O-78-533 - 3/30/1978ORDINANCE NO,
ORDINANCE BY THE CITY COUNCIL OF THE CITY
OF ROUND ROCK, TEXAS, APPROVING THE APPLI-
CATION DATE FOR F.C.C. CERTIFICATION AND
THE CONSTRUCTION AND OPERATION SCHEDULE OF
STOKES CABLE CO., INC.; REPEALING PARTS OF
ORDINANCES IN CONFLICT HEREWITH.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF ROUND ROCK, TEXAS:
Section 1: That the application date for F.C,C. certifica-
tion and the schedule for construction and operation of the cable
TV system of Stokes Cable Co., Inc., a copy of which is attached
hereto and marked Exhibit A, and made a part of this Ordinance,
is hereby accepted and confirmed.
Section 2: All parts of Ordinances in conflict with the
provisions of this Ordinance are to the extent of such conflict
hereby repealed, otherwise such Ordinances shall remain in full
force and effect.
(Nark through the following alternative that is not applicable)
Alternative 1.
By motion duly made, seconded and passed with an affirmative
vote of all the Council members present, the requirement for
reading this ordinance on two separate days was dispensed with.
READ, PASSED, and ADOPTED on first reading this 30 day
of PtatelLi , 1978.
READ �b and�-� OWED on first ref ding this the day of
Alternative 2.
, 19
READ ,„A'PI1OVED and ADOPTED on second readin
ST:
1978.
the
AY . IT 4 , -Mayor
City of Round Rock, Texas
JOJ NNE LAND,
y Secretary
March 1978
EXHIBIT A
PLAN OF ACTION •
ROUND ROCK, TEXAS
cabie
Meet with Round Rock City Council; present
Plan of Action, receive approval of new
ordinance.
April 1978 Submit certificate of compliance application
documents to Washington attorney for filing.
May 1978
Completion of filing for certificate of
compliance. (It is estimated that the normal
expectancy of certificate approval is six
months minimum, depending upon protest factors,
etc.)
Fall 1978 Begin satellite ground receiving station
coordination engineering surveys.
Fall 1978
February 1979
1st Quarter 1979
2nd Quarter 1979
3rd Quarter 1979
4th Quarter 1979
4th Quarter 1979
Initial strand mapping process.
Completion of final system cash flow projections.
Completion of system construction bids.
Completion of system financial arrangements.
Begin construction.
Completion of construction.
Turn -on date; begin operation.
During the period between April 1978 and 3rd Quarter of 1979 there will
be many other major and minor events occurring. Items such as: office site
selection, ordering of tower, antennas, satellite earth station, personnel
contd.
4300A WEST WACO DRIVE • P. 0. BOX 7052 • WACO, TEXAS 76710 • 817-776-1141
• plan`'of Action Contd.
' a g e 7A .
hiring and training, utility pole permit applications, and make ready arrangements,
marketing and advertising plans, etc. The list goes on and on, but the major
developmental stages are the "key" denominations in reaching our goals.
Cablevision looks forward in beginning this new and exciting project and
hopes to become an important and respected corporate citizen of .Round Rock, Texas.