry
• Wood roof trusses
■ Wood roof decking
■ Wood rafters and framing at awning
• Plywood ceilings
■ Miscellaneous wood blocking
■ Attic access panel
Caulking and Flashing
■ Sealant at masonry control joints
• Base Flashing
• Openings flashing
Roofing and Sheet Metal
Furnish and install GAF Timberline HD fiberglass asphalt shingles with matching ridge cap
over a 15 Ib. felt
■ Fabricate and install 24-gauge galvanized eave metal, 16 ga. Fascia and valleys
■ 25 Year Manufacturer's Warranty
■ 2 Year Workmanship Warranty
Doors, Frames & Hardware
• Hollow metal door, frame, hardware 2 ea
• Installation 1 Is
• Handle & Sort Doors, Frames & Hdw. 2 ea
Glazing
Aluminum sliding shutters per elevation on Sheet A821 and details 5/A821 & 10/A821
27
Round Rock Public Safety Training Facility GMP Cost Estimate
Flooring
■ Concrete sealer
Painting
■ Paint& Finish as specified
■ Paint hollow metal frames and doors
Signage
■ Exterior building sign
Fire Extinguishers
■ Fire extinguisher 1 ea
Plumbing
■ Hose bib 1 ea
Electrical
■ Disconnect and panel
■ Outlets
■ Lights
22) One Story with Garage
General Description
■ 1,476 sf single story shell building, structural CMU, wood trusses, pitched roof with shingles,
aluminum police slider windows
Site Layout, BIM/CAD/As Built Coordination
■ Layout all site work and CAD services for construction
Temporary Power and Lighting
■ Temporary power and lighting
■ Construction power
Building Pad
■ Select fill building pad
■ Subgrade prep
28
Round Rock Public Safety Training Facility GMP Cost Estimate
Items Excluded in Original RFP
■ Field engineering 3 wk
■ Small tools 1 Is
■ Ice, water, and cups 7 mo
■ Waste containers 2 ea
• General clean up 10 wk
■ Plan reproduction 1 Is
• As built drawings 1 Is
■ Final clean 1 bldg
Fencing
• 6' Standard galvanized chain link fence - 100 If
• Chain link swing gates -2 ea
Ground Cover at Police &Fire Buildings
■ Decomposed granite 2,457 sf
■ Artificial Turf including liner, nailer, flex base curb and turf
with infill material 3,167 sf
Building Concrete
■ Structural Concrete
Masonry
■ CMU block-Type I and Type II - all natural gray plain
■ Exterior block to have integral waterproofing
■ Mortars as specified
• Reinforced unit masonry
■ Joint reinforcement
■ Grout
■ Bond beams
■ Reinforcing steel
• Masonry anchors
■ Weeps
• Control joints
• Clean down of masonry
Structural Steel
■ Fabricate Steel -Window frame angles - 3 ea
■ Erect frames
Rough Carpentry
■ Wood roof trusses
• Wood roof decking
• Wood rafters and framing at awning
• Plywood ceilings
29
Round Rock Public Safety Training Facility GMP Cost Estimate
■ Miscellaneous wood blocking
■ Attic access panel
Caulking & Flashing
■ Sealant at masonry control joints
■ Base Flashing
■ Openings flashing
Roofing
■ Furnish and install GAF Timberline HD fiberglass asphalt shingles with matching ridge cap
over a 15 Ib. felt
■ Fabricate and install 24-gauge galvanized eave metal, 16 ga. Fascia and valleys
■ 25 Year Manufacturer's Warranty
■ 2 Year Workmanship Warranty
Doors, Frames & Hardware
■ Hollow metal door, frame, hardware 2 ea
■ Installation 1 ea
■ Handle & Sort Doors, Frames & Hdw. 2 ea
Coiling & Overhead Doors
■ Residential garage doors model 170, non-insulated. Factory standard finish. Manual
operated, inside lock, no windows
■ Door#2202A-10'x7'
Glazing
■ Aluminum sliding shutters per elevation on Sheet A821 and details 5/A821 & 10/A821
Flooring
■ Concrete sealer
Painting
■ Paint& Finish as specified
■ Paint hollow metal frames and doors
Signage
■ Exterior building sign
Fire Extinguishers
■ Fire extinguisher 1 ea
30
Round Rock Public Safety Training Facility GMP Cost Estimate
Plumbinq
■ Hose bib
■ Water into building
Electrical
■ Disconnect and panel
■ outlets
■ lights
23) Two Story with Garage
General Description
■ 2,624 sf two story shell building, structural CMU, light gauge floor trusses, wood roof trusses,
pitched roof with shingles, aluminum police slider windows
Site Layout, BIM/CAD/As Built Coordination
■ Layout all site work and CAD services for construction
Temporary Power and Lighting
■ Temporary power and lighting
■ Construction power
Buildinq Pad
■ Select fill building pad
■ Subgrade prep
Items Excluded in Original RFP
■ Field engineering 3 wk
■ Small tools 1 Is
■ Ice, water, and cups 7 mo
■ Waste containers 2 ea
■ General clean up 10 wk
■ Plan reproduction 1 Is
■ As built drawings 1 Is
■ Final clean 1 bldg
Fencinq
■ 6' Standard wood fence - 170 If
■ Wood swing gates -2 ea
31
Round Rock Public Safety Training Facility GMP Cost Estimate
Ground Cover at Police & Fire Buildings
■ Decomposed granite 2,084 sf
• Artificial Turf including liner, nailer,flex base curb and turf
with infill material 1,485 sf
Building Concrete
• Structural Concrete
• Topping slab
Masonry
• CMU block-Type I and Type II -all natural gray plain
■ Exterior block to have integral waterproofing
• Mortars as specified
■ Reinforced unit masonry
