CM-2016-1236 - 11/14/2016Page I of 3 Contract Quantity Adjustment/Change Order ��aauNonoce nz�s rev, 01/16 Department: PARD Project Name: Old Settlers Park Improvement Project - Phase 2 Date: 10/17/16 City Project Change Order/Quantity ID Number Adjustment No. #2 Vendor Central Road and Utility 8760 A Research Blvd. #192, Austin, TX 785758 512-989-2602 Company Name Address Phone No. Justification location of the trail was necessary to meet ADA specifications. Additionally, relocating the trail eliminated conflicts caused by grading the �morial tree grove. The trail relocation required significantly more grading. Additional RCP pipes were required to fix the drainage issues ;ociated with the trail. Finally, it was determined that the dumpster pad at Lake Creek Park should be poured at 6" thickness rather than the specified in order to withstand the wear and tear of a garbage truck. 5UMMAKY Original Contract Price: Amount $621,688.50 Change Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): $0.00 Total Contract Price with Quantity Adjustment(s): $621,688.50 Previous Change Order(s): $32,444.00 5% This Change Order: $25,963.00 4% Total Change Order(s) To Date: $58,407.00 9% Adjusted Contract Price [Original Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)]: $680,095.50 Difference between Original and Adjusted Contract Prices: $58,407.00 Original Contract Time: 120 days Time Adjustment by previous Quan. Adj./Change Order: 0 Time Adjustment by this Quan. Adj./Change Order: 0 New Contract Time: 120 days Submitted for Approval Prepared By: 907C` 28Odgr= V 17 Signature Printed Name, Title, Company Dat Approvals f Contractor: � � _kk& coofGG Ip Signature Printed Name, Title, Company Date City Project Manager: - L. LJD£ Alm, PWS n BV. /D j (o _Signature Mayor/City S Printed Name, Title D� % Manager L X10Rw" ! J� /"I G L�! � I!&1 ! '�J' , "/ fl 1 j�j�i tip 1l (% Si9natur4 Printed N me, Title 1 Date Page 2 of'3 -:: Contract Quantity Adjustment/ Change Order RDdt'[r:.. �f( R�IIhD rev,/01/16 Project Name: Old Settlers Park Improvement Project - Phase 2 Quan. Adj./Change Order No.: #2 Change Order Data Project Name: Old Settlers Park Improvement Project - Phase 2 Quan. Adj./Change Order No.: #2 Quantity Adjustment Data Bid Item # Item Description Unit qty. Unit Price Amount Contract Item # Item Description Unit . Qty. Unit Price Amount Contract Time us Adjustment s 1 New 8' Concrete Trail LF 40 $41.00 $1,640.00 0 2 New 5' Concrete Trail LF 144 $35.00 $5,040.00 3 New 5' Concrete Trail along parking lot LF 336 $35.00 $11,760.00 4 Revegetation of previously excavated areas LS 1 $1,100.00 $1,100.00 5 2-18" RCP Pipe with concrete safety end treatments LF 10 $225.00 $2,250.00 6 Dumpster Pad 6" thickness LS 1 $1,125.00 $1,125.00 7 Old to new 8' Concrete Trail LF 72 -$41.00 -$2,952.00 8 Sidewalk additional grading CY 1 400 $15.00 $6,000,00 - - $0.00 $0.00 - $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTALS: $2-5-,963.001 0 Project Name: Old Settlers Park Improvement Project - Phase 2 Quan. Adj./Change Order No.: #2 Quantity Adjustment Data Bid Item # Item Description Unit qty. Unit Price Amount Contract Page 3 of 3 Contract Quantify Adjustment/Change Order ��' ROS!!❑figCK IL::J.i rev, 6l/l6 $0.00 $0.00 $0.00 $0.00 $0.00 0.00 $0.00 0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0,00 $0.00 $0.00 $0,00 $0.00 $0.00 $0,00 $0.00 $0.00 - $0.00 TOTALS: 0,00 0 City of Round Rock ROUND ROCK TEXAS Agenda Item Summary Agenda Number: Title: Consider executing Quantity Adjustment/Change Order No. 2 with Central Road and Utility for the Old Settlers Park Improvement Project Phase 2. Type: City Manager Item Governing Body: City Manager Approval Agenda Date: 11/11/2016 Dept Director: Rick Atkins, Director Cost: $25,963.00 Indexes: 2014 General Obligation Bonds Attachments: LAF - Quantity Adjustment -Change Order #2 w- Central Road and Utility (00366804xA08F8).pdf, Back-up OSP Phase 2.pdf Department: Parks and Recreation Department Text of Legislative File CM -2016-1236 Consider executing Quantity Adjustment/Change Order No. 2 with Central Road and Utility for the Old Settlers Park Improvement Project Phase 2. This item will authorize the City Manager to execute Quantity Adjustment/Change Order No. 2 with Central Road and Utility. Items included in this Change Order include: realigning the trail to meet ADA specifications, additional grading associated with the trail realignment, additional drainage pipe to address areas of washout, and a thicker concrete profile at the dumpster pad for durability. This project includes installation of a looping trail system around Bright Lake, ADA improvements around the Joanne Land Playground, Lakeview and Rabb pavilions, and road realignment and parking improvements at Lake Creek Park. PARD recommends approval of this item. This project is in line with numerous objectives within Strategic Plan Goals 1 -High Value Services. $25,963.00 City of Round Rock Page 1 Printed on 1111012016 Agenda Item Summary Continued (CM -2016-1236) 2014 General Obligations Bonds Department official recommends approval of this item. City of Round Rock Page 2 Printed on 1111012016