Loading...
CM-2015-691 - 2/27/2015City of Round Rock nc qso soot Agenda Item Summary Agenda Number: Title: Consider executing Quantity Adjustment/Change Order No. 1 with CRU, Ltd. for the Oakridge Drive/Creekview Drive Drainage Improvements Project. Type: City Manager Item Governing Body: City Manager Approval Agenda Date: 2/27/2015 Dept Director: Michael Thane, Director of Utilities and Environmental Services Cost: $34,603.70 Indexes: 2014 Drainage Revenue Bonds Attachments: QA-CO#1_CRU_Oakdddge-Creekview_CM2.27.15 Department: Utilities and Environmental Services Text of Legislative File CM -2015-691 In October of 2014, City Council approved a Construction Contract with CRU, Ltd. in the amount of $279,160.10 for the Oakridge Drive/Creekview Drive Drainage Improvements Project. This Quantity Adjustment/Change Order No. 1 reflects the costs associated with necessary field changes made during the construction of this project. Change order items include additional hydromulch, mobilization, and trench gravel, which equal $8,754.50. Quantity adjustments for various items equal an additional $25,849.20. City Staff recommends execution of this Quantity Adjustment/Change Order No.1 in the amount of $34,603.70, which will increase the contract total to $313,763.80. Staff recommends approval. Clyefeaund Rech Pt➢v 1 PfIMW on ]AMOfb LEGAL DEPARTMENT APPROVAL FOR CITY COUNCILICITY MANAGER ACTION Required for Submission of ALL City Council and City Manager Items Oakddge DrivelCua iaw Drive Drainage Department Name: Utilities s Environmental services Project Name: Improvements Project Mgr/Resource: Lance shelleneerger ContractorNendor: CRU, Lm. r—lcouncil Action: ORDINANCE RESOLUTION QCity Manager Approval Attorney Appr< Attorney CMA Wording Consider executing Quantity AdjustmengChenge Order No. 1 with CRU, Ltd, for the Oakddge Drive/Creekview Ddve Drainage Improvements Project. r O:lwdox\SCClnts\0199\14731MISC\00329805.XLS Updated 6/3/08 Contract Quantity Adjustment/Change Order —'MU Department: Ublities and Em drohmental Services Project Oakridge Ddve/Ccekview Dnve Drainage Name: Improvements City Project Total Contract Price with Quantity Adjrrstrnends): ID Number OKCRK Page I of3 Date: 2/17/15 Change Order/Quantity Adjustment No. I Justification All Quantity adjustments Were needed due to existing field conditions not noted in plans. Change orders were deemed necessary by the Project Engineer to complete the project successfully. �nnnhar Original Contra¢ Prim Previous Quantity AdjusnmeM(s): This Quantity Adjusthnent $25,849.20 Total Qu Mfty Adlusment(s): $25,949,20 Total Contract Price with Quantity Adjrrstrnends): (305,009.30 Prevbus Change Order(s): 0.00 This Change Order: $8,754.50 0.03 Total Change Order(s) To Date: $8,754.50 0.03 Adjusted Contract Prire (Original Contract Price Plus Quantity Adjus mt(s) Plus Change Order(s)]: $313,763.80 DMrmm between Original and Adjusted CDrnract Prl e : $34,603.70 Original Contract time: Time Adjustment by previous Quan. Ad)./Change Order: Time ACjusiem by this Qua^. Adj./Charge Oiler:. Naw (bntract Time: g City Project CM -906-1091 IM —/S n Page 2 of J Contract Quantity Adjustment/Change Order eVo Project Name: Oakridge Drive/Creekview Drive Drainage Improvements Quan. Adj./Change Order No.: 1 Chan eOrder Data Item Ar Item Description Unit Qty. Unit price Amount Contract Time Adjustment Da I Hydromulch SY 2809 $0.50 $1,404.50 2 Wheeler Motxlization fwpaving patch IS 1 $4,950.00 $4,950.00 3 Gravel for AC Waterline trench TN 120 ;20.00 ;2,400.00 $0.00 $0.00 $0.a0 $o.oD $0.00 $0.ao $0.00 $ci o. $0.00 o.DD $o.ao $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 0.00 $0.00 T 54.5 Page 3 of3 Contract Quantity Adjustment/Change Order Project Name: Oakridge Drive/Cmekview Drive Drainage Improvements Quan. Adj./Charge Order No.: 1 Ouandtv Adiustment Data etd Item S Item Description Unit Qty. Unit Price Amount Contract Time Adjustment 2 P.C. Concrete Curb & Gutter LF 203 $1260 $2,557.80 5 Surfate Killing SY 28 $19.10 $534.80 6 HMAC Type D,2" Nam. Thickness TN 3 $165.00 —995-00 9 P.C. Curb&Gutter (Exravatlon) LF 203 $12.70 $2,578.10 12 Edge Protection Railing LF 2 $130.00 $260.00 13 New P,C. Concrete Sidewalks, 5'Thlck SF 429.25 $10.00 $4,292.50 30 Corvrete RIP Rap CY 9 $575. 5,175.00 31 Wirgwa I Umestone 8 —ST- 1 .6 380.00 $4,788.00 32 Topsoil —SV-- 174 15.00 ;2,610.00 33 Sodding SY 174 $7.00 $1,218.00 40 Traf6 Sign - Remove 7 Replace EA 3 ;700.00 $2,100.DD 39 Permanent Sol Erosion Control Mat SY -38 $20.00 -$760.00 $0.00 x.00 00 50.00 $0.00 $0.00 $0.00 00 $0.00 $0.55 $0.00 $0.00 $0.00 A 25 849.20 0