■ Joint reinforcement
■ Grout
■ Bond beams
■ Reinforcing steel
■ Masonry anchors
■ Weeps
• Control joints
■ Clean down of masonry
Structural Steel
• Fabricate steel
• Erect steel
• Window frame angles - 9 ea
■ Erect frames
■ Erect floor decking
Rough Carpentry
• Wood roof trusses
■ Wood roof decking
■ Plywood ceilings at 2nd floor
® Miscellaneous wood blocking
■ Residential attic access ladder
Caulking & Flashing
• Sealant at masonry control joints
■ Base Flashing
• Openings flashing
32
Round Rock Public Safety Training Facility GMP Cost Estimate
Roofinq
■ Furnish and install GAF Timberline HD fiberglass asphalt shingles with matching ridge cap
over a 15 Ib. felt
■ Fabricate and install 24-gauge galvanized eave metal, 16 ga. Fascia and valleys
■ 25 Year Manufacturer's Warranty
■ 2 Year Workmanship Warranty
Doors, Frames & Hardware
■ Hollow metal door, frame, hardware 3 ea
■ Installation 1 ea
■ Handle & Sort Doors, Frames & Hdw. 3 ea
Coiling & Overhead Doors
■ Residential garage doors model 170, non-insulated. Factory standard finish. Manual
operated, inside lock, no windows
■ Door#2302A-18'x7'
Glazing
■ Aluminum sliding shutters per elevation on Sheet A821 and details 51A821 & 10/A821
Drywall & Light Gauge Framing
■ Light gauge metal Floor joists with bridging and bracing as required
Flooring
■ Concrete sealer
Painting
■ Paint & Finish as specified
■ Paint hollow metal frames and doors
Signage
■ Exterior building sign
Fire Extinguishers
■ Fire extinguisher 2 ea
Plumbing
■ Hose bib
■ Water into building
33
Round Rock Public Safety Training Facility GMP Cost Estimate
Electrical
• Disconnect and panel
■ outlets
• lights
24) Two Story Zero Lot with Garage
General Description
2,624 sf two story shell building, structural CMU, light gauge floor trusses, wood roof trusses,
pitched roof with shingles, aluminum police slider windows
Site Layout, BIM/CAD/As Built Coordination
■ Layout all site work and CAD services for construction
Temporary Power and Lightinq
• Temporary power and lighting
■ Construction power
Building Pad
■ Select fill building pad
■ Subgrade prep
Items Excluded in Original RFP
• Field engineering 3 wk
■ Small tools 1 Is
■ Ice, water, and cups 7 mo
■ Waste containers 2 ea
■ General clean up 10 wk
■ Plan reproduction 1 Is
• As built drawings 1 Is
• Final clean 1 bldg
Fencing
■ 6' Standard wood fence - 12 If
Wood swing gates - 1 ea
■ Outside wood fence
Ground Cover at Police & Fire Buildings
■ Decomposed granite 1,042 sf
■ Artificial Turf including liner, nailer, flex base curb and turf
with infill material 743 sf
34
Round Rock Public Safety Training Facility GMP Cost Estimate
Building Concrete
■ Structural Concrete
■ Topping slab
Masonry
■ CMU block-Type I and Type II -all natural gray plain
• Exterior block to have integral waterproofing
■ Mortars as specified
■ Reinforced unit masonry
■ Joint reinforcement
■ Grout
■ Bond beams
■ Reinforcing steel
• Masonry anchors
■ Weeps
® Control joints
• Clean down of masonry
Structural Steel
■ Fabricate steel
■ Erect steel
• Window frame angles - 7 ea
■ Erect frames
• Erect floor decking
Rough Carpentry
■ Wood roof trusses
■ Wood roof decking
• Wood rafters and framing at awning
■ Plywood ceilings at 2nd floor
■ Miscellaneous wood blocking
■ Residential attic access ladder
Caulking & Flashing
• Sealant at masonry control joints
• Base Flashing
• Openings flashing
Roofing
■ Furnish and install GAF Timberline HD fiberglass asphalt shingles with matching ridge cap
over a 15 lb. felt
Fabricate and install 24-gauge galvanized eave metal, 16 ga. Fascia and valleys
25 Year Manufacturer's Warranty
2 Year Workmanship Warranty
35
Round Rock Public Safety Training Facility GMP Cost Estimate
Doors, Frames & Hardware
■ Hollow metal door, frame, hardware 2 ea
■ Installation 1 ea
■ Handle & Sort Doors, Frames & Hdw. 2 ea
Coiling & Overhead Doors
■ Residential garage doors model 170, non-insulated. Factory standard finish. Manual
operated, inside lock, no windows
■ Door#2402A-10'x7'
Glazinq
■ Aluminum sliding shutters per elevation on Sheet A821 and details 5/A821 & 10/A821
Drywall & Light Gauge Framing
■ Light gauge metal Floor joists with bridging and bracing as required
Floorinq
■ Concrete sealer
Painting
■ Paint & Finish as specified
■ Paint hollow metal frames and doors
Signage
■ Exterior building sign
Fire Extinguishers
■ Fire extinguisher 2 ea
Plumbing
■ Hose bib
■ Water into building
Electrical
■ Disconnect and panel
■ outlets
■ lights
36
Round Rock Public Safety Training Facility GMP Cost Estimate
25) Two Story Zero Lot with Garage
General Description
■ 2,624 sf two story shell building, structural CMU, light gauge floor trusses, wood roof trusses,
pitched roof with shingles, aluminum police slider windows
Site Layout, BIM/CAD/As Built Coordination
■ Layout all site work and CAD services for construction
Temporary Power and Lighting
• Temporary power and lighting
■ Construction power
