CM-2015-694 - 2/27/2015City of Round Rock Roxun"s°aeOr Agenda Item Summary Agenda Number: Title: Consider executing Quality Adjustment/Change Order No. 3 with Fazzone Construction Co. for the Veterans Park Improvements Project. Type: City Manager Item Governing Body: City Manager Approval Agenda Date: 2/27/2015 Dept Director: Rick Atkins, Director Cost: $38,160.00 Indexes: 2007 General Obligation Bonds Attachments: CO#3.pdf, LAF - Veterans Park Improvem QA-CO#3 w-Fazzone Construction Co. - Proj (00329994xA08F8).pdf Department: Parks and Recreation Department Text of Legislative File CM -2015-594 This item will authorize the City to execute CO #3, which would include removing the existing asphalt basketball court and replacing it with a concrete court. The existing court is in poor condition and is a maintenance issue. Concrete courts are easier and more cost effective to maintain. The project includes the demolition of existing park amenities and construction of a new park pavilion, trail segment, rest room building, and site furnishings (picnic tables, grills, benches, and trash receptacles). The Veterans Park Improvement Project is being jointly funded through Parks and Recreation funds, as well as CDBG HUD Entitlement Grants. The project includes the demolition of existing park amenities and construction of a new pedestrian path system, pavilion, and site furnishings. Staff met with the neighborhood twice over the past year to gather input on the park improvement plan. The final plan presented to the neighborhood received positive feedback and the neighborhood was excited to see the redevelopment efforts. Staff recommends approval of this item. ClWalRounER00 Peas1 Pdr d.]/fY 5 LEGAL DEPARTMENT APPROVAL FOR CITY COUNCIUCITY MANAGER ACTION Required for Submission of ALL City Council and City Manager Items Department Name: PARD Project Mgr/Resource: Katie Baker Council Action: ORDINANCE Fxx-lCily Manager Approval Attorney Apprr QAttorney, Project Name: Veterans Park Improvements Contractor/Vendor: Ferzane Con der ctlen Co. RESOLUTION CMA Wording Consider executing Quantity AdjuslmentrChange Order No. 3 with Fazzone Construction Co. for the Veterans Park Improvements Project. Date 0:\wdox\SCClnts\0199\1387-1\MISC\00329994.XLS Updated 6/3/08 N, 1013 Contract Quantity Adjustment/Change Order —nnl %flange Department: PARD Project $0.00 Name: Veteans Park Smprovement Project Date: 2117/15 City Project Change Order/Quantity ID Number PRRPL_VETPK Adjustment No. 3 3ustinmelon Remove e,d4 rg, cracked asphalt basketball court and replacilq svim more durable car¢re[e court to mcet current park sandartls Original ContraU Price: Previous Quantity Adjudbnent(s): Thiz Quanmy AOlustrnenC TCAM Qvanmy Ad)usimenl(s): I Oral Contract Rice with Quandt, Adjtetment(s): Previous change Omer(s) This Change Order: Total Change Orders) To Date: Ad)0sted Cpnuact Price IOrglnal Contract Pree Plus Quendry Aajuunends) Plus Change ONer(s)): DJrwence between Original and Adjusted Conrad Prices: Orpinal Contract Time: Tme Adjustment by previous Quan. klj./Change Omer: Time kjustment by Nk Quan. MJ.JChznge Order: Hew Centr. Time: Submitted for Approval Amount %flange 5309,739.50 $0.00 $O.DD $309,719.50 $9,477.40 0.03 $38,160.00 0.13 $47,637.40 0.16 $352,351.90 $47,637.90 120 days 52 days 25 days 197 days Prepared By: FAtt' � KAnE StaGF.K k DfiV c IAL a (ARR— Z 17 tali S1g,aNre Printed Name, Title, Company Date Approvals CondaM% ^ .... iA.� fI%-L'i'.G �.F.st�/, d--��'- %S Sgnatme Printed Name, Title, Company Date Ckk - ao1S- lAL4 Pape? n13 Contract Quantity Adjustment/Change Order k. nur Project Name: Veterans Park Improvement Project Qnan. Adj./Change Order No.: 3 Change Order Data esc Item # Item Dri Ugn unit Qty. UnPrice Amount Contac Time Adjustment s 1 Repladng basketball court surfacing L.S. 1 $38,160.00 $30,160.00 $0.00 $0.00 s0A0 $0.00 $O.00 $0.oO $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $O.ODII $0.00 $0.00 sa.oO $O.oO P.P+ 3 ofl .. Contract Quantity Adjustment/Change Order R..nun Project Name: Veterans Park improvement Pmjed Quan. Adj./Change Order M.: 3 ouomtro