Building Pad
• Select fill building pad
■ Subgrade prep
Items Excluded in Original RFP
■ Field engineering 3 wk
• Small tools 1 Is
■ Ice, water, and cups 7 mo
• Waste containers 2 ea
■ General clean up 10 wk
• Plan reproduction 1 Is
■ As built drawings 1 Is
■ Final clean 1 bldg
Fencinq
■ 6' Standard wood fence - 12 If
■ Wood swing gates - 1 ea
■ Outside wood fence
Ground Cover at Police & Fire Buildings
• Decomposed granite 1,042 sf
■ Artificial Turf including liner, nailer, flex base curb and turf
with infill material 743 sf
Building Concrete
• Structural Concrete
• Topping slab
37
Round Rock Public Safety Training Facility GMP Cost Estimate
Masonry
■ CMU block-Type I and Type II -all natural gray plain
■ Exterior block to have integral waterproofing
■ Mortars as specified
■ Reinforced unit masonry
■ Joint reinforcement
■ Grout
■ Bond beams
■ Reinforcing steel
■ Masonry anchors
■ Weeps
• Control joints
■ Clean down of masonry
Structural Steel
• Fabricate steel
■ Erect steel
■ Window frame angles - 7 ea
■ Erect frames
• Erect floor decking
Rough Carpentry
■ Wood roof trusses
■ Wood roof decking
• Wood rafters and framing at awning
■ Plywood ceilings at 2nd floor
■ Miscellaneous wood blocking
■ Residential attic access ladder
Caulking & Flashing
■ Sealant at masonry control joints
■ Base Flashing
• Openings flashing
Roofing
■ Furnish and install GAF Timberline HD fiberglass asphalt shingles with' matching ridge cap
over a 15 Ib. felt
Fabricate and install 24-gauge galvanized eave metal, 16 ga. Fascia and valleys
25 Year Manufacturer's Warranty
2 Year Workmanship Warranty
Doors, Frames & Hardware
■ Hollow metal door, frame, hardware 2 ea
• Installation 1 ea
■ Handle & Sort Doors, Frames & Hdw. 2 ea
38
Round Rock Public Safety Training Facility GMP Cost Estimate
Coilinq & Overhead Doors
■ Residential garage doors model 170, non-insulated. Factory standard finish. Manual
operated, inside lock, no windows
• Door#2502A-10'x7'
Glazing
■ Aluminum sliding shutters per elevation on Sheet A821 and details 5/A821 & 10/A821
Drywall & Light Gauge Framing
■ Light gauge metal Floor joists with bridging and bracing as required
Flooring
■ Concrete sealer
Painting
■ Paint& Finish as specified
■ Paint hollow metal frames and doors
Signage
■ Exterior building sign
Fire Extinguishers
■ Fire extinguisher 2 ea
Plumbing
■ Hose bib
• Water into building
Electrical
• Disconnect and panel
• outlets
■ lights
39
Round Rock Public Safety Training Facility GMP Cost Estimate
26) One Story with Garage
General Description
■ 2,798 sf one story shell building, structural CMU, wood roof trusses, pitched roof with shingles,
aluminum police slider windows
Site Layout, BIM/CAD/As Built Coordination
■ Layout all site work and CAD services for construction
Temporary Power and Lightinq
■ Temporary power and lighting
■ Construction power
Building Pad
■ Select fill building pad
■ Subgrade prep
Items Excluded in Original RFP
■ Field engineering 3 wk
■ Small tools 1 Is
■ Ice, water, and cups 7 mo
■ Waste containers 2 ea
■ General clean up 10 wk
■ Plan reproduction 1 Is
■ As built drawings 1 Is
■ Final clean 1 bldg
Fencinq
■ 6' Standard wood fence - 142 If
■ Wood swing gates - 1 ea
Ground Cover at Police & Fire Buildings
■ Decomposed granite 4,412 sf
■ Artificial Turf including liner, nailer, flex base curb and turf
with infill material 2,922 sf
Building Concrete
■ Structural Concrete
■ Topping slab
40
Round Rock Public Safety Training Facility GMP Cost Estimate
Masonry
■ CMU block-Type I and Type II - all natural gray plain
• Exterior block to have integral waterproofing
■ Mortars as specified
■ Reinforced unit masonry
■ Joint reinforcement
■ Grout
■ Bond beams
■ Reinforcing steel
■ Masonry anchors
• Weeps
■ Control joints
• Clean down of masonry
Structural Steel
■ Window frame angles -7 ea
0 Erect frames
Rough Carpentry
■ Wood roof trusses
■ Wood roof decking
■ Plywood ceilings
■ Miscellaneous wood blocking
■ Residential attic access ladder
Caulking & Flashing
■ Sealant at masonry control joints
■ Base Flashing
■ Openings flashing
Roofinq
■ Furnish and install GAF Timberline HD fiberglass asphalt shingles with matching ridge cap
over a 15 Ib. felt
■ Fabricate and install 24-gauge galvanized eave metal, 16 ga. Fascia and valleys
■ 25 Year Manufacturer's Warranty
■ 2 Year Workmanship Warranty
Doors, Frames & Hardware
■ Hollow metal door, frame, hardware 2 ea
■ Installation 1 ea
• Handle & Sort Doors, Frames & Hdw. 2 ea
41
Round Rock Public Safety Training Facility GMP Cost Estimate
Coilinq & Overhead Doors
■ Residential garage doors model 170, non-insulated. Factory standard finish. Manual
operated, inside lock, no windows
■ Door#2602A-18'x7'
Glazinq
■ Aluminum sliding shutters per elevation on Sheet A821 and details 5/A821 & 10/A821
Floorinq
■ Concrete sealer
Painting
■ Paint & Finish as specified
■ Paint hollow metal frames and doors
Signage
■ Exterior building sign
Fire Extinguishers
■ Fire extinguisher 1 ea
Plumbinq
■ Hose bib
■ Water into building
Electrical
■ Disconnect and panel
■ outlets
■ lights
42
Round Rock Public Safety Training Facility GAAP Cost Estimate
31) Outdoor Classroom & Shared Storage
General Description
■ 5,651 sf one story building, structural CMU, light gauge roof trusses, pitched roof with
shingles, plumbing and HVAC
Site Layout, BIM/CAD/As Built Coordination
■ Layout all site work and CAD services for construction
Temporary Power and Lighting
■ Temporary power and lighting
■ Construction power
Buildinq Pad
■ Select fill building pad
■ Subgrade prep
Items Excluded in Original RFP
• Field engineering 3 wk
■ Small tools 1 Is
■ Ice, water, and cups 5 mo
■ Waste containers 3 ea
■ General clean up 22 wk
■ Plan reproduction 1 Is
• As built drawings 1 Is
■ Final clean 1 bldg
Fencing
■ Interior chain link fencing - 11'4"
Building Concrete
■ Structural Concrete
■ Topping slab
Masonry
■ CMU block-Type I and Type II - all natural gray plain
■ Exterior block to have integral waterproofing
• Mortars as specified
■ Reinforced unit masonry
• Joint reinforcement
■ Grout
• Bond beams
• Reinforcing steel
Masonry anchors
43
Round Rock Public Safety Training Facility GMP Cost Estimate
• Weeps
• Control joints
■ Clean down of masonry
Structural Steel
■ Fabricate steel
■ Erect steel
■ Erect roof deck
Rough Carpentry
• Wood roof decking (over metal trusses by Drywall)
■ Miscellaneous wood blocking
® Fiber cement fascia boards
■ Vented cement fiber soffits at exterior locations
Caulking & Flashing
■ Sealant at masonry control joints
■ Base Flashing
• Openings flashing
Roofing
■ Furnish and install GAF Timberline HD fiberglass asphalt shingles with matching ridge cap
over a 15 Ib. felt
■ Fabricate and install 24-gauge galvanized eave metal, 16 ga. Fascia and valleys
■ 25 Year Manufacturer's Warranty
2 Year Workmanship Warranty
Doors, Frames & Hardware
• Hollow metal door, frame, hardware 6 ea
■ Installation 1 ea
■ Handle & Sort Doors, Frames & Hdw. 6 ea
Coiling & Overhead Doors
■ Insulated coiling doors, Model 627, Factory standard finish, Manual operated
■ Non insulated coiling doors, Model 620, Factory standard finish, Manual operated
■ 1 ea -#3109A- 10'x7'4"
Drywall, Light Gauge Framing & Insulation
Light gauge metal roof trusses with bridging and bracing as required
■ 12" Batt insulation at roof
2" Rigid insulation applied to CMU walls
44
Round Rock Public Safety Training Facility GMP Cost Estimate
Floorin_g
Concrete sealer
Painting
■ Paint & Finish as specified
■ Paint hollow metal frames and doors
Signage
■ Exterior building sign
Equipment
■ Full Size Ice Maker(OFCI) 1 ea
■ Vertical Air Compressor(CFCI) 1 ea
Fire Extinguishers
■ Fire extinguisher 2 ea
Toilet Partitions &Accessories
■ Floor Mounted Overhead Brace Solid Polymer Partitions with Aluminum Continuous Brackets.
Color To Be Selected From Manufacture Standard Full Range Color Selection
■ Wall Mounted Urinal Screen
■ Toilet Accessories as scheduled
Plumbing
■ PVC waste and vent below slab to 5' outside building line
■ Cast Iron waste and vent above slab
■ Copper domestic water
■ Insulation of domestic water
• Fixtures
HVAC
■ Furnish and install two (2) split systems with accessories as per plans
■ Fans as shown and specified
• Ductwork, insulation, condensate and refrigerant piping and all air devices as shown and
specified
Electrical
® Disconnect and panel
• outlets
■ lights
45
Round Rock Public Safety Training Facility GMP Cost Estimate
41) Fire Tower
General Description
■ 3,185 sf 5 story shell building, structural concrete floors and roof, structural CMU, aluminum
plate windows
Site Layout, BIM/CAD/As Built Coordination
■ Layout all site work and CAD services for construction
Temporary Power and Lighting
■ Temporary power and lighting
■ Construction power
Building Pad
■ Select fill building pad
■ Subgrade prep
Items Excluded in Original RFP
■ Field engineering 1 wk
■ Small tools 1 Is
■ Ice, water, and cups 5 mo
■ Waste containers 4 ea
■ General clean up 10 wk
■ Plan reproduction 1 Is
■ As built drawings 1 Is
■ Final clean 6 levels
Building Concrete
■ Slab on grade 1,073 sf
■ 2nd-5th floor structural concrete 3,774 sf
■ Structural concrete roof 743 sf
■ Stair pan 160 ea
■ Landing 10 ea
Masonry
■ CMU block-Type I and Type II -all natural gray plain
■ Refractory fire brick on the floor of level 4
■ Exterior block to have integral waterproofing
■ Mortars as specified
■ Reinforced unit masonry
■ Joint reinforcement
■ Grout
■ Bond beams
■ Reinforcing steel
■ Masonry anchors
46
Round Rock Public Safety Training Facility GMP Cost Estimate
■ Weeps
■ Control joints
■ Clean down of masonry
Structural Steel
■ Fabricate steel
■ Erect steel
■ Additional steel at High roof
■ Repelling anchors
■ Stair nosings
Jib Crane
■ Jib Crane
■ FS300DD-14-12C10
■ 1 Ton
■ 460V/3/60 — 120VControl
■ Span: 15 ft.
■ Height Under Boom: 10 ft.
■ Rotational stops to protect building
■ Motorized Rotation at .5 RPM
■ 10 Year Manufacturer's Warranty
■ Hoist Acco Model 2130130 (1 Ton)
■ 61 ft of lift
■ Trolley Speed 36 FPM
■ Lift Speed 27 FP
Rough Carpentry
■ 3/" CDX plywood over metal stud framing (by others) at Stair— 1 -Wall type MS 1
Caulking & Flashing
■ Sealant at masonry control joints
■ Masonry flashing
Roofing &Sheet Metal
■ Fabricate and install 20 gauge galvanized scuppers, conductor boxes, and downspouts
■ Sheet metal roofing
■ Collector boxes and downspouts are priced as galvanized material that will not be painted
Doors, Frames & Hardware
■ Hollow metal door, frame, hardware 25 ea
■ Installation 1 ea
■ HM window frames 5 ea
■, Handle & Sort Doors, Frames & Hdw. 29 ea
47
Round Rock Public Safety Training Facility GIMP Cost Estimate
Coiling & Overhead Doors
• Non Insulated Overhead Door- Model 620 Stormtite Rolling Steel Service Door, Manual
operated, Galy. Guides, bottom bar, brackets, Factory standard finish
■ Door#401 A- 6'x8'
Glazinq
■ Type A aluminum windows with 1/4"fixed aluminum panels
Drywall & Framing
MS.1 Walls at stairs
Flooring
Concrete sealer
Painting
■ Paint & Finish as specified
■ Paint hollow metal frames and doors
® Paint high-temperature-resistant paint as specified on section 09 97 13
Signage
■ Exterior building sign
• Interior stairwell sign
■ Jib crane signage
■ Room signs
1 e
Elevator
• ThyssenKrupp Elevator will furnish the necessary labor and material to install a hoistway
entrance to be used for training purposes only, which is not part of a functioning elevator
■ Scope of work includes:
• Hoistway Door Equipment: tracks & hangers, interlocks & pickups, reel closers
• Hoistway Entrance: frame, 2 speed center opening hoistway doors, sills, sill supports
■ Fixtures: intermediate hall lantern and chime, intermediate hall buttons
Fire Protection
■ 6 Story dry manual stand pipe system for training facility for training purposes only
Plumbinq
■ Roof drain
■ Overflow drain
• Floor drain
48
Round Rock Public Safety Training Facility GMP Cost Estimate
Electrical
■ Disconnect and panel
■ Vandal and waterproof light fixtures
■ Convenience outlets
■ Fire prop circuit
Fire Props
■ Based on fire props by Fireblast
■ Smoke Generation Eqpt.
■ High Temperature Lining Systems
■ Office Fire Desk Prop with File Cabinet Extension Fire
■ Office Exterior Window Fire (Exterior)—2 ea, 2nd floor and 41h floor
■ Interior Class A Training Room
43) Fire Apartment
General Description
■ 4,588 sf two story shell building, structural concrete floors and roof, structural CMU, aluminum
plate windows
Site Layout, BIM/CAD/As Built Coordination
■ Layout all site work and CAD services for construction
Temporary Power and Lighting
■ Temporary power and lighting
■ Construction power
Building Pad
■ Select fill building pad
■ Subgrade prep
Items Excluded in Original RFP
■ Field engineering 1 wk
■ Small tools 1 Is
■ Ice, water, and cups 5 mo
■ Waste containers 4 ea
■ General clean up 10 wk
■ Plan reproduction 1 Is
■ As built drawings 1 Is
■ Final clean 1 bldg
Ground Cover at Police & Fire
■ Decomposed granite 5,896 sf
49
Round Rock Public Safety Training Facility GMP Cost Estimate
Building Concrete
■ Slab on grade 3,304 sf
• 2nd floor structural slab 3,304 sf
Masonry
• CMU block-Type I and Type II - all natural gray plain
• Exterior block to have integral waterproofing
• Mortars as specified
■ Reinforced unit masonry
■ Joint reinforcement
■ Grout
■ Bond beams
■ Reinforcing steel
• Masonry anchors
• Weeps
• Control joints
■ Clean down of masonry
Structural Steel
■ Fabricate steel
■ Erect steel and decking
■ Steel at props
• Stair nosings
Jib Crane
■ Jib Crane
• FS30ODD-14-12C10
■ 1 Ton
• 460V/3/60— 120VControl
■ Span: 15 ft.
■ Height Under Boom: 10 ft.
• Rotational stops to protect building
■ Motorized Rotation at .5 RPM
• 10 Year Manufacturer's Warranty
• Hoist Acco Model 2130130 (1 Ton)
■ 27 ft of lift
• Trolley Speed 36 FPM
• Lift Speed 27 FP
Rough Carpentry
• 3/" CDX plywood over metal stud framing (by others) at Stair— 1 -Wall type MS 1
■ Plywood on hat channels at wall marked MS 2 in Elect. / Prop Equip Room
■ 2x8 Wood rafters and plywood at mansard roof(per structural 1/S112)
■ Ventilated fiber cement soffit board at mansard roof(per8/A812)
• Wood framed Collapsed Floor Structures and Collapsed Roof Structure (at 3 levels in Room
108) 6/A841
■ Unstable floor prop 4/A431
50
Round Rock Public Safety Training Facility GMP Cost Estimate
Flat roof ventilation prop 3/A431 and 9/A&12
Caulking & Flashing
■ Sealant at masonry control joints
■ Masonry flashing
Roofing & Sheet Metal
■ Furnish and install metal roofing with matching ridge cap over a 15 Ib. felt
■ Fabricate and install 24-gauge galvanized eave metal, 16 ga. Fascia and valleys
■ 25 Year Manufacturer's Warranty
■ 2 Year Workmanship Warranty
a Fabricate and install 20 gauge galvanized scuppers, conductor boxes, and downspouts
® Collector boxes and downspouts are priced as galvanized material that will not be painted
Doors, Frames & Hardware
■ Hollow metal door, frame, hardware 31 ea
■ Installation 1 ea
■ HM window frames 8 ea
■ Handle & Sort Doors, Frames & Hdw. 39 ea
Glazing
• Glaze type A HM window frame with '/"fixed aluminum panels
■ Type B aluminum windows with 1/4"fixed aluminum panels
• Glaze type C HM window frame with '/"fixed aluminum panels
■ Glaze sidelights at Doors marked Type - B with '/" Fixed aluminum panels
Drywall & Framing
■ MS.1 Walls at stairs
Flooring
Concrete sealer
Painting
• Paint & Finish as specified
■ Paint hollow metal frames and doors
■ Paint high-temperature-resistant paint as specified on section 09 97 13
Signage
Exterior building sign
Interior stairwell sign
Jib crane signage
Room signs
51
Round Rock Public Safety Training Facility GMP Cost Estimate
Plumbing
■ Roof drain
■ Overflow drain
■ Floor drain
Electrical
■ Disconnect and panel
■ Vandal and waterproof light fixtures
■ Convenience outlets
■ Fire prop circuit
Fire Props
■ Fire props by Fireblast
■ Smoke Generation Eqpt.
■ High Temperature Lining Systems
■ Gas Meter Fire Prop (Exterior)
■ Kitchen Fire Prop with Grease Fire Flare-up
■ Corridor Flashover Prop (208)
■ Electrical Panel Fire Simulator
■ Interior Class A Training Room
Maze panels by GLF (Note. These are the only Maze Panels in the project)
■ 2771-084096 30" Maze Panel 50 ea
■ Maze Panel Dolly 2 ea
■ Custom 48" Maze Panel with built in door 5 ea
44) Fire House
General Description
■ 2,823 sf two story shell building, structural concrete floors and attic, structural CMU, light
gauge roof trusses, pitched roof with shingles and aluminum plate windows
Site Layout, BIM/CAD/As Built Coordination
■ Layout all site work and CAD services for construction
Temporary Power and Lighting
■ Temporary power and lighting
■ Construction power
Building Pad
■ Select fill building pad
■ Subgrade prep
52
Round Rock Public Safety Training Facility GMP Cost Estimate
Items Excluded in Original RFP
• Field engineering 1 wk
■ Small tools 1 Is
■ Ice, water, and cups 5 mo
■ Waste containers 4 ea
■ General clean up 10 wk
■ Plan reproduction 1 Is
■ As built drawings 1 Is
■ Final clean 6 levels
Building Concrete
■ Slab on grade 1,839 sf
■ 2nd floor structural slab 903 sf
■ Attic floor structural slab 903 sf
Masonry
■ CMU block-Type I and Type II -all natural gray plain
■ Exterior block to have integral waterproofing
• Mortars as specified
■ Reinforced unit masonry
■ Joint reinforcement
■ Grout
• Bond beams
■ Reinforcing steel
• Masonry anchors
■ Weeps
• Control joints
• Clean down of masonry
Structural Steel
• Fabricate steel
• Erect steel
■ Erect roof deck
■ Stair nosings
Rough Carpentry
• 1" CDX plywood roof deck (over metal deck and trusses by others)
■ Treated 4x12 wood fascia 3/A811
• Ventilated fiber cement soffit board at mansard roof(per 3/A811)
• Attic Truss prop 2/A524 and 11/A811
■ Wood Roof Vent Prop in the yard of Bldg. 44 (see details 8 and 9 on Sheet Al 32 and detail 1
on Sheet Al 33 in Vol 1-Site, Folder 04B_Architectural Fire. Also House Site Plan Sheet A511
in Volume 4-Fire Village, Folder 04 Archtectural)
53
Round Rock Public Safety Training Facility GMP Cost Estimate
Caulking & Flashing
• Sealant at masonry control joints
■ Masonry flashing '
Roofinq & Sheet Metal
■ Furnish and install GAF Timberline HD fiberglass asphalt shingles with matching ridge cap
over a 15 Ib. felt
Y Fabricate and install 24-gauge galvanized eave metal, 16 ga. Fascia and valleys
■ 25 Year Manufacturer's Warranty
i 2 Year Workmanship Warranty
■ Fabricate and install 20 gauge galvanized scuppers, conductor boxes, and downspouts
Collector boxes and downspouts are priced as galvanized material that will not be painted
Doors, Frames & Hardware
■ Hollow metal door, frame, hardware 13 ea
■ Installation 1 ea
• HM window frames 8 ea
■ Handle & Sort Doors, Frames & Hdw. 21 ea
Coiling &Overhead Doors
■ Non Insulated Overhead Door- Model 620 Stormtite Rolling Steel Service Door, Manual
operated, Galy. Guides, bottom bar, brackets, Factory standard finish
■ Door# 101 A- 6'x8'
Glazing
■ Type A aluminum windows with '/" fixed aluminum panels
Drywall & Framing
■ Light gauge metal roof trusses with bridging and bracing as required
• MS.1 Walls at stairs
Floorinq
Concrete sealer
Paintinq
■ Paint & Finish as specified
■ Paint hollow metal frames and doors
■ Paint high-temperature-resistant paint as specified on section 09 97 13
Signage
• Exterior building sign
■ Interior stairwell sign
■ Room signs
1 e
54
Round Rock Public Safety Training Facility GMP Cost Estimate
Plumbing
■ Roof drain
■ Overflow drain
• Floor drain
Electrical
■ Disconnect and panel
■ Vandal and waterproof light fixtures
■ Convenience outlets
■ Fire prop circuit
Fire Props
■ Fire props by Fireblast
■ Smoke Generation Eqpt.
■ High Temperature Lining Systems
• Kitchen Fire Prop with Ceiling Rollover
• Sofa Fire Prop
■ Garage /Attic Fire Prop
Site Infrastructure
• Infrastructure includes all the site work, utilities, fencing, roads, and site electrical
Erosion Controls
■ Stabilized construction entrance
■ Inlet protection
■ Silt fence
■ Rock berm
■ Concrete washout
■ Sw3p
General Site Work and Excavation
■ Maintenance of Erosion control and tree protection (installed by others)
■ Sawcut
• Demo curb &gutter
• Demolition of structures
■ Remove and dispose of existing fence
■ Miscellaneous site demolition
■ Clearing
• Strip 3" topsoil
■ Excavation
■ Embankment
■ Haul off spoils
■ Backfill curb
■ Respread 4" onsite topsoil
■ Subgrade prep
• Excavation & grading at sidewalks, Astroturf and decomposed granite areas
■ All final grading around buildings, walkways, sidewalks and curbs per site plan
■ General fill parking & buildings
55
Round Rock Public Safety Training Facility GMP Cost Estimate
Rail Car Prop
® Excavation and grading as required
• Railroad ties
■ 8" Ballast
■ Street crossing
■ Steel rails
Building Pads
■ Subgrade preparation at building pads
■ Install building pads using on-site materials
Site Concrete Work
6" Concrete paving
7" Concrete paving
8" Concrete paving
■ Integral curb at paving
• Mow strips
■ Bollards throughout project- Install only
• Transformer pad
■ Monument sign foundations and walls
■ Dumpster pads
■ AC pads
■ Concrete approaches
• CMU wall footings
■ Flagpole bases
■ Light pole bases
■ Sidewalks
• Handicap ramps
■ Propane tank footings, slabs, curbs, etc.
• Concrete work at Fuel Spill area
■ Concrete work at Rail Crossing
■ Perimeter Curbs at Artificial Turf and Decomposed Granite areas
■ Confined Space and Trench Rescue
■ All work associated with the Confined Space and Trench Rescue Area including but not
necessarily limited to excavation, compacted base below footings and slabs, all backfill, all
formwork, concrete and reinforcing, form liners, grate support angles, FRP grating at roof,
perforated PVC drain pipe with filter fabric, and other incidental work at the cast in place
confined space trench, all below grade confined space HDPE piping, precast junction
structures and manholes with lids, all above grade confined space concrete pipe, vertical
fiberglass manhole with cover, cast in place breach walls with galvanized angle frames and
1/4" removable aluminum checker plates, cast in place headwall. Work is shown in Volume
1-Site, Group 04B Architectural (Fire), plan sheets A111, A112, A113, A131,'A132, A133,
A151, A191 and Volume 1-Site, Group 02 Civil, plan sheet C1.09
Water
12" waterline
Fire hydrant assemblies
■ 6" DI FH leads
■ 2"waterline
■ 6" Fire line
■ 3"Waterline
■ Water line to bldgs. 21, 22, 23, 24, 25, 26, 31
■ 2"domestic meter
■ 2" Irrigation meter/ BFP (meter by others)
Remove & replace pavement
56
Round Rock Public Safety Training Facility GMP Cost Estimate
a Remove & replace curb & gutter
■ Tie to waterline in Street
■ 6" Fire demand meter (meter by others)
■ 12" Gate valve
■ 6" Gate valve
■ 3" Gate valve
■ 2" Gate valve
■ Fire line turn-up at Buildings
■ Sleeves
■ Sawcut for Water
■ Trench Safety for Water
C Traffic Control for Water
■ Erosion Control Maintenance Required for this Scope
Y Revegetation for Water
Wastewater
■ 8"Wastewater line
■ 6"Wastewater line
■ Trench drains, 6" lines and building tie-ins for fire/foam recovery at buildings 41, 43 & 44
(C1.06)
■ All work associated with the 20,000 gal and 30,000 gal Grease Interceptor Tanks, including
tanks, excavation, backfill, anchorage, piping, fittings and all other incidental items (C1.09)
• Drain, drain line and trap at Fuel Spill Area
• Wastewater manholes
■ Wastewater separator
• Tie to wastewater WWMH
■ Cleanouts
■ Concrete encasement where shown
■ Sawcut for Wastewater
■ Trench Safety for Wastewater
■ Traffic Control for Wastewater
• Erosion Control Maintenance Required for this Scope
■ Revegetation for Water
Storm System
■ 6" PVC
■ 12" RCP
C 18" RCP
24" RCP
■ 36" RCP
■ 42" RCP
c Downspout connections
■ Remove &replace 15' curb inlet in street
18" Headwall
0 24" Headwall
■ 42" Headwall
■ 5' Curb inlet
v 10' Curb inlet
20' Curb inlet
4' Storm sewer manhole
5' Storm sewer manhole
■ All work associated with the Drafting Tank, including 20,000 gal tank, Excavation, backfill,
anchorage, piping, fittings and all other incidental items (C1.08)
57
Round Rock Public Safety Training Facility GMP Cost Estimate
■ All work associated with the two (2) Stormtrooper Storm water Quality Interceptor tanks
• Sawcut for Storm
■ Trench Safety for Storm
■ Traffic Control for Storm
■ Erosion Control Maintenance Required for this Scope
■ Revegetation for Storm
Miscellaneous
■ Small tools
■ Ice, water, and cups
■ Waste containers
■ General clean up
• Plan reproduction
■ As built drawings
■ Lava Rock at the Fuel Spill Prop
■ 6" curb
■ Cast iron downspout boots at the fire village
Fire Props (Props by Fireblast)
■ Propane System (by Centex Propane)
• Mobile Live Fire Car Trainer Prop (Exterior)
■ Mobile Live Fire Dumpster Prop (Exterior
• Live Fire Running Fuel Spill Prop (Exterior)
58
Round Rock Public Safety Training Facility GMP Cost Estimate
D. Alternates
EVOC —Alternate No. 1
■ Site Work & Excavation
■ Concrete work
■ Storm System
■ Fine grade, hydromulch and re-vegetation
■ Electrical
Swift water Rescue—Alternate No. 2
■ Excavation & Site Work
■ Concrete work
■ Utilities, Storm and Pumping Systems with controls
• Liner& Filter fabric
■ Obstacle Course - Allow the sum of $50,000.00 to demolish the exisisting obstacale couse
and re-construct a new course on-site
■ Electrical
North Parkinq —Alternate No. 3
■ Site Work & Excavation
• Concrete Work
■ Electrical
42) Fire Warehouse (Alternate No. 4)
General Description
7,054 sf two story shell building, structural concrete floors and roof, structural CMU, aluminum
plate windows
Site Layout, BIM/CAD/As Built Coordination
a Layout all site work and CAD services for construction
Temporary Power and Lighting
• Temporary power and lighting
■ Construction power
Building Pad
• Select fill building pad
• Subgrade prep
59
Round Rock Public Safety Training Facility GMP Cost Estimate
Items Excluded in Original RFP
■ Field engineering 1 wk
■ Small tools 1 Is
■ Ice, water, and cups 5 mo
■ Waste containers 4 ea
■ General clean up 10 wk
■ Plan reproduction 1 Is
■ As built drawings 1 Is
■ Final clean 1 bldg
Ground Cover at Police & Fire
■ Decomposed granite 10,491 sf
■ Artificial Turf including liner, nailer, flex base curb and turf
with infill material 5,494 sf
Building Concrete
• Slab on grade 5,037 sf
• 2nd floor 2,959 sf
■ Roof 4,232 sf
Masonry
• CMU block-Type I and Type II -all natural gray plain
® Exterior block to have integral waterproofing
■ Mortars as specified
■ Reinforced unit masonry
■ Joint reinforcement
■ Grout
■ Bond beams
■ Reinforcing steel
• Masonry anchors
■ Weeps
■ Control joints
• Clean down of masonry
Structural Steel
• Fabricate steel
• Erect steel and decking
■ Repelling anchors
■ Stair nosings
Rough Carpentry
■ 3/4" CDX plywood over metal stud framing (by others) at Stair—2—Wall marked MS 1
■ Plywood on hat channels at wall marked MS 2 in Elect. / Prop Equip Room
60
Round Rock Public Safety Training Facility GMP Cost Estimate
Caulking & Flashing
■ Sealant at masonry control joints
■ Masonry flashing
Roofing &Sheet Metal
■ Fabricate and install 20 gauge galvanized scuppers, conductor boxes, and downspouts
■ Skylights -2 ea
Doors, Frames & Hardware
• Hollow metal door, frame, hardware 34 ea
• Installation 1 ea
■ HM window frames 6 ea
■ Handle & Sort Doors, Frames & Hdw. 40 ea
Coiling and Overhead Doors
Y Non Insulated Overhead Door- Model 620 Stormtite Rolling Steel Service Door, Manual
operated, Galy. Guides, bottom bar, brackets, Factory standard finish
■ 2 ea -Dock bumpers equal to B4506-14
Glazing
■ Type A aluminum windows with 1/4" fixed aluminum panels
■ Glaze type C HM sidelight frames with '/"fixed aluminum panels
Drywall & Framing
■ MS.1 Walls at stairs
Flooring
■ Concrete sealer
Painting
■ Paint& Finish as specified
■ Paint hollow metal frames and doors
■ Paint high-temperature-resistant paint as specified on section 09 97 13
Signage
■ Exterior building sign
• Interior stairwell sign
■ Room signs
Fire Protection
Fire Riser
61
Round Rock Public Safety Training Facility GMP Cost Estimate
Plumbinq
■ Roof drain
■ Overflow drain
■ Floor drain
Electrical
■ Disconnect and panel
■ Vandal and waterproof light fixtures
■ Convenience outlets
■ Fire prop circuit
Fire Props
■ Based on fire props by Fireblast
■ Smoke Generation Eqpt.
■ High Temperature Lining Systems
■ Warehouse Storage Rack Fire (101)
■ Dumpster Fire Prop (Exterior)
E. Contingency
A Construction Manager's Contingency of 3.75% is included in this price. This contingency is for
the exclusive use of the Construction Manager to complete the scope of work indicated in the
project Drawings and as described herein, and to account for final development of the Drawings
and Specifications that are consistent with the Contract Documents and reasonably inferable
therefrom. Such further development does not include such things as changes in scope, systems,
kinds and quality of materials,finishes or equipment, all of which, if required, shall be incorporated
by Change Order. In addition, the Contingency may be used for other costs which are properly
reimbursable as Cost of the Work but not the basis for a Change Order. The contingency is not
for use by the Owner to add improvements to the project or to perform work that involves an
increase in the original scope of the project as defined by the documents. Such items added by
the Owner shall be addressed by Change Orders to the Contract. Any amount of the Construction
Manager's Contingency that remains unused by the Contractor at the completion of the project
shall be returned to the Owner in full.
F. Exclusions
■ The following items are not included in our base Cost Estimate:
■ Hazardous material assessment, removal, or abatement
■ Materials testing
■ Site and building permits
■ Plan review fees
■ TAS fees
■ Final survey
■ Sales tax
■ Landscape maintenance
■ Demolition or re-construction of the existing obstacle training course
■ Fire brick flooring except at Building 41
■ "Total Flash" stainless steel system (042200, 2.2, H)was not indicated in drawings
■ Roof cover board (it is shown, but was deleted at DD phase pricing)
62
Round Rock Public Safety Training Facility GMP Cost Estimate
■ Fire pumps
■ Electrical coordination studies
• Any items noted in this scope narrative as "not included" or"not included in price"
G. Schedule
Subject to amendments as allowed by the Contract Documents, the project shall be substantially
completed within 540 calendar days from the date work is allow to commence on site, such date
to be documented by a Notice to Proceed issued by the Owner.
63
Chasco Constructors RRPS-GMP 10-17-16-Exbt A
10/21/2016
SITE AREA:
BASE BUDGET
4e r
31_ �
General Conditions
Site Layout,BIM/CAD/As Built Coordination ?";R
Temporary Power and LightingS
Project Equipment µ
Mock-Up Panel '5,0 p,
Site Work,Utilities,and Site Concrete
Building Pads
Fencecrete Along Mays , �s
Fencin '.
Ground Cover at Police&Fire Buildings _r
Y
Landscaping&Irrigation
Building Concrete 4 £
Tilt Wall Concrete f, x
Masonry
Steel :6 %f
Jib Crane {;
Rough Carpentry
Finish Carpentry and Cabinets
xn
Caulking and Flashing ;
Roofing
Doors,Frames,and Hardware
Coiling Doors .
Storefront Windows and Aluminum Plate"Windows"
Stucco
Drywall and Acoustical
Ceramic Tile
Flooring and Concrete Polishing :
Painting
Signage
Equipment Schedule
Knox Box r•._ � �j
Moveable Panels "
Fire Extinguishers and Cabinets :�70
Toilet Partitions&Accessories5
Operable Partitions
Flagpoles89II
Elevatorx*"
Fire Protection 15
Plumbing
HVAC
Electrical
Fire Props
Security Systems all
Firing Range HVAC
AV Systems ,
Technology Systems
Firing Ran e Equipment
-4if
Subtotal 1
Construction Contingency 3.00%•. r $> 5
Subtotal 2
Builders Risk Insurance � =v ,��€�
Excess Liability Insurance :"•_50....
Subtotal 37$
P&P Bond
Fee 2.50%
Total , :W1 :